ANALISIS FAKTOR- FAKTOR RISIKO TAHAP PENAWARAN TERHADAP KINERJA PROYEK (STUDI KASUS PEKERJAAN KONSTRUKSI RAWA DI PROVINSI ACEH)

Ukuran: px
Mulai penontonan dengan halaman:

Download "ANALISIS FAKTOR- FAKTOR RISIKO TAHAP PENAWARAN TERHADAP KINERJA PROYEK (STUDI KASUS PEKERJAAN KONSTRUKSI RAWA DI PROVINSI ACEH)"

Transkripsi

1 ISSN Pascasarjana Universitas Syiah Kuala 8 Pages pp ANALISIS FAKTOR- FAKTOR RISIKO TAHAP PENAWARAN TERHADAP KINERJA PROYEK (STUDI KASUS PEKERJAAN KONSTRUKSI RAWA DI PROVINSI ACEH) Roni Saputra 1, Eldina Fatimah 2 nurisra 2 1) Magister Teknik Sipil Banda Aceh 2) Fakultas Teknik Universitas Syiah Kuala Abstract: Construction business shows increasing competition for auctioned jobs. In bidding stage, evaluation of the impact and frequency of the risk often received less attention from contractors. The objective of this research was to find out risk factors affecting the bidding process that can influence the performance of construction project. Object of the research were contractors who carried out swamp construction project in Aceh province funded with state budget of 2010 and 2011 by public tender procurement system. Data collected in this research were primary data in the form of questionnaires filled out by contractors and secondary data obtained from Center of Sumatra River Region I (Balai Wilayah Sungai Sumatra I). Data processing was conducted by validity test, reliability analysis, mean analysis, frequency index (FI) analysis, severity index analysis (SI), and important index analysis (II). Based on important index calculation, the most 10 influencing risk factors were obtained due to high frequency of occurrence and high level of the impact. Based on factors beyond the control of the contactor they were: 1) Condition and environment of the project do not work as expected at the time of the preparation of bidding, 2)Weather changes on project site, 3) Lack of transportation to the project site, 4) the number of bidders, 5) the availability of work in relation to economic and political conditions. Based on factors under the control of contractors they were: 1) procurement implemented was e-procurement, 2) financing of projects that are not well planned, 3) the need for job, 4) work experience with similar projects, 5) current workload (the project being handled). By analyzing aforementioned risk factors, the contractors can avoid cost overrun of the fees that have been calculated at the time of bidding, by adding overhead cost in addition to taxes and benefits on the total costs of bidding. Keywords: risk factors, bidding, project performance, swamp Abstrak: Bisnis konstruksi menunjukkan persaingan yang semakin ketat untuk memperoleh pekerjaan yang dilelang. Pada tahap penawaran, sering sekali evalusi dampak dan frekuensi risiko kurang mendapat perhatian dari kontraktor. Penelitian ini ditujukan untuk mengetahui faktor-faktor risiko yang berpengaruh pada proses penawaran yang dapat mempengaruhi kinerja proyek konstruksi. Pada penelitian ini yang menjadi objek penelitian adalah kontraktor yang melaksanakan pekerjaan konstruksi rawa di Provinsi Aceh yang bersumber dana APBN pada Tahun 2010 dan 2011 dengan sistem pengadaan secara pelelangan umum. Data yang dikumpulkan dalam penelitian ini adalah data primer berupa kuisioner yang diisi oleh kontraktor dan data sekunder yang diperoleh dari Balai Wilayah Sungai Sumatera-I. Pengolahan data dilakukan dengan uji validitas, analisis reliabilitas, analisis mean, analisis Frequency Index (FI), analisis Severity Index (SI) dan analisis Importance Index (II). Berdasarkan hasil perhitungan II didapat 10 (sepuluh) faktor-faktor risiko yang paling berpengaruh karena memiliki frekuensi kejadian sangat sering dan dampak tingkat pengaruh sangat tinggi. Berdasarkan faktor diluar kendali kontraktor yaitu : 1) Kondisi dan lingkungan pekerjaan tidak sesuai dengan perkiraan pada saat penyusunan penawaran, 2) Perubahan cuaca pada lokasi proyek, 3) Sulitnya transportasi ke lokasi proyek, 4) Jumlah peserta tender, 5) Ketersediaan pekerjaan sehubungan dengan kondisi perekonomian dan politik. Berdasarkan faktor dibawah kendali kontraktor yaitu : 1) Pengadaan yang dilaksanakan secara E-Procurement, 2) Pendanaan kegiatan proyek yang tidak terencana dengan baik, 3) Kebutuhan akan pekerjaan, 4) Pengalaman proyek dengan pekerjaan sejenis, 5) Beban kerja saat ini (proyek yang sedang ditangani). Dengan menganalisis faktor risiko tersebut di atas kontraktor dapat terhindar dari beban biaya tambahan (cost overrun) dari biaya yang telah dihitung pada saat penawaran, dengan cara menambah biaya tak terduga (overhead) selain pajak dan keuntungan pada total biaya penawaran. Kata Kunci : faktor risiko, penawaran, kinerja proyek, rawa Volume 1, No. 2, November

2 Pascasarjana Universitas Syiah Kuala Proses pelelangan sampai dengan selesainya pekerjaan konstruksi dapat terjadi hal yang tidak terduga terkait dengan faktor-faktor risiko, sehingga kontraktor harus dapat mempertahankan kinerja yang baik agar dapat bersaing dengan kontraktor lain untuk memperoleh pekerjaan konstruksi. Berdasarkan pendapat dan pengalaman, kontraktor memperkirakan risiko tersebut, namun tidak dilakukan evaluasi frekuensi dan dampak risiko secara sistematis terhadap kinerja proyek. Metode yang digunakan dalam penelitian ini adalah bersifat diskriptif analitis yaitu mengumpulkan data proyek-proyek konstruksi rawa yang telah dilaksanakan. Data yang digunakan dalam penelitian ini adalah data primer dan data sekunder. Ruang lingkup penelitian ini dibatasi pada risiko yang disebabkan oleh faktor-faktor diluar kendali kontraktor dan faktor-faktor dibawah kendali kontraktor, sedangkan risiko yang disebabkan oleh tindakan kelalaian, atau kesalahan kontraktor (Non-Excusable Delay) tidak diperhitungkan dalam penelitian ini. Pada penelitian ini yang menjadi objek penelitian adalah kontraktor yang melaksanakan pekerjaan konstruksi rawa di Provinsi Aceh yang bersumber dana APBN pada Tahun Anggaran 2010 dan 2011 dengan sistem pengadaan secara pelelangan umum. Hasil dari penelitian dapat memberikan informasi kepada kontraktor dalam menganalisis faktor-faktor risiko pada tahap penawaran yang paling berpengaruh yang perlu diperhatikan karena memiliki frekuensi kejadian sangat sering dan dampak tingkat pengaruh sangat tinggi. METODE PENELITIAN Metode pengumpulan data, pengolahan data, pengujian data dan analisis data sebagaimana dirumuskan pada bagan alir metode penelitian Gambar 1. Data Primer : Data Kuisioner Tidak Gambar 1 Bagan alir Penelitian Mulai Identifikasi dan Perumusan Masalah Studi Literatur Pengumpulan Data Data Sekunder : Data nama proyek, nilai proyek, nama kontraktor Pengolahan Data Uji Reliabilitas dan Validitas Sumber dan Pengumpulan Data Ya Analisa Mean Analisis Frequency Index (FI) Analisis Severity Index (SI) Analisis Importance Index (II) Hasil dan Pembahasan Selesai Sumber data dalam penelitian ini berupa data primer diperoleh dari lembaran kuisioner yang disebarkan kepada responden seperti manajer proyek atau top manajemen dan data sekunder diperoleh dari Balai Wilayah Sungai Sumatera-I Provinsi Aceh. Kuisioner bersifat tertutup, yaitu responden memilih salah satu pertanyaan yang telah disediakan bersifat multiplechoice dengan skala yang digunakan adalah skala likert. Adapun jawaban responden diukur berdasarkan skala likert dengan menggunakan skor 1 (satu) sampai 5 (lima). Volume 1, No. 2, November

3 Penyebaran dan pengumpulan kuisioner dilakukan dalam waktu 2 (dua) minggu, yaitu mulai tanggal 15 Agustus s/d 31 Agustus Pengolahan Data Setelah seluruh kuisioner yang telah diisi oleh responden terkumpul, kemudian kuesioner dikuantitatifkan sehingga menghasilkan keluaran berupa angka yang selanjutnya dilakukan uji validitas, analisis reliabilitas, analisis mean, analisis frequency index, analisis severity index dan analisis importance index, dengan menggunakan alat bantu seperangkat komputer dengan software SPSS (Statistical Product dan Service Solution) dan Microsoft Excel. TINJAUAN PUSTAKA Kegiatan Proyek Konstruksi Rawa Proyek konstruksi rawa adalah mereklamasi daerah rawa dengan suatu sistem jaringan drainase dan tata guna air yang bertujuan antara lain untuk pengembangan wilayah dan meningkatkan hasil produksi pertanian terutama pangan (Peraturan Pemerintah Republik Indonesia 1991, Tentang Rawa No. 27). Pengertian Risiko Risiko pada pekerjaan konstruksi adalah suatu kondisi yang mungkin terjadi karena ketidakpastian kejadian yang akan menimbulkan konsekuensi fisik dan finansial yang menyebabkan tidak tercapainya sasaran kinerja proyek yaitu : kinerja biaya, kinerja waktu dan kinerja mutu (Gray, dan Larson, 2000). Kinerja Proyek Kinerja proyek adalah membandingkan antara realisasi pekerjaaan yang telah dilaksanakan dengan rencana pekerjaan pada kontrak yang telah disepakati oleh pemilik proyek dan kontraktor (Kuncoro, A 1999) Faktor Risiko yang Mempengaruhi Kinerja Proyek Identifikasi faktor-faktor risiko yang mempengaruhi pengambilan keputusan pada tahap penawaran dan mempengaruhi pelaksanaan konstruksi, selanjutnya dibuat suatu model analisis sumber risiko dalam proses penawaran terhadap kinerja proyek (Elbab A, 2001:42) dapat dijelaskan seperti Gambar 2. Environment Pra-Kontrak Faktor Internal (controllable factors) Faktor Eksternal (uncontrollable factors) Gambar 2 Model Analisis Sumber Risiko Tahap Penawaran (Elbab, A 2001) Analisis Statistik Uji validitas Arikunto, S (2010:211) mendefinisikan bahwa suatu instrumen dikatakan valid apabila mampu mengukur dan mengungkap data dari variable yang diteliti secara tepat. Untuk menguji validitas dihitung dengan menggunakan rumus teknik correlation product moment dimana nilai Corrected item total correlation harus lebih besar dari r table (r hitung > r table). Risk and Decision Proses penawaran dan analisis risiko Proses pelaksanaan konstruksi Consequences Kinerja proyek Input Process Output Volume 1, No.2, November

4 Analisis reliabilitas Reliabilitas menunjukan suatu pengertian bahwa suatu instrument cukup dapat dipercaya dan diandalkan, dengan menggunakan analisis Cornbach Alpha, Suatu kuisioner dianggap andal apabila koefisien Alpha lebih besar atau sama dengan 0,6 (Arikunto S, 2010:221). Analisis Frequency Index (FI) Analisis Frequency Index (FI) menghasilkan indeks frekuensi terjadinya dari faktor-faktor risiko yang mempengaruhi kinerja kontraktor pada proyek konstruksi rawa di Provinsi Aceh. Untuk menghitung Analisis Frequency Index digunakan rumus pada persamaan (Berstein dan Bernstein, 1999 dikutip dari Long, dkk, 2008 : 369) sebagai berikut : FI = 5 i 1 ai. ni 5N. (1) dimana : i = Indeks kategori respon(1,2,3,4dan 5). a i = Bobot yang dihubungkan dengan nilai respon ke-i (1,2,3,4,5 secara berurutan). n i = Frekuensi dari respon ke-i sebagai persentase dari total responden untuk setiap faktor. N = Total jumlah responden. Analisis Severity Index (SI) Analisis Severity Index (SI) menghasilkan indeks dampak tingkat pengaruh dari faktor-faktor risiko yang mempengaruhi kinerja kontraktor pada proyek konstruksi rawa di Provinsi Aceh. Untuk menghitung Analisis Severity Index digunakan rumus pada persamaan (Berstein dan Bernstein, 1999 dikutip dari Long, dkk, 2008 : 369) sebagai berikut : SI = ai. ni 1.. (2) 5N i 5 dimana : i = Indeks kategori respon(1,2,3,4dan 5). a i = Bobot yang dihubungkan dengan nilai respon ke-i (1,2,3,4,5 secara berurutan). n i = Frekuensi dari respon ke-i sebagai persentase dari total responden untuk setiap faktor. N = Total jumlah responden. Analisis Importance Index (II) Analisis Importance Index (II) menunjukan faktor risiko yang paling mempengaruhi kinerja kontraktor pada proyek konstruksi rawa di Provinsi Aceh. Untuk menghitung Analisis Importance Index digunakan rumus pada persamaan (Berstein dan Bernstein, 1999 dikutip dari Long, dkk, 2008 : 369) sebagai berikut II = FIxSI...(3) dimana : FI = Frequency Index. SI = Severity Index. HASIL PEMBAHASAN Uji Validitas Berdasarkan hasil Statistical Product and Service Solution (SPSS) dapat dilihat bahwa untuk item pernyataan variabel faktor diluar kendali kontraktor (uncontrolable factors) memperoleh nilai r hitung berkisar antara 0,537 0,972 > r table = 0,344, yang dapat disimpulkan bahwa untuk item pernyataan 39 - Volume 1, No. 2, November 2012

5 faktor diluar kendali kontraktor seluruhnya dinyatakan valid. Untuk item pernyataan variabel faktor dibawah kendali kontraktor (controlable factors) memperoleh nilai r hitung berkisar antara > r table = 0,344, dengan demikian seluruh item pernyataan variabel faktor dibawah kendali kontraktor dinyatakan valid. Uji Reliabilitas Berdasarkan analisis reliabilitas dapat diketahui bahwa alpha untuk masing-masing variabel yaitu variabel faktor diluar kendali kontraktor (uncontrolable factors) diperoleh nilai alpha sebesar 0,950, alpha > 0,60 yang berarti variabel tersebut dinyatakan handal dan variabel faktor dibawah kendali kontraktor (controlable factors) diperoleh nilai alpha sebesar 0,971, alpha > 0,60 dengan demikian variabel faktor tersebut dinyatakan handal. Analisis Importance Index (II) Hasil perhitungan Importance Index (II) dari faktor-faktor risiko tahap penawaran diluar kendali kontraktor dan faktor dibawah kendali kontraktor terhadap kinerja proyek berdasarkan frekuensi kejadian dan dampak tingkat pengaruh dapat dilihat pada tabel 1 dan 2. Tabel 1 Hasil perhitungan Importance Index (II) dari faktor-faktor risiko tahap penawaran diluar kendali kontraktor. Pe ring kat 1 Faktor Risiko Kondisi dan lingkungan pekerjaan tidak sesuai dengan perkiraan pada saat penyusunan penawaran. II 0,863 2 Perubahan cuaca pada lokasi proyek. 0,758 3 Sulitnya transportasi ke lokasi proyek. 0,744 4 Jumlah pesaing/peserta tender. 0,744 5 Ketersediaan pekerjaan sehubungan dengan kondisi perekonomian & politik. 0,722 6 Perubahan kebijakan pemerintah (pajak, peraturan dan ekonomi). 0,663 7 Inflasi. 0,540 8 Perubahan nilai tukar mata uang. 0,535 9 Pemogokan tenaga kerja. 0, Terjadinya kerusakan/pengrusakan akibat kelalaian atau perbuatan pihak ketiga. 0,465 Tabel 2 Hasil perhitungan Importance Index (II) dari faktor-faktor risiko tahap penawaran dibawah kendali kontraktor. Pe ring kat 1 2 Faktor Risiko Pengadaan Barang/Jasa yang dilaksanakan secara elektronik at (E-Procurement) Pendanaan kegiatan proyek yang tidak terencana dengan baik. II 0,795 0,788 3 Kebutuhan akan pekerjaan 0,784 4 Pengalaman proyek dengan pekerjaan sejenis 0,780 5 Beban kerja saat ini (proyek yang sedang ditangani) 0,736 6 Jenis dan jumlah peralatan yang diperlukan atau yang tersedia 0,713 7 Kesesuaian pemilihan metode konstruksi 0,681 8 Jenis dan jumlah tenaga pengawas/pelaksana yang diperlukan atau yang tersedia 0,674 9 Jangka waktu proses pelaksanaan proyek 0, Ketersediaan dana dan kondisi financial 0, Jenis dan jumlah tenaga kerja yang diperlukan atau yang tersedia 0, Keterlibatan owner dalam proyek 0, Tingkat kesulitan proyek yang dinyatakan dengan penggunaan teknologi/inovasi teknologi. 0, Pembahasan Reputasi dan profesionalisme pihak-pihak yang terkait Jangka waktu proses penawaran yang diberikan Beban general overhead kantor pusat. 0,490 0,464 0,396 Sepuluh faktor-faktor risiko pada tahap penawaran yang paling berpengaruh terhadap kinerja proyek yang perlu diperhatikan, karena memiliki frekuensi kejadian sangat sering dan dampak tingkat pengaruh sangat tinggi adalah sebagai berikut : Volume 1, No.2, November

6 Kondisi dan lingkungan pekerjaan tidak sesuai dengan perkiraan pada saat penyusunan penawaran. Pada saat penyusunan penawaran kontraktor mengasumsikan kondisi dan lingkungan pekerjaan rawa dalam katagori kondisi medan ringan, sedangkan kenyataan yang ada sebagian besar daerah rawa pada kondisi katagori medan berat yang akan mempengaruhi dalam perhitungan harga satuan alat berat dan waktu pelaksanaan pekerjaan, hal disebabkan kontraktor tidak memahami kondisi dan lingkungan daerah rawa. Untuk menghindari hal tersebut di atas kontraktor harus mengikuti atau meminta panitia lelang melakukan peninjauan lapangan (aanwijzing lapangan) pada saat proses lelang. Perubahan cuaca pada lokasi proyek. Pekerjaan konstruksi rawa di Provinsi Aceh dominan berada pada daerah pantai barat (Aceh Jaya, Aceh Barat, Nagan Raya, Aceh Selatan dan Singkil), daerah ini memiliki tingkat perubahan cuaca yang cukup tinggi, perubahan cuaca seperti angin kencang dan curah hujan yang tinggi dapat menyebabkan penambahan biaya dan keterlambatan pekerjaan yang mempengaruhi kinerja proyek. Dalam menyusun penawaran kontraktor harus menghitung waktu efektif pelaksanaan pekerjaan akibat adanya perubahan cuaca pada saat pelaksanaan pekerjaan dan membandingkan jangka waktu pelaksanaan yang ditetapkan dalam dokumen lelang. Sulitnya transportasi ke lokasi proyek. Pada umumnya pekerjaan konstruksi rawa berada pada daerah terpencil yang sarana transportasi ke lokasi pekerjaan masih dalam kondisi sulit dan belum memadai, bahkan ada yang harus ditempuh melalui jalur sungai, hal ini dapat menyebabkan minimnya ketersedian material dan menambah biaya mobilitas dari bahan material tersebut. Pada tahap penyusunan penawaran kontraktor harus mencari informai terkait ketersedian material dan menambahkan biaya mobilitas dalam biaya bahan material. Jumlah pesaing/peserta tender. Akibat terlalu banyak peserta yang mengikuti pelelangan pada paket pekerjaan konstruksi rawa, dapat meningkatkan persaingan antar peserta, untuk memenangkan persaingan kontraktor memberikan harga penawaran yang terlalu rendah yaitu < 60% dari harga Owner Estimate (OE) yang akan berpengaruh terhadap kinerja proyek. Sebaiknya kontraktor menawarkan harga yang wajar berdasarkan perhitungan harga yang profesional. Ketersediaan pekerjaan sehubungan dengan kondisi perekonomian dan politik. Sedikitnya jumlah paket yang dilelangkan akibat kondisi perekonomian dan politik, dapat menyebabkan persaingan yang tidak sehat pada saat penawaran. Dokumen penawaran yang diajukan tidak memperhitungkan risiko, hanya semata-mata untuk memenangkan persaingan. Hal ini nantinya dalam pelaksanaan pekerjaan akan mempengaruhi kinerja proyek Volume 1, No. 2, November 2012

7 Seharusnya kontraktor mempelajari dokumen lelang dan menyusun penawaran yang responsible. Pengadaan Barang/Jasa yang dilaksanakan secara E-Procurement. Pengadaan Barang/Jasa yang dilaksanakan dengan menggunakan teknologi informasi dan transaksi elektronik (E-Procurement) menyebabkan terbatasnya informasi dan komunikasi, sebaiknya kontraktor mempersiapkan sumber daya manusia dan peralatan dalam mengikuti pengadaan barang/jasa yang dilaksanakan secara E- Procurement. Pendanaan kegiatan proyek yang tidak terencana dengan baik. Pada saat penawaran kontraktor tidak merencanakan dan mehitungkan harga penawaran secara akurat, harga satuan pekerjaan yang ditawarkan lebih rendah dari harga pasar pada lokasi pekerjaan. Sebaiknya kontraktor melakukan survey harga pasar sebelum menghitung harga penawaran. Pengalaman proyek dengan pekerjaan sejenis Pada dokumen lelang untuk kualifikasi usaha kecil, pengalaman perusahaan hanya disyaratkan memiliki pengalaman pada bidang sipil, sehingga perusahaan yang belum pernah mengerjakan pekerjaan konstruksi rawa (pekerjaan sejenis) dapat mengikuti dan memenangkan pelelangan. Dengan mengikuti pelelangan sesuai pekerjaan sejenis, kontraktor dapat memprediksi faktor-faktor risiko sesuai jenis pekerjaan pada saat penyusunan penawaran. Beban kerja saat ini (proyek yang sedang ditangani) Pada saat akan mengikuti suatu pelelangan kontraktor harus memperhitungkan beban kerja saat ini (proyek yang sedang ditangani), karena kemanpuan menangani paket pada saat bersamaan ditentukan sebagai berikut : SKP = (1,2 N) jumlah paket yang sedang ditangani, dimana : SKP= Sisa Kemampuan Paket, N = Jumlah paket pekerjaan terbanyak yang dapat ditangani pada saat bersamaan selama kurun waktu 5 (lima) tahun terakhir. Kebutuhan akan pekerjaan Akibat dari kebutuhan akan pekerjaan seringkali kontraktor tidak menganalisi faktorfaktor risiko pada tahap penawaran suatu pekerjaan, sehingga memberikan penawaran terlalu rendah yaitu < 60% dari harga Owner Estimate (OE) yang berpotensi mendapat kerugian. SIMPULAN DAN SARAN Simpulan Faktor-faktor risiko diluar kendali kontraktor (uncontrolable factors) dan dibawah kendali kontraktor (controlable factors) pada tahap penawaran secara simultan berpengaruh terhadap kinerja proyek. Analisis faktor-faktor risiko pada tahap penawaran sangat penting bagi kontraktor untuk menghindari beban biaya tambahan (cost overrun) Volume 1, No.2, November

8 dari biaya yang telah dihitung pada saat penawaran dengan cara menambah biaya tak terduga (overhead) selain pajak dan keuntungan pada total biaya penawaran. Saran Penelitian ini diharapkan dapat memberi masukan pada Pengguna Jasa (Owners) dan Penyedia Jasa (kontraktor) sehingga faktor-faktor risiko yang berakibat kegagalan menyelesaikan proyek sesuai biaya, mutu dan waktu berdasarkan kontrak, dapat dihindari dari sejak tahap penawaran. Dapat dilakukan penelitian lebih lanjut untuk menghitung persentase besarnya biaya overhead terhadap faktor-faktor risiko pada tahap penawaran, sehingga diperoleh harga penawaran yang wajar berdasarkan perhitungan harga yang professional. DAFTAR PUSTAKA Arikunto, S., Prosedur Penelitian Suatu Pendekatan Praktik. Jakarta: Rineka Cipta. Ebab, A., Analisis Resiko pada Tahap Penawaran Proyek-proyek Konstruksi di Jabotabek. Tesis Magister Teknik. Universitas Indonesia: Jakarta. Gray, C.F., dan Larson, E.W., Project Management. First edition. Irwin McGraw- Hill. Boston. Kuncoro, A., Pengaruh Kualitas Dokumen Penawaran Terhadap Kinerja Proyek Konstruksi Jalan Bina Marga. Tugas Akhir Teknik Sipil Universitas Indonesia: Jakarta. Long, dkk., Delay and Cost Overruns in Vietnam Large Construction Project : A Comparison with Other Selected Countries. Korean Society of Civil Engineering Journal of Civil Engineering,.Vol 12. Peraturan Pemerintah Republik Indonesia 1991,.Tentang Rawa No. 27: Jakarta Volume 1, No. 2, November 2012

ANALISIS FAKTOR-FAKTOR YANG DAPAT MENGUBAH METODE PELAKSANAAN KERJA PADA PROYEK-PROYEK KONSTRUKSI DI KOTA MEDAN LAPORAN

ANALISIS FAKTOR-FAKTOR YANG DAPAT MENGUBAH METODE PELAKSANAAN KERJA PADA PROYEK-PROYEK KONSTRUKSI DI KOTA MEDAN LAPORAN ANALISIS FAKTOR-FAKTOR YANG DAPAT MENGUBAH METODE PELAKSANAAN KERJA PADA PROYEK-PROYEK KONSTRUKSI DI KOTA MEDAN LAPORAN Disusun sebagai Satu Syarat untuk Menyelesaikan Matakuliah Tugas Akhir pada Program

Lebih terperinci

SURVEI MENGENAI BIAYA OVERHEAD SERTA FAKTOR-FAKTOR YANG MEMPENGARUHINYA

SURVEI MENGENAI BIAYA OVERHEAD SERTA FAKTOR-FAKTOR YANG MEMPENGARUHINYA SURVEI MENGENAI BIAYA OVERHEAD SERTA FAKTOR-FAKTOR YANG MEMPENGARUHINYA Henry Pascal Magaline 1, Alvin Januar Haryono 2, Andi 3 ABSTRAK : Biaya overhead sebuah proyek merupakan salah satu unsur harga pokok

Lebih terperinci

POLITEKNIK NEGERI MEDAN

POLITEKNIK NEGERI MEDAN ANALISIS FAKTOR-FAKTOR YANG MEMPENGARUHI KONTRAKTOR DALAM MENGIKUTI PELELANGAN PEKERJAAN KONSTRUKSI DI KOTA MEDAN Ditulis untuk Menyelesaikan Matakuliah Tugas Akhir Semester VIII Program Studi D-IV MRKG

Lebih terperinci

STUDI FAKTOR-FAKTOR UTAMA PENYEBAB PEMBOROSAN MATERIAL (MATERIAL WASTE) PADA PROYEK REHABILITASI JARINGAN IRIGASI PROVINSI ACEH

STUDI FAKTOR-FAKTOR UTAMA PENYEBAB PEMBOROSAN MATERIAL (MATERIAL WASTE) PADA PROYEK REHABILITASI JARINGAN IRIGASI PROVINSI ACEH ISSN 2302-0253 7 Pages pp. 15-21 STUDI FAKTOR-FAKTOR UTAMA PENYEBAB PEMBOROSAN MATERIAL (MATERIAL WASTE) PADA PROYEK REHABILITASI JARINGAN IRIGASI PROVINSI ACEH Muktian 1, Alfiansyah Yulianur 2, Eldina

Lebih terperinci

ANALISIS RISIKO PENAWARAN UNDERESTIMATE COST TERHADAP KUALITAS PROYEK KONSTRUKSI JALAN DI PROVINSI ACEH

ANALISIS RISIKO PENAWARAN UNDERESTIMATE COST TERHADAP KUALITAS PROYEK KONSTRUKSI JALAN DI PROVINSI ACEH ISSN 2088-9321 ISSN e-2502-5295 pp. 511-520 ANALISIS RISIKO PENAWARAN UNDERESTIMATE COST TERHADAP KUALITAS PROYEK KONSTRUKSI JALAN DI PROVINSI ACEH Hamdani 1, M. Isya 2, Hafnidar A. Rani 3 1) Mahasiswa

Lebih terperinci

FAKTOR-FAKTOR RISIKO KETERLAMBATAN PELAKSANAAN PEKERJAAN KONSTRUKSI DIBIDANG SUNGAI DINAS PENGAIRAN ACEH

FAKTOR-FAKTOR RISIKO KETERLAMBATAN PELAKSANAAN PEKERJAAN KONSTRUKSI DIBIDANG SUNGAI DINAS PENGAIRAN ACEH ISSN 30-053 10 Pages pp. 33-4 FAKTOR-FAKTOR RISIKO KETERLAMBATAN PELAKSANAAN PEKERJAAN KONSTRUKSI DIBIDANG SUNGAI DINAS PENGAIRAN ACEH Rina Andriani 1, Azmeri, Nurisra 1) Magister Teknik Sipil Program

Lebih terperinci

STRATEGI PENANGANAN RISIKO PADA PROYEK KONSTRUKSI DI KOTA JAYAPURA (STUDI KASUS PROYEK JALAN)

STRATEGI PENANGANAN RISIKO PADA PROYEK KONSTRUKSI DI KOTA JAYAPURA (STUDI KASUS PROYEK JALAN) STRATEGI PENANGANAN RISIKO PADA PROYEK KONSTRUKSI DI KOTA JAYAPURA (STUDI KASUS PROYEK JALAN) Irianto 1, Didik S. S. Mabui 2 1,2 Teknik Sipil, Fakultas Teknik dan Sistem Informasi, Universitas Yapis Papua

Lebih terperinci

IDENTIFIKASI FAKTOR DOMINAN YANG BERPENGARUH PADA KEGAGALAN PEMENANGAN TENDER TUGAS AKHIR

IDENTIFIKASI FAKTOR DOMINAN YANG BERPENGARUH PADA KEGAGALAN PEMENANGAN TENDER TUGAS AKHIR IDENTIFIKASI FAKTOR DOMINAN YANG BERPENGARUH PADA KEGAGALAN PEMENANGAN TENDER TUGAS AKHIR Ditulis sebagai Syarat Menyelesaikan Matakuliah Tugas Akhir Semester VIII Program Sarjana Sains Terapan (Diploma

Lebih terperinci

PENGARUH QUALITY MANAGEMENT TERHADAP DAYA SAING KONTRAKTOR PADA PROYEK KONSTRUKSI GEDUNG DI KOTA BANDA ACEH

PENGARUH QUALITY MANAGEMENT TERHADAP DAYA SAING KONTRAKTOR PADA PROYEK KONSTRUKSI GEDUNG DI KOTA BANDA ACEH ISSN 2088-9321 ISSN e-2502-5295 pp. 67-76 PENGARUH QUALITY MANAGEMENT TERHADAP DAYA SAING KONTRAKTOR PADA PROYEK KONSTRUKSI GEDUNG DI KOTA BANDA ACEH Nya Munanta 1, Muttaqin Hasan 2, Hafnidar A. Rani 3

Lebih terperinci

ANALISIS FREKUENSI, DAMPAK, DAN JENIS KETERLAMBATAN PADA PROYEK KONSTRUKSI

ANALISIS FREKUENSI, DAMPAK, DAN JENIS KETERLAMBATAN PADA PROYEK KONSTRUKSI ANALISIS FREKUENSI, DAMPAK, DAN JENIS KETERLAMBATAN PADA PROYEK KONSTRUKSI Theresia Monica Sudarsono 1, Olivia Christie 2 and Andi 3 ABSTRAK: Dalam proyek konstruksi terdapat beberapa kemungkinan terjadinya

Lebih terperinci

FAKTOR-FAKTOR RISIKO YANG MEMPENGARUHI KINERJA TAHAP PELAKSANAAN PROYEK IRIGASI (Studi Kasus di Provinsi Aceh)

FAKTOR-FAKTOR RISIKO YANG MEMPENGARUHI KINERJA TAHAP PELAKSANAAN PROYEK IRIGASI (Studi Kasus di Provinsi Aceh) ISSN 2302-0253 14 Pages pp. 12-25 FAKTOR-FAKTOR RISIKO YANG MEMPENGARUHI KINERJA TAHAP PELAKSANAAN PROYEK IRIGASI (Studi Kasus di Provinsi Aceh) Nizamuddin 1, Masimin 2, Ibnu Abbas Madjid 2 1) Magister

Lebih terperinci

BAB 3 METODE PENELITIAN

BAB 3 METODE PENELITIAN 61 BAB 3 METODE PENELITIAN 3.1. Pendahuluan Metode Penelitian adalah suatu metode yang digunakan untuk menjawab masalah secara detil yang meliputi : Variabel yang diteliti. Desain riset yang digunakan.

Lebih terperinci

ANALISIS FAKTOR-FAKTOR PENYEBAB KETERLAMBATAN PADA PROYEK KONSTRUKSI PEMERINTAH DAN SWASTA DI TIMOR LESTE

ANALISIS FAKTOR-FAKTOR PENYEBAB KETERLAMBATAN PADA PROYEK KONSTRUKSI PEMERINTAH DAN SWASTA DI TIMOR LESTE THESIS ANALISIS FAKTOR-FAKTOR PENYEBAB KETERLAMBATAN PADA PROYEK KONSTRUKSI PEMERINTAH DAN SWASTA DI TIMOR LESTE SONIA ELISABETH VIEIRA ANICETO. No. Mhs : 135101972/PS/MTS PROGRAM STUDI MAGISTER TEKNIK

Lebih terperinci

ANALISIS FAKTOR-FAKTOR DOMINAN PENYEBAB KETERLAMBATAN PROYEK KONSTRUKSI BANGUNAN APARTEMEN X BANDUNG

ANALISIS FAKTOR-FAKTOR DOMINAN PENYEBAB KETERLAMBATAN PROYEK KONSTRUKSI BANGUNAN APARTEMEN X BANDUNG SKRIPSI ANALISIS FAKTOR-FAKTOR DOMINAN PENYEBAB KETERLAMBATAN PROYEK KONSTRUKSI BANGUNAN APARTEMEN X BANDUNG ARIE RAHAYU P. NPM: 2012410017 PEMBIMBING: Theresita Herni Setiawan, Ir., MT. UNIVERSITAS KATOLIK

Lebih terperinci

BAB III METODE PENELITIAN

BAB III METODE PENELITIAN BAB III METODE PENELITIAN 3. 1. PENDAHULUAN Pendekatan yang digunakan pada penelitian ini mengacu pada kerangka pemikiran dasar manajemen risiko yaitu dengan melakukan identifikasi risiko hingga analisa

Lebih terperinci

ANALISIS PENGARUH FAKTOR-FAKTOR KOMPETENSI PROJECT MANAGER TERHADAP KEBERHASILAN PROYEK KONSTRUKSI SUNGAI PADA DINAS PENGAIRAN ACEH

ANALISIS PENGARUH FAKTOR-FAKTOR KOMPETENSI PROJECT MANAGER TERHADAP KEBERHASILAN PROYEK KONSTRUKSI SUNGAI PADA DINAS PENGAIRAN ACEH ISSN 2088-9321 ISSN e-2502-5295 pp. 317-328 ANALISIS PENGARUH FAKTOR-FAKTOR KOMPETENSI PROJECT MANAGER TERHADAP KEBERHASILAN PROYEK KONSTRUKSI SUNGAI PADA DINAS PENGAIRAN ACEH Safrial 1, Masimin 2, Anita

Lebih terperinci

BAB I PENDAHULUAN 1.1. Latar Belakang 1.2. Perumusan Masalah

BAB I PENDAHULUAN 1.1. Latar Belakang 1.2. Perumusan Masalah BAB I PENDAHULUAN 1.1. Latar Belakang Pembangunan apartemen adalah salah satu pembangunan yang menimbulkan risiko tinggi bagi proyek tersebut maupun lingkungan sekitarnya dibandingkan dengan pembangunan

Lebih terperinci

HALAMAN JUDUL HALAMAN PERNYATAAN...

HALAMAN JUDUL HALAMAN PERNYATAAN... DAFTAR ISI HALAMAN JUDUL HALAMAN PERNYATAAN... i LEMBAR PENGESAHAN LAPORAN TUGAS AKHIR... ii ABSTRAK... iii UCAPAN TERIMA KASIH... iv DAFTAR ISI... v DAFTAR TABEL... viii DAFTAR GAMBAR... ix BAB I PENDAHULUAN

Lebih terperinci

BAB I PENDAHULUAN. Dalam upaya mendapatkan pekerjaan ( proyek ) pada sector jasa konstruksi hampir

BAB I PENDAHULUAN. Dalam upaya mendapatkan pekerjaan ( proyek ) pada sector jasa konstruksi hampir BAB I PENDAHULUAN 1.1. Latar Belakang Dalam upaya mendapatkan pekerjaan ( proyek ) pada sector jasa konstruksi hampir selalu melalui proses yang dinamakan pelelangan ( tender ). Proses ini menjadi sangat

Lebih terperinci

III. METODOLOGI PENELITIAN. Penelitian ini bertujuan untuk mengetahui tingkat kepuasan penyedia barang/

III. METODOLOGI PENELITIAN. Penelitian ini bertujuan untuk mengetahui tingkat kepuasan penyedia barang/ III. METODOLOGI PENELITIAN A. Desain Penelitian Penelitian ini bertujuan untuk mengetahui tingkat kepuasan penyedia barang/ jasa terhadap pelaksanaan e-procurement di Propinsi Lampung. Jenis data pada

Lebih terperinci

BAB II TINJAUAN PUSTAKA. Risiko dalam proyek konstruksi merupakan probabilitas kejadian yang muncul

BAB II TINJAUAN PUSTAKA. Risiko dalam proyek konstruksi merupakan probabilitas kejadian yang muncul 5 BAB II TINJAUAN PUSTAKA 2.1 Manajemen Risiko Pada manajemen proyek, yang sangat berpengaruh dari risiko ialah kegagalan mempertahankan biaya, waktu dan mencapai kualitas serta keselamatan kerja. Risiko

Lebih terperinci

IDENTIFIKASI FAKTOR-FAKTOR KESELAMATAN DAN KESEHATAN KERJA (K3) YANG MEMPENGARUHI KINERJA PROYEK KONSTRUKSI

IDENTIFIKASI FAKTOR-FAKTOR KESELAMATAN DAN KESEHATAN KERJA (K3) YANG MEMPENGARUHI KINERJA PROYEK KONSTRUKSI ISSN 2302-0253 9 Pages pp. 218-226 IDENTIFIKASI FAKTOR-FAKTOR KESELAMATAN DAN KESEHATAN KERJA (K3) YANG MEMPENGARUHI KINERJA PROYEK KONSTRUKSI Yudi Pratama 1, Teuku Budi Aulia 2, Nurisra 3 1) Magister

Lebih terperinci

Jurnal Teknik Sipil ISSN

Jurnal Teknik Sipil ISSN ISSN 2088-9321 ISSN e-2502-5295 pp. 317-328 ANALISIS FAKTOR-FAKTOR PEMBENGKAKAN BIAYA (COST OVERRUN) YANG BERPENGARUH TERHADAP KETIDAKPASTIAN BIAYA (CONTINGENCY COST) PADA PROYEK IRIGASI DI KABUPATEN ACEH

Lebih terperinci

ANALISIS FAKTOR-FAKTOR PENGHAMBAT YANG BERPENGARUH TERHADAP WAKTU PROYEK IRIGASIDI PROVINSI ACEH

ANALISIS FAKTOR-FAKTOR PENGHAMBAT YANG BERPENGARUH TERHADAP WAKTU PROYEK IRIGASIDI PROVINSI ACEH ISSN 2088-9321 ISSN e-2502-5295 pp. 259-268 ANALISIS FAKTOR-FAKTOR PENGHAMBAT YANG BERPENGARUH TERHADAP WAKTU PROYEK IRIGASIDI PROVINSI ACEH Anita Rauzana 1, Gunawan 2, Masimin 3 1,3) Jurusan Teknik Sipil,

Lebih terperinci

FAKTOR-FAKTOR YANG MENYEBABKAN KETERLAMBATAN WAKTU PELAKSANAAN PROYEK PADA PEKERJAAN JALAN DAN JEMBATAN DI KABUPATEN MOROWALI

FAKTOR-FAKTOR YANG MENYEBABKAN KETERLAMBATAN WAKTU PELAKSANAAN PROYEK PADA PEKERJAAN JALAN DAN JEMBATAN DI KABUPATEN MOROWALI FAKTOR-FAKTOR YANG MENYEBABKAN KETERLAMBATAN WAKTU PELAKSANAAN PROYEK PADA PEKERJAAN JALAN DAN JEMBATAN DI KABUPATEN MOROWALI Elce Misba Bansambua Staff Pengajar Jurusan Teknik Sipil, Fakultas Teknik Universitas

Lebih terperinci

BAB I PENDAHULUAN. Project life cycle. Construction. Tender Document. Product

BAB I PENDAHULUAN. Project life cycle. Construction. Tender Document. Product BAB I PENDAHULUAN 1. 1. LATAR BELAKANG MASALAH Secara umum siklus kehidupan proyek konstruksi terbagi atas empat bagian besar yaitu studi kelayakan (feasibility study), estimasi proyek (detail estimate

Lebih terperinci

II. TINJAUAN PUSTAKA. Kata Kunci : identifikasi risiko, matriks probabilitasdampak, respon risiko, severity indeks. I. PENDAHULUAN

II. TINJAUAN PUSTAKA. Kata Kunci : identifikasi risiko, matriks probabilitasdampak, respon risiko, severity indeks. I. PENDAHULUAN 1 IDENTIFIKASI DAN RESPON RISIKO PADA PROYEK PEMBANGUNAN JEMBATAN PENGHUBUNG TERMINAL MULTIPURPOSE TELUK LAMONG PELABUHAN TANJUNG PERAK SURABAYA PAKET C DARI PERSEPSI KONTRAKTOR Asraf Ali Hamidi, Yusroniya

Lebih terperinci

Abstrak. Universitas Kristen Maranatha

Abstrak. Universitas Kristen Maranatha Abstrak Penelitian ini dilaksanakan untuk mengetahui informasi yang dapat menjelaskan mengenai gambaran kemandirian remaja bungsu SMA Negeri X di Bandung berdasarkan tiga aspek kemandirian Steinberg (2002),

Lebih terperinci

BAB III METODOLOGI PENELITIAN. penelitian digunakan untuk memecahkan suatu masalah, memahami, serta

BAB III METODOLOGI PENELITIAN. penelitian digunakan untuk memecahkan suatu masalah, memahami, serta BAB III METODOLOGI PENELITIAN BAB III METODOLOGI PENELITIAN 3.1. TinjauanUmum Metode penelitian merupakan suatu cara alamiah untuk memperoleh data dengan kegunaan dan tujuan tertentu. Secara umum data

Lebih terperinci

PRESENTASI UJIAN TESIS FAKTOR-FAKTOR YANG BERKONTRIBUSI TERHADAP KETERLAMBATAN PROYEK KONSTRUKSI DI PT. NEWMONT NUSA TENGGARA

PRESENTASI UJIAN TESIS FAKTOR-FAKTOR YANG BERKONTRIBUSI TERHADAP KETERLAMBATAN PROYEK KONSTRUKSI DI PT. NEWMONT NUSA TENGGARA PRESENTASI UJIAN TESIS FAKTOR-FAKTOR YANG BERKONTRIBUSI TERHADAP KETERLAMBATAN PROYEK KONSTRUKSI DI PT. NEWMONT NUSA TENGGARA Nugroho Adi / NIM: 9111202806 Surabaya, 31 Oktober 2014 PROGRAM STUDI MAGISTER

Lebih terperinci

Kata kunci: Gugurnya Penawaran, E-Procurement, Pekerjaan Jasa Konsultan

Kata kunci: Gugurnya Penawaran, E-Procurement, Pekerjaan Jasa Konsultan ABSTRAK ANALISIS FAKTOR-FAKTOR YANG MEMPENGARUHI GUGURNYA PENAWARAN PENGADAAN JASA KONSULTAN PERENCANA DIKOTA MALANG DITINJAU DARI PEMENUHAN PERSYARATAN PENGADAAN Oleh: Rizki Arisandy 0910613059 Mulai

Lebih terperinci

STUDI PERSEPSI FAKTOR-FAKTOR PENYEBAB KLAIM PADA PELAKSANAAN PROYEK KONSTRUKSI BANGUNAN GEDUNG

STUDI PERSEPSI FAKTOR-FAKTOR PENYEBAB KLAIM PADA PELAKSANAAN PROYEK KONSTRUKSI BANGUNAN GEDUNG Konferensi Nasional Teknik Sipil 4 (KoNTekS 4) Sanur-Bali, 2-3 Juni 2010 STUDI PERSEPSI FAKTOR-FAKTOR PENYEBAB KLAIM PADA PELAKSANAAN PROYEK KONSTRUKSI BANGUNAN GEDUNG Wahida Handayani 1, Yohanes Lim Dwi

Lebih terperinci

BAB III METODE PENELITIAN

BAB III METODE PENELITIAN BAB III METODE PENELITIAN 3.1 Metodologi Penelitian Metodologi penelitian merupakan alur pemikiran yang ditempuh dalam menentukan analisis metode dari penelitian ini. Untuk mendapat data di dalam penelitian

Lebih terperinci

BAB II TINJAUAN PUSTAKA. RISIKO DALAM PROYEK KONSTRUKSI MERUPAKAN PROBABILITAS KEJADIAN YANG MUNCUL

BAB II TINJAUAN PUSTAKA. RISIKO DALAM PROYEK KONSTRUKSI MERUPAKAN PROBABILITAS KEJADIAN YANG MUNCUL BAB II TINJAUAN PUTAKA. RIIKO DALAM PROYEK KONTRUKI MERUPAKAN PROBABILITA KEJADIAN YANG MUNCUL 5 BAB II TINJAUAN PUTAKA 2.1 Manajemen Risiko Pada manajemen proyek, yang sangat berpengaruh dari risiko

Lebih terperinci

MANAJEMEN RISIKO PADA PROYEK KONSTRUKSI GEDUNG DI YOGYAKARTA DENGAN MENGGUNAKAN METODE HOUSE OF RISK

MANAJEMEN RISIKO PADA PROYEK KONSTRUKSI GEDUNG DI YOGYAKARTA DENGAN MENGGUNAKAN METODE HOUSE OF RISK TESIS MANAJEMEN RISIKO PADA PROYEK KONSTRUKSI GEDUNG DI YOGYAKARTA DENGAN MENGGUNAKAN METODE HOUSE OF RISK PARAMANANDA SOFYAN SOFANDI No. Mhs.: 155102492/PS/MTS PROGRAM STUDI MAGISTER TEKNIK SIPIL PROGRAM

Lebih terperinci

BAB I PENDAHULUAN. kegagalan pencapaian tujuan/sasaran proyek pada umumnya.

BAB I PENDAHULUAN. kegagalan pencapaian tujuan/sasaran proyek pada umumnya. BAB I PENDAHULUAN 1.1. Latar Belakang Masalah Proyek konstruksi merupakan suatu rangkaian kegiatan yang berkaitan dengan upaya pembangunan suatu bangunan infrastruktur. Faktor-faktor ketidakpastian dan

Lebih terperinci

BAB III METODOLOGI PENELITIAN

BAB III METODOLOGI PENELITIAN BAB III METODOLOGI PENELITIAN Metode penelitian adalah langkah dan prosedur yang akan dilakukan dalam pengumpulan data atau informasi guna memecahkan permasalahan dan menguji hipotesis penelitian. Sesuai

Lebih terperinci

TINGKAT KESIAPAN MASYARAKAT JASA KONSTRUKSI DALAM PENERAPAN E-PROCUREMENT DI LHOKSEUMAWE

TINGKAT KESIAPAN MASYARAKAT JASA KONSTRUKSI DALAM PENERAPAN E-PROCUREMENT DI LHOKSEUMAWE TINGKAT KESIAPAN MASYARAKAT JASA KONSTRUKSI DALAM PENERAPAN E-PROCUREMENT DI LHOKSEUMAWE M. Fauzan 1), Mukhlis 2), T. Ricky Husny 3) 1) 2) Jurusan Teknik Sipil Fakultas Teknik Universitas Malikussaleh

Lebih terperinci

IDENTIFIKASI FAKTOR-FAKTOR YANG DIPERTIMBANGKAN DALAM USULAN PROYEK IRIGASI (STUDI KASUS PADA BALAI WILAYAH SUNGAI SUMATERA-I ACEH)

IDENTIFIKASI FAKTOR-FAKTOR YANG DIPERTIMBANGKAN DALAM USULAN PROYEK IRIGASI (STUDI KASUS PADA BALAI WILAYAH SUNGAI SUMATERA-I ACEH) ISSN 2302-0253 Program 13 Pages pp. 44-56 IDENTIFIKASI FAKTOR-FAKTOR YANG DIPERTIMBANGKAN DALAM USULAN PROYEK IRIGASI (STUDI KASUS PADA BALAI WILAYAH SUNGAI SUMATERA-I ACEH) Isnaini Aliyansyah 1, Azmeri

Lebih terperinci

ANALISIS FAKTOR FAKTOR YANG MEMPENGARUHI COST OVERRUNS PADA PROYEK KONSTRUKSI DI SURABAYA

ANALISIS FAKTOR FAKTOR YANG MEMPENGARUHI COST OVERRUNS PADA PROYEK KONSTRUKSI DI SURABAYA ANALISIS FAKTOR FAKTOR YANG MEMPENGARUHI COST OVERRUNS PADA PROYEK KONSTRUKSI DI SURABAYA ANALYSIS OF FACTORS - FACTORS AFFECTING THE COST OVERRUNS ON CONSTRUCTION PROJECTS IN SURABAYA Ari Swezni, Retno

Lebih terperinci

ABSTRACT. Keywords: Audit Committee, Internal Audit, State-Owned Enterprises. Universitas Kristen Maranatha

ABSTRACT. Keywords: Audit Committee, Internal Audit, State-Owned Enterprises. Universitas Kristen Maranatha ABSTRACT Most of the shares of State Owned Enterprises (SOEs) funded from the state, therefore the management of SOEs should be accountable. Role of both the internal auditor and the audit committee is

Lebih terperinci

ABSTRAK. Kata kunci: kompensasi finansial, gaya kepemimpinan, motivasi kerja, kinerja karyawan

ABSTRAK. Kata kunci: kompensasi finansial, gaya kepemimpinan, motivasi kerja, kinerja karyawan ABSTRACT This study aims to determine the relationship between financial compensation, leadership style and motivation to the employee s performance of company. The number of respondent in this study were

Lebih terperinci

ANALISIS FAKTOR PENAWARAN RENDAH PADA PELELANGAN PROYEK DI LINGKUNGAN PEMERINTAH

ANALISIS FAKTOR PENAWARAN RENDAH PADA PELELANGAN PROYEK DI LINGKUNGAN PEMERINTAH ANALISIS FAKTOR PENAWARAN RENDAH PADA PELELANGAN PROYEK DI LINGKUNGAN PEMERINTAH Youngki Firmansyah, Supani Hardjo Diputro Program Studi Magister Manajemen Teknologi ITS Bidang Keahlian Manajemen Proyek

Lebih terperinci

Lampiran 1 : KUESIONER REDUKSI VARIABEL PENELITIAN

Lampiran 1 : KUESIONER REDUKSI VARIABEL PENELITIAN 122 Lampiran 1 : KUESIONER REDUKSI VARIABEL PENELITIAN ANALISIS FAKTOR RISIKO YANG MEMPENGARUHI KINERJA KUALITAS KONTRAKTOR I. PENDAHULUAN Penelitian ini akan berusaha mengidentifikasi dan menganalisis

Lebih terperinci

BAB III METODOLOGI PENELITIAN

BAB III METODOLOGI PENELITIAN BAB III METODOLOGI PENELITIAN 3.1 Tahapan Penelitian Pada bab ini akan di uraikan tahapan penelitian yang akan dilalui dari awal sampai akhir. Hal ini dilakukan untuk mempermudah proses analisis dalam

Lebih terperinci

`BAB III METODE PENELITIAN. bimbingan kelompok dengan komunikasi antar pribadi siswa kelas VIII di

`BAB III METODE PENELITIAN. bimbingan kelompok dengan komunikasi antar pribadi siswa kelas VIII di `BAB III METODE PENELITIAN A. Bentuk Penelitian Penelitian ini merupakan penelitian korelasi, yaitu untuk mengetahui apakah ada hubungan yang signifikan antara keaktifan mengikuti layanan bimbingan kelompok

Lebih terperinci

ANALISIS FAKTOR KETERLAMBATAN PEMBANGUNAN GEDUNG DENGAN STRUCTURAL EQUATION MODELING (SEM)

ANALISIS FAKTOR KETERLAMBATAN PEMBANGUNAN GEDUNG DENGAN STRUCTURAL EQUATION MODELING (SEM) TESIS ANALISIS FAKTOR KETERLAMBATAN PEMBANGUNAN GEDUNG DENGAN STRUCTURAL EQUATION MODELING (SEM) ADRIAN AUSTEN No Mhs : 145102284/MTS PROGRAM STUDI MAGISTER TEKNIK SIPIL PROGRAM PASCASARJANA UNIVERSITAS

Lebih terperinci

BAB 1 PENDAHULUAN. Universitas Indonesia. Pengelolaan risiko..., Budi Suanda, FT UI, 2008

BAB 1 PENDAHULUAN. Universitas Indonesia. Pengelolaan risiko..., Budi Suanda, FT UI, 2008 1 BAB 1 PENDAHULUAN 1.1 Latar Belakang Industri jasa konstruksi merupakan industri yang memiliki karakteristikkarakteristik khusus yang sulit untuk diantisipasi karena unik, sumber daya yang berfluktuasi,

Lebih terperinci

FAKTOR-FAKTOR YANG MEMPENGARUHI KINERJA PANITIA PENGADAAN PEKERJAAN KONSTRUKSI FISIK DI KABUPATEN JEMBER

FAKTOR-FAKTOR YANG MEMPENGARUHI KINERJA PANITIA PENGADAAN PEKERJAAN KONSTRUKSI FISIK DI KABUPATEN JEMBER FAKTOR-FAKTOR YANG MEMPENGARUHI KINERJA PANITIA PENGADAAN PEKERJAAN KONSTRUKSI FISIK DI KABUPATEN JEMBER Hernu Suyoso 1), Agoes Soehardjono 2), As ad Munawir 3) 1) Jurusan Teknik Sipil Fakultas Teknik

Lebih terperinci

SKRIPSI KAJIAN FAKTOR KETERLAMBATAN PADA PROYEK BANGUNAN AIR BERSIH ( STUDI KASUS ) DI KABUPATEN MANATUTU TIMOR LESTE

SKRIPSI KAJIAN FAKTOR KETERLAMBATAN PADA PROYEK BANGUNAN AIR BERSIH ( STUDI KASUS ) DI KABUPATEN MANATUTU TIMOR LESTE SKRIPSI KAJIAN FAKTOR KETERLAMBATAN PADA PROYEK BANGUNAN AIR BERSIH ( STUDI KASUS ) DI KABUPATEN MANATUTU TIMOR LESTE DiajukanUntuk Memenuhi Persyaratan Dalam Menyelesaikan Pendidikan Tingkat Sarjana (strata

Lebih terperinci

ANALISA PENGARUH RENDAHNYA KUALITAS SUMBER DAYA MANUSIA TERHADAP KINERJA PROYEK DI SURABAYA

ANALISA PENGARUH RENDAHNYA KUALITAS SUMBER DAYA MANUSIA TERHADAP KINERJA PROYEK DI SURABAYA ANALISA PENGARUH RENDAHNYA KUALITAS SUMBER DAYA MANUSIA TERHADAP KINERJA PROYEK DI SURABAYA Soelistyono 1) Program Studi Pascasarjana Teknik Sipil, Institut Teknologi Sepuluh Nopember, Jl. Kampus ITS Sukolilo,

Lebih terperinci

BAB 1 PENDAHULUAN. 1.1 Latar Belakang Masalah

BAB 1 PENDAHULUAN. 1.1 Latar Belakang Masalah BAB 1 PENDAHULUAN 1.1 Latar Belakang Masalah Proyek merupakan suatu kegiatan yang memiliki tujuan yang harus dicapai dengan beberapa spesifikasi tertentu, memiliki awal dan akhir, dengan keterbatasan sumber

Lebih terperinci

BAB I PENDAHULUAN 1.1. Latar Belakang

BAB I PENDAHULUAN 1.1. Latar Belakang BAB I PENDAHULUAN 1.1. Latar Belakang Menurut Project Management Institute (1996) sebuah proyek memiliki dua karakteristik utama yaitu bersifat temporer dan unik. Disebut temporer karena hanya terjadi

Lebih terperinci

STUDI HARGA PENAWARAN DAN FAKTOR PENENTU PEMENANG TENDER PROYEK KONSTRUKSI DI DIY UNTUK KUALIFIKASI NON KECIL (234K)

STUDI HARGA PENAWARAN DAN FAKTOR PENENTU PEMENANG TENDER PROYEK KONSTRUKSI DI DIY UNTUK KUALIFIKASI NON KECIL (234K) STUDI HARGA PENAWARAN DAN FAKTOR PENENTU PEMENANG TENDER PROYEK KONSTRUKSI DI DIY UNTUK KUALIFIKASI NON KECIL (234K) Zaenal Arifin 1 dan Dara Juwanti 2 1 Jurusan Teknik Sipil, Universitas Islam Indonesia,

Lebih terperinci

BAB V KESIMPULAN DAN SARAN. 1. Frekuensi risiko yang paling dominan terjadi dalam pembangunan proyekproyek. konstruksi di Yogyakarta, yaitu:

BAB V KESIMPULAN DAN SARAN. 1. Frekuensi risiko yang paling dominan terjadi dalam pembangunan proyekproyek. konstruksi di Yogyakarta, yaitu: BAB V KESIMPULAN DAN SARAN 5.1. Kesimpulan Berdasarkan hasil pembahasan pada bab sebelumnya, maka dapat ditarik beberapa kesimpulan sebagai berikut : 1. Frekuensi risiko yang paling dominan terjadi dalam

Lebih terperinci

IDENTIFIKASI FAKTOR-FAKTOR KRITIKAL YANG MEMPENGARUHI KESUKSESAN PELAKSANAAN PROYEK JALAN DI PROVINSI ACEH

IDENTIFIKASI FAKTOR-FAKTOR KRITIKAL YANG MEMPENGARUHI KESUKSESAN PELAKSANAAN PROYEK JALAN DI PROVINSI ACEH ISSN 2302-0253 10 Pages pp. 97-106 IDENTIFIKASI FAKTOR-FAKTOR KRITIKAL YANG MEMPENGARUHI KESUKSESAN PELAKSANAAN PROYEK JALAN DI PROVINSI ACEH Hery Irfansyah 1, M.Isya 2, Mubarak 3 1) Magister Teknik Sipil

Lebih terperinci

IV METODE PENELITIAN 4.1 Lokasi dan Waktu Penelitian 4.2 Jenis dan Sumber Data

IV METODE PENELITIAN 4.1 Lokasi dan Waktu Penelitian 4.2 Jenis dan Sumber Data IV METODE PENELITIAN 4.1 Lokasi dan Waktu Penelitian Penelitian dilakukan di PT. Sang Hyang Seri (Persero) Regional Manajer I Sukamandi di Sukamandi, Kabupaten Subang. Pemilihan lokasi penelitian dilakukan

Lebih terperinci

FAKTOR-FAKTOR PENGARUH MANAJEMENN RISIKO KONSTRUKSI PADA PROYEK PEMBANGUNAN WADUK BAJULMATI DI BANYUWANGI-SITUBONDO JAWA TIMUR

FAKTOR-FAKTOR PENGARUH MANAJEMENN RISIKO KONSTRUKSI PADA PROYEK PEMBANGUNAN WADUK BAJULMATI DI BANYUWANGI-SITUBONDO JAWA TIMUR FAKTOR-FAKTOR PENGARUH MANAJEMENN RISIKO KONSTRUKSI PADA PROYEK PEMBANGUNAN WADUK BAJULMATI DI BANYUWANGI-SITUBONDO JAWA TIMUR SKRIPSI Oleh Dwi Gesang Ageng Pangapuri NIM 091910301087 JURUSAN TEKNIK SIPIL

Lebih terperinci

FAKTOR FAKTOR YANG MENYEBABKAN COST OVERRUN PADA PROYEK KONSTRUKSI

FAKTOR FAKTOR YANG MENYEBABKAN COST OVERRUN PADA PROYEK KONSTRUKSI FAKTOR FAKTOR YANG MENYEBABKAN COST OVERRUN PADA PROYEK KONSTRUKSI Yeltsin C. Dapu A.K.T. Dundu, Ronny Walangitan Fakultas Teknik Jurusan Sipil Universitas Sam Ratulangi Manado email: yeltsindapu@yahoo.co.id

Lebih terperinci

UNIVERSITAS INDONESIA FAKTOR PENYEBAB TERJADINYA KLAIM YANG MEMPENGARUHI KINERJA WAKTU PROYEK KONSTRUKSI JALAN TOL DI JABODETABEK TESIS

UNIVERSITAS INDONESIA FAKTOR PENYEBAB TERJADINYA KLAIM YANG MEMPENGARUHI KINERJA WAKTU PROYEK KONSTRUKSI JALAN TOL DI JABODETABEK TESIS UNIVERSITAS INDONESIA FAKTOR PENYEBAB TERJADINYA KLAIM YANG MEMPENGARUHI KINERJA WAKTU PROYEK KONSTRUKSI JALAN TOL DI JABODETABEK TESIS ANDREAS PARTOGI PASARIBU 0706304965 FAKULTAS TEKNIK PROGRAM PASCASARJANA

Lebih terperinci

TINGKAT KEPENTINGAN FAKTOR FAKTOR PRODUKTIVITAS PEKERJA BERDASARKAN TINGKAT PENGARUH DAN TINGKAT FREKUENSI

TINGKAT KEPENTINGAN FAKTOR FAKTOR PRODUKTIVITAS PEKERJA BERDASARKAN TINGKAT PENGARUH DAN TINGKAT FREKUENSI TINGKAT KEPENTINGAN FAKTOR FAKTOR PRODUKTIVITAS PEKERJA BERDASARKAN TINGKAT PENGARUH DAN TINGKAT FREKUENSI Albertus Andhika 1, Alfonso Wijanalto 2, Andi 3 ABSTRAK : Produktivitas pekerja konsruksi telah

Lebih terperinci

ANALISIS FAKTOR-FAKTOR PENYEBAB KETERLAMBATAN PELAKSANAAN PROYEK KONSTRUKSI DI KABUPATEN BULELENG

ANALISIS FAKTOR-FAKTOR PENYEBAB KETERLAMBATAN PELAKSANAAN PROYEK KONSTRUKSI DI KABUPATEN BULELENG ANALISIS FAKTOR-FAKTOR PENYEBAB KETERLAMBATAN PELAKSANAAN PROYEK KONSTRUKSI DI KABUPATEN BULELENG TUGAS AKHIR Oleh : Ni Kadek Lia Arista 1204105007 JURUSAN TEKNIK SIPIL FAKULTAS TEKNIK UNIVERSITAS UDAYANA

Lebih terperinci

IV. METODE PENELITIAN

IV. METODE PENELITIAN IV. METODE PENELITIAN 4.1 Lokasi Penelitian dan Waktu Penelitian Penelitian ini dilakukan pada Restoran River Side yang berlokasi di Kawasan Wisata Sungai Musi, Komplek Benteng Kuto Besak, Jalan Rumah

Lebih terperinci

BAB I PENDAHULUAN. Di Indonesia sektor jasa konstruksi selama ini sudah terbukti sebagai salah

BAB I PENDAHULUAN. Di Indonesia sektor jasa konstruksi selama ini sudah terbukti sebagai salah 14 BAB I PENDAHULUAN 1.1. Latar Belakang Di Indonesia sektor jasa konstruksi selama ini sudah terbukti sebagai salah satu sektor usaha yang mampu memberikan sumbangan yang cukup signifikan bagi pertumbuhan

Lebih terperinci

ANALISIS FAKTOR-FAKTOR PENGARUH KONFLIK (DISPUTE) TERHADAP KEBERHASILAN PROYEK KONSTRUKSI DI PROVINSI ACEH

ANALISIS FAKTOR-FAKTOR PENGARUH KONFLIK (DISPUTE) TERHADAP KEBERHASILAN PROYEK KONSTRUKSI DI PROVINSI ACEH ISSN 2088-9321 ISSN e-2502-5295 pp. 149-158 ANALISIS FAKTOR-FAKTOR PENGARUH KONFLIK (DISPUTE) TERHADAP KEBERHASILAN PROYEK KONSTRUKSI DI PROVINSI ACEH Rinaldy 1, Teuku Budi Aulia 2, Anita Rauzana 3 1)

Lebih terperinci

MODEL SUMBER DAN PENYEBAB REWORK PADA TAHAPAN PROYEK KONSTRUKSI

MODEL SUMBER DAN PENYEBAB REWORK PADA TAHAPAN PROYEK KONSTRUKSI MODEL SUMBER DAN PENYEBAB REWORK PADA TAHAPAN PROYEK KONSTRUKSI Erick Chundawan 1, Ratna S Alifen 2 ABSTRAK: Dalam dunia konstruksi, rework merupakan hal yang tidak dapat dihindari. Rework dapat terjadi

Lebih terperinci

BAB V PENUTUP. dijelaskan pada bab sebelumnya. Kesimpulan akan mencakup pembahasan dari hasil evaluasi

BAB V PENUTUP. dijelaskan pada bab sebelumnya. Kesimpulan akan mencakup pembahasan dari hasil evaluasi BAB V PENUTUP Bab ini akan memaparkan kesimpulan dan saran berdasarkan hasil penelitian yang telah dijelaskan pada bab sebelumnya. Kesimpulan akan mencakup pembahasan dari hasil evaluasi pada 3 titik penting

Lebih terperinci

ANALISIS FAKTOR-FAKTOR PENYEBAB KETERLAMBATAN PELAKSANAAN PROYEK KONSTRUKSI

ANALISIS FAKTOR-FAKTOR PENYEBAB KETERLAMBATAN PELAKSANAAN PROYEK KONSTRUKSI Konferensi Nasional Teknik Sipil 11 Universitas Tarumanagara, 26-27 Oktober 2017 ANALISIS FAKTOR-FAKTOR PENYEBAB KETERLAMBATAN PELAKSANAAN PROYEK KONSTRUKSI I.A.Rai Widhiawati 1, I G.A.Adnyana Putera 1,

Lebih terperinci

BAB 3 METODE PENELITIAN. yang disesuaikan dengan tujuan penelitian sehingga dapat melakukan analisis. Berikut. Jenis dan Metode. pelanggan.

BAB 3 METODE PENELITIAN. yang disesuaikan dengan tujuan penelitian sehingga dapat melakukan analisis. Berikut. Jenis dan Metode. pelanggan. BAB 3 METODE PENELITIAN 3.1 Desain Penelitian Untuk mengetahui jenis penelitian yang dilakukan, digunakan desain penelitian yang disesuaikan dengan tujuan penelitian sehingga dapat melakukan analisis.

Lebih terperinci

BAB I. 1.1 Latar Belakang Masalah

BAB I. 1.1 Latar Belakang Masalah BAB I BAB 1 PENDAHULUAN 1.1 Latar Belakang Masalah Jasa konstruksi mempunyai peran strategis dalam Pembangunan Nasional. Perum Perumnas adalah salah satu Badan Usaha Milik Negara (BUMN) berbentuk Perusahaan

Lebih terperinci

ABSTRACT. Keyword : Financial Compensation, Non Financial Compensation, Performance. vii. Universitas Kristen Maranatha

ABSTRACT. Keyword : Financial Compensation, Non Financial Compensation, Performance. vii. Universitas Kristen Maranatha ABSTRACT Management Control Systems is a very important factor in the company. One important part of the SPM that should receive more attention is labor. Labor is a major driver of the smooth running of

Lebih terperinci

ANALISA PENGARUH CHANGE ORDER TERHADAP BIAYA, WAKTU DAN MUTU PROYEK KONSTRUKSI DI SURABAYA

ANALISA PENGARUH CHANGE ORDER TERHADAP BIAYA, WAKTU DAN MUTU PROYEK KONSTRUKSI DI SURABAYA ANALISA PENGARUH CHANGE ORDER TERHADAP BIAYA, WAKTU DAN MUTU PROYEK KONSTRUKSI DI SURABAYA Michella Beatrix 1) dan I Putu Artama Wiguna 2) 1) Program Studi Pascasarjana Teknik Sipil, Institut Teknologi

Lebih terperinci

ABSTRACT. Key words: Perception of compensation systems, employee motivation

ABSTRACT. Key words: Perception of compensation systems, employee motivation ABSTRACT Development in technology and information era has impact on changing the way companies in doing business and change behavior, consumer preferences and demands. The key to success for the company

Lebih terperinci

MODEL PENETAPAN TARGET PRICE PADA HPS/OE GUNA MENINGKATKAN CONFIDENCE LEVEL PENGAMBIL KEPUTUSAN PADA PELELANGAN PROYEK EPC MIGAS DI INDONESIA

MODEL PENETAPAN TARGET PRICE PADA HPS/OE GUNA MENINGKATKAN CONFIDENCE LEVEL PENGAMBIL KEPUTUSAN PADA PELELANGAN PROYEK EPC MIGAS DI INDONESIA MODEL PENETAPAN TARGET PRICE PADA HPS/OE GUNA MENINGKATKAN CONFIDENCE LEVEL PENGAMBIL KEPUTUSAN PADA PELELANGAN PROYEK EPC MIGAS DI INDONESIA Ignatius Totok Sugiarto 1) dan Tri Joko Wahyu Adi 2) 1) Program

Lebih terperinci

ANALISIS FAKTOR-FAKTOR YANG MEMPENGARUHI PENILA1AN PENGGUNA JASA /KLIEN PRO YEK KONSTRUKSI DALAM PROSES PEMILIHAN KONTRAKTOR. I s n a r n o.

ANALISIS FAKTOR-FAKTOR YANG MEMPENGARUHI PENILA1AN PENGGUNA JASA /KLIEN PRO YEK KONSTRUKSI DALAM PROSES PEMILIHAN KONTRAKTOR. I s n a r n o. ANALISIS FAKTOR-FAKTOR YANG MEMPENGARUHI PENILA1AN PENGGUNA JASA /KLIEN PRO YEK KONSTRUKSI DALAM PROSES PEMILIHAN KONTRAKTOR I s n a r n o Abstrak Pemilihan kontraktor merupakan salah satu tahapan penting

Lebih terperinci

BAB 3 METODE PENELITIAN. Pendekatan objektif menganggap perilaku manusia disebabkan oleh kekuatan-kekuatan

BAB 3 METODE PENELITIAN. Pendekatan objektif menganggap perilaku manusia disebabkan oleh kekuatan-kekuatan BAB 3 METODE PENELITIAN 3.1 Pendekatan dan Metodologi 3.1.1 Pendekatan Pendekatan yang digunakan dalam penelitian ini adalah pendekatan objektif. Pendekatan objektif menganggap perilaku manusia disebabkan

Lebih terperinci

METODOLOGI PENELITIAN

METODOLOGI PENELITIAN IV. METODOLOGI PENELITIAN 4.1. Penentuan Lokasi dan Waktu Penelitian Penelitian ini merupakan studi kasus yang dilakukan di Kantor Pelayanan Pajak Pratama Bandung Tegallega di Jalan Soekarno Hatta No 216,

Lebih terperinci

BAB III METODE PENELITIAN

BAB III METODE PENELITIAN BAB III METODE PENELITIAN 3.1. Metodologi Penelitian Metode penelitian yang digunakan adalah observasi dan studi kasus pada salah satu proyek yang sedang dikerjakan oleh Takenaka Total J.O. Metode penelitian

Lebih terperinci

BAB I. PENDAHULUAN PENDAHULUAN

BAB I. PENDAHULUAN PENDAHULUAN 1 BAB I. PENDAHULUAN PENDAHULUAN A. Latar Belakang Jalan merupakan infrastruktur transportasi darat yang berperan sangat penting dalam perkembangan suatu wilayah. Jalan berfungsi untuk mendukung kegiatan

Lebih terperinci

TESIS STUDI MENGENAI HUBUNGAN KARAKTERISTIK DAN KINERJA PERUSAHAAN KONTRAKTOR KUALIFIKASI KECIL DI DAERAH ISTIMEWA YOGYAKARTA

TESIS STUDI MENGENAI HUBUNGAN KARAKTERISTIK DAN KINERJA PERUSAHAAN KONTRAKTOR KUALIFIKASI KECIL DI DAERAH ISTIMEWA YOGYAKARTA TESIS STUDI MENGENAI HUBUNGAN KARAKTERISTIK DAN KINERJA PERUSAHAAN KONTRAKTOR KUALIFIKASI KECIL DI DAERAH ISTIMEWA YOGYAKARTA ALBERTUS DWI CHRISTIAWAN No. Mhs : 12 51 01895/PS/MTS PROGRAM STUDI MAGISTER

Lebih terperinci

STUDI MENGENAI FAKTOR PENGHAMBAT PELAKSANAAN PROYEK DI SORONG PAPUA BARAT

STUDI MENGENAI FAKTOR PENGHAMBAT PELAKSANAAN PROYEK DI SORONG PAPUA BARAT TESIS STUDI MENGENAI FAKTOR PENGHAMBAT PELAKSANAAN PROYEK DI SORONG PAPUA BARAT ELKI IVAN RANTEPASANG No Mhs : 145102224/MTS PROGRAM STUDI MAGISTER TEKNIK SIPIL PROGRAM PASCASARJANA UNIVERSITAS ATMA JAYA

Lebih terperinci

ABSTRACT. Keywords : Compensation, whistleblower, fraud. vii Universitas Kristen Maranatha

ABSTRACT. Keywords : Compensation, whistleblower, fraud. vii Universitas Kristen Maranatha ABSTRACT Deceitfulness or commonly referred as a fraud is done with a variety of modes and growing over time. With granting the appropriate compensation to the employee as well as the appearance of the

Lebih terperinci

BAB III...19 RENCANA KEGIATAN...19

BAB III...19 RENCANA KEGIATAN...19 DAFTAR ISI ABSTRAK... i UCAPAN TERIMA KASIH... ii DAFTAR ISI... iii DAFTAR TABEL... v DAFTAR GAMBAR... vi BAB I...1 PENDAHULUAN...1 1.1 Latar Belakang... 1 1.2 Rumusan Masalah... 2 1.3 Tujuan Penelitian...

Lebih terperinci

STUDI KLASIFIKASI DAN PERINGKAT PENYEBAB- PENYEBAB KETERLAMBATAN WAKTU PELAKSANAAN PROYEK

STUDI KLASIFIKASI DAN PERINGKAT PENYEBAB- PENYEBAB KETERLAMBATAN WAKTU PELAKSANAAN PROYEK STUDI KLASIFIKASI DAN PERINGKAT PENYEBAB- PENYEBAB KETERLAMBATAN WAKTU PELAKSANAAN PROYEK Flora NRP : 0421033 Pembimbing : Ir. Yohanes Lim Dwi A., MT. FAKULTAS TEKNIK JURUSAN TEKNIK SIPIL UNIVERSITAS KRISTEN

Lebih terperinci

ANALISIS RISIKO FONDASI BORED PILE DAN TIANG PANCANG PROYEK TUNJUNGAN PLAZA 6 SURABAYA

ANALISIS RISIKO FONDASI BORED PILE DAN TIANG PANCANG PROYEK TUNJUNGAN PLAZA 6 SURABAYA ANALISIS RISIKO FONDASI BORED PILE DAN TIANG PANCANG PROYEK TUNJUNGAN PLAZA 6 SURABAYA Felicia T. Nuciferani [1], Mohamad F.N Aulady [2], Nila A. Putri [3] Jurusan Teknik Sipil-InstitutTeknologi Adhi Tama

Lebih terperinci

IDENTIFIKASI FAKTOR PENYEBAB KETERLAMBATAN PELAKSANAAN PROYEK KONSTRUKSI JALAN BATAS KOTA BUKIT TINGGI - LUBUK SIKAPING BATAS SUMUT TESIS.

IDENTIFIKASI FAKTOR PENYEBAB KETERLAMBATAN PELAKSANAAN PROYEK KONSTRUKSI JALAN BATAS KOTA BUKIT TINGGI - LUBUK SIKAPING BATAS SUMUT TESIS. IDENTIFIKASI FAKTOR PENYEBAB KETERLAMBATAN PELAKSANAAN PROYEK KONSTRUKSI JALAN BATAS KOTA BUKIT TINGGI - LUBUK SIKAPING BATAS SUMUT TESIS Oleh : IRWAN YURNALIS 1220922010 PROGRAM MAGISTER TEKNIK SIPIL

Lebih terperinci

IDENTIFIKASI FAKTOR PENYEBAB KETERLAMBATAN PELAKSANAAN PROYEK KONSTRUKSI JALAN BATAS KOTA BUKIT TINGGI - LUBUK SIKAPING BATAS SUMUT TESIS.

IDENTIFIKASI FAKTOR PENYEBAB KETERLAMBATAN PELAKSANAAN PROYEK KONSTRUKSI JALAN BATAS KOTA BUKIT TINGGI - LUBUK SIKAPING BATAS SUMUT TESIS. IDENTIFIKASI FAKTOR PENYEBAB KETERLAMBATAN BATAS KOTA BUKIT TINGGI - LUBUK SIKAPING BATAS SUMUT TESIS Oleh : FAKULTAS TEKNIK-UNIVERSITAS ANDALAS 2017 IDENTIFIKASI FAKTOR PENYEBAB KETERLAMBATAN BATAS KOTA

Lebih terperinci

ANALISIS FAKTOR PENYEBAB KETERLAMBATAN PADA PROYEK KONSTRUKSI JALAN DI KOTAMADYA KUPANG

ANALISIS FAKTOR PENYEBAB KETERLAMBATAN PADA PROYEK KONSTRUKSI JALAN DI KOTAMADYA KUPANG ANALISIS FAKTOR PENYEBAB KETERLAMBATAN PADA PROYEK KONSTRUKSI JALAN DI KOTAMADYA KUPANG Sandro Fanggidae, I Putu Artama Wiguna Program Studi Magister Manajemen Teknologi Bidang Keahlian Manajemen Proyek

Lebih terperinci

BAB I PENDAHULUAN. dari hari ke hari. Oleh karenanya strategi menentukan harga penawaran menjadi

BAB I PENDAHULUAN. dari hari ke hari. Oleh karenanya strategi menentukan harga penawaran menjadi 1 BAB I PENDAHULUAN 1.1. Latar Belakang Tingkat kompetisi di dunia bisnis konstruksi terus meningkat secara tajam dari hari ke hari. Oleh karenanya strategi menentukan harga penawaran menjadi sangat penting

Lebih terperinci

KAJIAN FAKTOR-FAKTOR YANG MEMPENGARUHI KUALITAS PROYEK PEMBANGUNAN BANGUNAN GEDUNG NEGARA

KAJIAN FAKTOR-FAKTOR YANG MEMPENGARUHI KUALITAS PROYEK PEMBANGUNAN BANGUNAN GEDUNG NEGARA KAJIAN FAKTOR-FAKTOR YANG MEMPENGARUHI KUALITAS PROYEK PEMBANGUNAN BANGUNAN GEDUNG NEGARA Chandra 1 dan Yohanes LD. Adianto 2 1 Mahasiswa Program Magister Teknik Sipil Universitas Katolik Parahyangan Bandung

Lebih terperinci

III. METODE PENELITIAN

III. METODE PENELITIAN 16 III. METODE PENELITIAN 3.1. Kerangka Penelitian Sebagai salah satu perusahaan yang bergerak dalam bidang jasa perkreditan motor PT. Summit Oto Finance Cabang Bogor harus bersaing dengan perusahaan perkreditan

Lebih terperinci

OLEH : FITRI SUHARIYADI NIM:

OLEH : FITRI SUHARIYADI NIM: IDENTIFIKASI DAN ANALISA FAKTOR KRITIS KEBERHASILAN PADA IMPLEMENTASI PROYEK BOT : INFRASTRUKTUR JALAN TOL TESIS MAGISTER 'Karya tulis sebagai salah satu syarat untuk memperoleh gelar Magister dari Institut

Lebih terperinci

FAKTOR-FAKTOR PADA MANAJER PROYEK OWNER YANG BERPENGARUH TERHADAP PENINGKATAN KINERJA BIAYA PROYEK PRASARANA JALAN TESIS

FAKTOR-FAKTOR PADA MANAJER PROYEK OWNER YANG BERPENGARUH TERHADAP PENINGKATAN KINERJA BIAYA PROYEK PRASARANA JALAN TESIS No. 064/FT.01/TESIS/06/2007 FAKTOR-FAKTOR PADA MANAJER PROYEK OWNER YANG BERPENGARUH TERHADAP PENINGKATAN KINERJA BIAYA PROYEK PRASARANA JALAN TESIS Oleh LYDIA DARMIYANTI 64 04 01 03 98 PROGRAM STUDI TEKNIK

Lebih terperinci

The Influence of Communication Supervisor on Job Satisfaction and Affective Commitment Organization. Abstract

The Influence of Communication Supervisor on Job Satisfaction and Affective Commitment Organization. Abstract The Influence of Communication Supervisor on Job Satisfaction and Affective Commitment Organization Abstract This study was conducted to verificate communication supervisor and its impact on job satisfaction

Lebih terperinci

BAB II LANDASAN TEORI

BAB II LANDASAN TEORI BAB II LANDASAN TEORI 2.1. KONSEP DAN DEFINISI JASA Keanekaragaman makna dalam hal pemakaian istilah service dijumpai dalam literatur manajemen. Namun demikian, secara garis besar konsep service mengacu

Lebih terperinci

ANALISIS PENGARUH BUDAYA ORGANISASI DAN LINGKUNGAN KERJA TERHADAP KINERJA KARYAWAN PTPN IX PABRIK GULA TASIKMADU

ANALISIS PENGARUH BUDAYA ORGANISASI DAN LINGKUNGAN KERJA TERHADAP KINERJA KARYAWAN PTPN IX PABRIK GULA TASIKMADU ANALISIS PENGARUH BUDAYA ORGANISASI DAN LINGKUNGAN KERJA TERHADAP KINERJA KARYAWAN PTPN IX PABRIK GULA TASIKMADU PUBLIKASI ILMIAH Diajukan Untuk Memenuhi Tugas dan Syarat-syarat Guna Memperoleh Gelar Sarjana

Lebih terperinci

ANALISA RESIKO TEKNIS YANG MEMPENGARUHI KINERJA WAKTU PROYEK PEMBANGUNAN PENGAMAN PANTAI DI PROVINSI SULAWESI BARAT

ANALISA RESIKO TEKNIS YANG MEMPENGARUHI KINERJA WAKTU PROYEK PEMBANGUNAN PENGAMAN PANTAI DI PROVINSI SULAWESI BARAT ANALISA RESIKO TEKNIS YANG MEMPENGARUHI KINERJA WAKTU PROYEK PEMBANGUNAN PENGAMAN PANTAI DI PROVINSI SULAWESI BARAT Anwar 1) dan Tri Joko Wahyu Adi 2) 1) Program Studi Magister Manajemen Teknologi, Institut

Lebih terperinci

BAB 3 METODE PENELITIAN

BAB 3 METODE PENELITIAN BAB 3 METODE PENELITIAN 3.1 Pendahuluan Bab ini memaparkan mengenai perancangan penelitian yang digunakan untuk mencapai tujuan dalam penulisan ini. Metode yang digunakan dimulai dari mengidentifikasi

Lebih terperinci

Fielda Roza, Alizar Hasan, M. Nursyaifi Yulius Magister Teknik Sipil Pasca Sarjana Universitas Bunga Hatta.

Fielda Roza, Alizar Hasan, M. Nursyaifi Yulius Magister Teknik Sipil Pasca Sarjana Universitas Bunga Hatta. ANALISIS FAKTOR-FAKTOR PENYEBAB KETIDAKTEPATAN PERHITUNGAN BIAYA PROYEK PADA PROSES PERENCANAAN OLEH KONSULTAN PERENCANA (Studi Kasus Konsultan Perencana di Kota Padang) Fielda Roza, Alizar Hasan, M. Nursyaifi

Lebih terperinci

Jurnal Manajemen ISSN Pascasarjana Universitas Syiah Kuala 7 Pages pp

Jurnal Manajemen ISSN Pascasarjana Universitas Syiah Kuala 7 Pages pp ISSN 2302-0199 7 Pages pp. 54-60 PENGARUH PENGGUNAAN SISTEM INFORMASI DAN LINGKUNGAN KERJA TERHADAP MOTIVASI KERJA SERTA DAMPAKNYA PADA KINERJA PEGAWAI KANTOR KEMENTERIAN AGAMA KABUPATEN ACEH BARAT DAYA

Lebih terperinci