USULAN DESIGN SUB LINE TIPE BE 0: STUDI KASUS PADA PT XYZ

Ukuran: px
Mulai penontonan dengan halaman:

Download "USULAN DESIGN SUB LINE TIPE BE 0: STUDI KASUS PADA PT XYZ"

Transkripsi

1 USULAN DESIGN SUB LINE TIPE BE 0: STUDI KASUS PADA PT XYZ Dyah Budiastuti 1 ; Teguh Adhi Pribadi 2 ABSTRACT A long with the increasing of market demand on XYZ company product, it will be opened a new design sub line in Surabaya. The purpose of this article is to give working station design suggestion and design sub line working element for production capacity 450 unit/day and measuring efficiency on every working station. That is why, it need a follow up research to get the description of the problems. The problems can be identified after that and then start with data collection that consist of company general data, working element data, and working measure data that collect from direct measurement using stopwatch. After the data is collected, the next step is process data to be use as a basic planning in developing working station. Keywords: design, sub line design ABSTRAK Seiring dengan permintaan pasar yang meningkat terhadap produk PT XYZ maka akan dibuka jalur perakitan baru di Surabaya. Artikel bertujuan untuk memberikan usulan desain stasiun kerja dan elemen kerja lini perakitan (sub line) untuk kapasitas produksi 450 unit/hari dan mengukur efisiensi pada tiap stasiun kerja. Oleh karena itu, diperlukan penelitian pendahuluan untuk mendapatkan gambaran masalah yang ada. Setelah itu, masalah dapat diidentifikasikan kemudian dimulai kegiatan pengumpulan data yang antara lain terdiri dari data umum perusahaan, data elemen kerja, dan data pengukuran kerja yang didapat dari pengukuran langsung dengan stopwatch. Setelah data terkumpul, langkah selanjutnya adalah mengolah data untuk digunakan sebagai dasar perencanaan dalam pembentukan stasiun kerja. Kata kunci: desain, lini perakitan 1 Staf Pengajar Jurusan Teknik Industri, Fakultas Teknik, UBiNus, Jakarta 2 Sarjana Teknik, Jurusan Teknik Industri, Fakultas Teknik, UBiNus, Jakarta 30

2 PENDAHULUAN PT XYZ merupakan bagian dari PT Astra International yang bergerak di bidang perakitan sepeda motor dan saat ini merupakan pabrik perakitan sepeda motor dengan jumlah produksi terbesar di seluruh Indonesia. Bersamaan dengan kebijakan pemerintah dalam hal lokalisasi komponen, pengembangan proses produksi sepeda motor mulai diarahkan dari tingkat perakitan ketingkat full manufacturing. Sejalan dengan berkembangnya teknologi yang sangat pesat, khususnya dalam bidang otomotif, menyebabkan persaingan antara perusahaan/industri yang bergerak di bidang otomotif semakin ketat. Hal itu membuat masing-masing perusahaan harus meningkatkan kepekaan akan peluang menghasilkan produk baru dan tidak lupa mengembangkan yang sudah ada. Pengkajian yang lebih mendalam mengarah bagaimana memberikan kelebihan pada suatu produk mengikuti selera konsumen yang terus berubah sesuai dengan perkembangan zaman. Melihat kecenderungan permintaan pasar yang terus meningkat terhadap produk PT XYZ, muncul pemikiran untuk membuka jalur perakitan baru di Surabaya dengan salah satu tujuan untuk memasok kebutuhan pasar di daerah Indonesia Timur. Ide itu berakibat pada diperlukannya perencanaan stasiun kerja dan elemen kerja (sub line) yang baru, khususnya untuk kapasitas produksi 450 unit/hari. PEMBAHASAN Untuk merealisasikan rencana pembukaan jalur baru ini, dilakukan analisis menggunakan empat metode yang ada, yaitu Largest Candidate Rule, Ranked Positional Weight, J-Wagon, dan Comsoal dengan batasan sebagai berikut. 1. Penyesuaian elemen kerja didasarkan pada flow process yang dipakai di plant Sunter. 2. Kapasitas produksi ditentukan 450 unit/hari. 3. Jam kerja wib. a. Istirahat 1 jam b. Persiapan awal 10 menit c. Persiapan akhir 10 menit d. Total waktu kerja efektif = detik/hari Metode Largest Candidate Rule memprioritaskan operasi yang memiliki jumlah waktu yang lebih besar untuk lebih dahulu dikelompokan dalam stasiun. Di samping itu, operasi dibedakan antara sisi kanan dan sisi kiri. Akibatnya, beberapa operasi dapat dikelompokan dalam kedua belah sisi sehingga stasiun kerja juga dipisahkan dalam dua sisi. Usulan Design Sub Line (Dyah Budiastuti; Teguh Adhi Pribadi) 31

3 Metode Ranked Positional Weight memprioritaskan elemen kerja berdasarkan masing-masing nilai RPW dari operasi dan operasi yang memiliki nilai RPW lebih besar mendapat prioritas utama. Metode J-Wagon memprioritaskan elemen kerja berdasarkan jumlah elemen yang bergantung pada elemen itu sendiri dan elemen yang memiliki waktu lebih besar pada elemen yang memiliki jumlah elemen pengikut yang sama mendapat prioritas utama. Stasiun kerja terbaik dipilih dengan memperhatikan pemerataan beban kerja di setiap stasiun kerja. Metode Comsoal memprioritaskan elemen yang tidak memiliki elemen pendahulu dengan nilai probabilitas terbesar, antara probabilitas waktu baku dan probabilitas RPW. Gambar 1 sampai dengan Gambar 4 berikut memperlihatkan prosedur yang dilakukan untuk menganalisis masing-masing metode. 32

4 START Urutkan elemen pekerjaaan dalam tabel berdasarkan waktu terbesar hingga terkecil Pilih elemen kerja dengan waktu baku terbesar Pilih elemen kerja dengan waktu baku terbesar berikutnya TIDAK Data memenuhi Precedence diagram? YA YA TIDAK Data menyebabkan jumlah waktu stasiun kerja melebihi cycle time Data memenuhi Precedence diagram? YA YA TIDAK Masukkan elemen kerja ke dalam pembentukan stasiun kerja Hapuskan elemen terpilih dari dalam tabel Pilih elemen berikutnya yang tidak melebihi cycle time sesuai urutan dalam tabel YA Masih adakah elemen yang dapat ditambahkan tanpa melebihi cycle time TIDAK Apakah semua elemen telah terpilih? TIDAK Lanjutkan ke pembentukan stasiun kerja berikutnya YA STOP Gambar 1 Prosedur Metode Largest Candidate Rule Usulan Design Sub Line (Dyah Budiastuti; Teguh Adhi Pribadi) 33

5 START Hitung nilai RPW untuk tiap elemen Urutkan elemen pekerjaaan dalam tabel berdasarkan nilai RPW terbesar hingga terkecil Pilih elemen kerja dengan nilai RPW terbesar TIDAK TIDA AA Pilih elemen kerja dengan nilai RPW terbesar berikutnya Data memenuhi Precedence diagram? Y YA A YA A YA TIDA TIDAK AA Data memenuhi Precedence diagram? Y YA A Data menyebabkan jumlah waktu stasiun kerja melebihi cycle time TIDAK TIDA AA Masukkan elemen kerja ke dalam pembentukan stasiun kerja Hapuskan elemen terpilih dari dalam tabel Pilih elemen berikutnya yang tidak melebihi cycle time sesuai urutan dalam tabel YA Y A Masih adakah elemen yang dapat ditambahkan tanpa melebihi cycle time Apakah semua elemen telah terpilih? TIDA TIDAK AA TIDAK TIDA AA Lanjutkan ke pembentukan stasiun kerja berikutnya STOP Y YA A Gambar 2 Prosedur Metode Ranked Positional Weight 34

6 START Hitung nilai RPW untuk tiap elemen Hitung probabilitas RPW dan waktu elemen untuk masing-masing elemen kerja Buat tabel A untuk tiap elemen bersama dengan elemen yang mendahulunya Buat tabel B untuk tiap elemen yang tidak memiliki elemen pendahulu Buat tabel C untuk elemen kerja yang tidak menyebabkan jumlah waktu elemen-elemen pembentuk stasiun melebihi cycle time Lanjutkan pembentukan stasiun berikutnya Tidak Tidak Apakah ada elemen dalam tabel C? Ya YA A Prioritaskan elemen kerja yang memiliki probabilitas terbesar pada prioritas pertama Masukkan elemen pekerjaan dengan prioritas pertama dalam stasiun Hapuskan elemen terpilih dari tabel A Apakah semua elemen telah terpilih? Tidak Tidak STOP Ya YA A Gambar 3 Prosedur Metode Comsoal Usulan Design Sub Line (Dyah Budiastuti; Teguh Adhi Pribadi) 35

7 START Hitung jumlah elemen yang bergantung pada tiap elemen kerja Urutkan elemen pekerjaan berdasarkan jumlah elemen yang bergantung pada tiap elemen kerja dari yang terbesar hingga terkecil Prioritaskan elemen yang memiliki waktu terbesar pada jumlah elemen bergantung yang sama Prioritaskan elemen yang memiliki waktu terbesar pada kolom yang sama Urutkan elemen pekerjaan dalam sebuah tabel berdasarkan ketentuan di atas A Gambar 4 Prosedur Metode J-Wagon 36

8 A Pilih elemen dengan urutan pertama Pilih elemen dengan urutan berikutnya Tidak Data memenuhi precedence diagram? Ya Ya Data menyebabkan jumlah waktu stasiun melebihi cycle time? Tidak Data memenuhi precedence diagram? Ya Tidak Masukkan elemen ke dalam pembentukan stasiun Hapuskan elemen terpilih dari dalam tabel Pilih elemen berikutnya yang tidak melebihi cycle time sesuai urutan dalam tabel Ya Masih ada elemen yang dapat ditambahkan tanpa melebihi cycle time? Tidak Apakah semua elemen telah terpilllih Tidak Lanjutkan pembentukan stasiun berikutnya STOP Ya Gambar 4 Prosedur J-Wagon (Lanjutan) Usulan Design Sub Line (Dyah Budiastuti; Teguh Adhi Pribadi) 37

9 Hasil analisis keempat metode, diperlihatkan pada tabel berikut. 1. Metode Largest Candidate Rule Tabel 1 Urutan Operasi Berdasarkan Waktu Baku Terbesar No Nama Operasi Waktu Baku (detik) Operasi yang Mendahului 20 Pasang wire hearness Scan bercode, check Pasang cushion R rear set RH 43 Pasang cushion L rear set Pasang stay start magnetic switch RH 44 Pasang rod Rr brake RH 24 Sambung kabel switch assy ke coil RH 6 Operasi press mesin Pasang rectifier comp regulate RH 41 Pasang stay CDI unit Pasang bell steel under Angkat engine, letakkan pada jig ,22,25,31,33 36,37,41,42,43 44,47,48,51 Sisi Operasi 1 Angkat F/B, check Pasang magnetic starter RH 37 Pasang BF 6mm Pasang winker relay Pasang coil assy ,19 RH 38 Pasang unit comp CDI Jepit kabel W/H RH 14 Kaitkan spring D ke hook main Letakan F/B pada jig Pasang case battery Pasang NF 6mm (nut coil assy) Kaitkan magnetic starter RH 34 Pasang grommet AC case Pasang air cleaner assy ,19-15 Pasang ps 3x25 ke main stand Operasi numbering mesin Pasang pedal comp brake Pasang pipe Rr brake pivot Pasang race st top dan bottom Pasang grommet cord Selipkan barcode, geser

10 Tabel 1 Urutan Operasi Berdasarkan Waktu Baku Terbesar (lanjutan) 23 Pasang switch assy stop RH 40 Sambung kabel CDI ke winker relay 11 Pasang stand comp main Pasang BF 6mm Pasang BF 6mm RH 27 Pasang NF 6mm RH 17 Pasang rubber stand stopper Pasang BF 6x Pasang BW 8x Pasang tank comp fuel Balik F/B ,17-53 Pasang bar comp stand Pasang catch comp seat Balik F/B Tempelkan label helmat holder Sambungkan kabel tube tank Sambungkan W/H ke rectifier ,28 RH comp 12 Kaitkan hook main stand spring Kaitkan spring D ke stand comp Rapikan tube tank comp fuel Rapikan kabel pada F/B Total Tabel 2 Lini Perakitan Stasiun Kerja Usulan Berdasarkan Metode Largest Candidate Rule Stasiun Operasi Waktu Baku Jumlah waktu Efisiensi Lini I % II % Usulan Design Sub Line (Dyah Budiastuti; Teguh Adhi Pribadi) 39

11 Tabel 2 Lini Perakitan Stasiun Kerja Usulan Berdasarkan Metode Largest Candidate Rule (lanjutan) III IV % RH 92.39% V % VI VII RH 96.53% RH 95.43% 40

12 Tabel 2 Lini Perakitan Stasiun Kerja Usulan Berdasarkan Metode Largest Candidate Rule (lanjutan) VIII IX % 35.79% Tabel 3 Mean Square Idle Time Tiap Operator Berdasarkan Metode Largest Candidate Rule Stasiun Mean Square Idle Time Total Berdasarkan tabel dapat dilihat bahwa jumlah stasiun kerja adalah sebanyak 8 buah sehingga dapat dihitung efesiensi lini total sebagai berikut. Efisiensi Lini Total = [ (Jumlah total waktu seluruh stasiun kerja/(banyak stasiun x cycle time) ] x 100% Efisiensi Lini Total = x x 100% = 85.91% Dengan Mean Square Idle Time operator = = detik Usulan Design Sub Line (Dyah Budiastuti; Teguh Adhi Pribadi) 41

13 2. Metode Ranked Positional Weight Tabel 4 Urutan Operasi Berdasarkan Nilai RPW Terbesar No Nama Operasi Waktu Baku (detik) RPW Operasi yang Mendahului Sisi Operasi 1 Angkat F/B, check Operasi numbering mesin Scan bercode, check Selipkan barcode, geser Pasang race st top dan bottom 6 Operasi press mesin Letakan F/B pada jig Balik F/B Pasang pedal comp brake Pasang pipe Rr brake pivot Pasang stand comp main Kaitkan hook main stand spring 14 Kaitkan spring D ke hook main 15 Pasang ps 3x25 ke main stand 13 Pasang bell steel under Kaitkan spring D ke stand comp 17 Pasang rubber stand stopper 19 Balik F/B ,17-20 Pasang wire hearness Pasang coil assy ,19 RH 26 Pasang magnetic starter RH 38 Pasang unit comp CDI Pasang NF 6mm RH 23 Pasang switch assy stop RH 39 Pasang winker relay Pasang stay start magnetic RH switch 24 Sambung kabel switch assy RH ke coil 34 Pasang grommet AC case Pasang rectifier comp RH regulate 42 Pasang cushion R rear set RH 40 Sambung kabel CDI ke winker relay

14 Tabel 4 Urutan Operasi Berdasarkan Nilai RPW Terbesar (lanjutan) 43 Pasang cushion L rear set Pasang grommet cord Pasang rod Rr brake RH 35 Pasang air cleaner assy ,19-45 Pasang tank comp fuel Pasang stay CDI unit Pasang case battery Kaitkan magnetic starter RH 50 Pasang catch comp seat Pasang BF 6mm Rapikan tube tank comp fuel 25 Jepit kabel W/H RH 22 Pasang NF 6mm (nut coil assy) 33 Pasang BF 6mm Pasang BF 6mm RH 51 Pasang BF 6x Tempelkan label helmat holder 47 Sambungkan kabel tube tank 18 Sambungkan W/H ke ,28 RH rectifier comp 31 Rapikan kabel pada F/B Angkat engine, letakkan pada jig ,22,25,31,33 36,37,41,42,43 44,47,48,51 53 Pasang bar comp stand Pasang BW 8x Total Tabel 5 Lini Perakitan Stasiun Kerja Usulan Berdasarkan Nilai RPW Terbesar Stasiun Operasi Waktu Baku Waktu Kumulatif Efisiensi I % Usulan Design Sub Line (Dyah Budiastuti; Teguh Adhi Pribadi) 43

15 Tabel 5 Lini Perakitan Stasiun Kerja Usulan Berdasarkan Nilai RPW Terbesar (lanjutan) II III IV V VI VII % % % % % % 44

16 Tabel 5 Lini Perakitan Stasiun Kerja Usulan Berdasarkan Nilai RPW Terbesar (lanjutan) VIII IX % % Tabel 6 Mean Square Idle Time Tiap Operator Berdasarkan Nilai RPW Terbesar Operator Mean Square Idle Time Total Efisiensi Lini Total = [ (Jumlah total waktu seluruh stasiun kerja/(banyak stasiun x cycle time) ] x 100% Efisiensi Lini Total = Mean Square Idle Time = 9x61.33 X 100% = 85.91% = detik Usulan Design Sub Line (Dyah Budiastuti; Teguh Adhi Pribadi) 45

17 3. Metode J-Wagon No Nama Operasi Waktu Baku (detik) Tabel 7 Urutan Operasi Berdasarkan Jumlah Elemen yang Bergantung Jumlah Operasi yang bergantung Operasi yang mendahului Sisi Operasi 1 Angkat F/B, check Operasi numbering mesin Scan bercode, check Selipkan barcode, geser Pasang race st top dan bottom 6 Operasi press mesin Letakan F/B pada jig Balik F/B Pasang pedal comp brake Pasang pipe Rr brake pivot Pasang stand comp main Kaitkan hook main stand spring 14 Kaitkan spring D ke hook main 15 Pasang ps 3x25 ke main stand 16 Kaitkan spring D ke stand comp 13 Pasang bell steel under Pasang rubber stand stopper Balik F/B ,17-20 Pasang wire hearness Pasang magnetic starter RH 21 Pasang coil assy ,19 RH 38 Pasang unit comp CDI Pasang grommet AC case Pasang NF 6mm RH 29 Pasang stay start magnetic RH switch 39 Pasang winker relay Pasang air cleaner assy ,19-49 Pasang grommet cord Pasang switch assy stop RH 45 Pasang tank comp fuel Sambung kabel switch assy ke coil RH 46

18 Tabel 7 Urutan Operasi Berdasarkan Jumlah Elemen yang Bergantung (lanjutan) 28 Pasang rectifier comp RH regulate 32 Pasang case battery Kaitkan magnetic starter RH 40 Sambung kabel CDI ke winker relay 50 Pasang catch comp seat Rapikan tube tank comp fuel 42 Pasang cushion R rear set RH 43 Pasang cushion L rear set Pasang rod Rr brake RH 41 Pasang stay CDI unit Pasang BF 6mm Jepit kabel W/H RH 22 Pasang NF 6mm (nut coil assy) 33 Pasang BF 6mm Pasang BF 6mm RH 51 Pasang BF 6x Tempelkan label helmat holder 47 Sambungkan kabel tube tank 18 Sambungkan W/H ke ,28 RH rectifier comp 31 Rapikan kabel pada F/B Angkat engine, letakkan pada jig ,22,25,31,33 36,37,41,42,43 44,47,48,51 53 Pasang bar comp stand Pasang BW 8x Total Usulan Design Sub Line (Dyah Budiastuti; Teguh Adhi Pribadi) 47

19 Tabel 8 Lini Perakitan Stasiun Kerja Usulan Berdasarkan Metode J-Wagon Stasiun Operasi Waktu Baku Waktu Kumulatif Efisiensi I % II III IV V % 95.91% RH 99.87% RH 98.86% 48

20 Tabel 8 Lini Perakitan Stasiun Kerja Usulan Berdasarkan Metode J-Wagon (lanjutan) VI VII VIII % RH 95.48% 94.93% Tabel 9 Mean Square Idle Time Tiap Operator Berdasarkan Metode J-Wagon Stasiun Mean Square Idle Time Total Usulan Design Sub Line (Dyah Budiastuti; Teguh Adhi Pribadi) 49

21 Efisiensi Lini Total = [ (Jumlah total waktu seluruh stasiun kerja/(banyak stasiun x cycle time) ] x 100% Efisiensi Lini total = x X 100% = 96.65% Mean Square Idle Time = = detik 8 4. Metode Comsoal Probabilitas Waktu Baku = n 1 / n = / = Probabilitas RPW = n 1 / n = / = No Nama Operasi Waktu Baku (detik) Tabel 10 Urutan Operasi Berdasarkan Probabilitas Maks. Terbesar RPW Probabilitas Waktu Baku Probabilitas RPW Probabilitas Maks 20 Pasang wire hearness Angkat F/B, check Operasi numbering mesin Scan bercode, check Selipkan barcode, geser Pasang race st top dan bottom 6 Operasi press mesin Letakan F/B pada jig Balik F/B Pasang pedal comp brake Pasang pipe Rr brake pivot Pasang stand comp main Kaitkan hook main stand spring 14 Kaitkan spring D ke hook main 15 Pasang ps 3x25 ke main stand 13 Pasang bell steel under Kaitkan spring D ke stand comp

22 Tabel 10 Urutan Operasi Berdasarkan Probabilitas Maks. Terbesar (lanjutan) 17 Pasang rubber stand stopper Balik F/B Pasang cushion R rear set Pasang cushion L rear set Pasang stay start magnetic switch 44 Pasang rod Rr brake Sambung kabel switch assy ke coil 28 Pasang rectifier comp regulate 41 Pasang stay CDI unit Angkat engine, letakkan pada jig 26 Pasang magnetic starter Pasang BF 6mm Pasang winker relay Pasang coil assy Pasang unit comp CDI Jepit kabel W/H Pasang case battery Pasang NF 6mm (nut coil assy) 30 Kaitkan magnetic starter Pasang grommet AC case Pasang air cleaner assy Pasang grommet cord Pasang switch assy stop Sambung kabel CDI ke winker relay 33 Pasang BF 6mm Pasang BF 6mm Pasang NF 6mm Pasang BF 6x Pasang tank comp fuel Pasang BW 8x Pasang catch comp seat Pasang bar comp stand Tempelkan label helmat holder 47 Sambungkan kabel tube tank 18 Sambungkan W/H ke rectifier comp Usulan Design Sub Line (Dyah Budiastuti; Teguh Adhi Pribadi) 51

23 Tabel 10 Urutan Operasi Berdasarkan Probabilitas Maks. Terbesar (lanjutan) 46 Rapikan tube tank comp fuel 31 Rapikan kabel pada F/B Total Tabel 11 Lini Perakitan Stasiun Kerja Usulan Berdasarkan Metode Comsoal Stasiun Operasi Waktu baku Waktu kumulatif Efisiensi I % II III IV V % % RH 92.39% 98.47% 52

24 Tabel 11 Lini Perakitan Stasiun Kerja Usulan Berdasarkan Metode Comsoal (lanjutan) VI VII VIII IX RH 96.56% RH 84.82% 86.37% 35.79% Tabel 12 Mean Square Idle Time Berdasarkan Metode Comsoal Stasiun Mean Square Idle Time Total Usulan Design Sub Line (Dyah Budiastuti; Teguh Adhi Pribadi) 53

25 Efisiensi Lini Total = [ (Jumlah total waktu seluruh stasiun kerja/(banyak stasiun x cycle time) ] x 100% Efisiensi Lini Total = x X 100% = 85.91% Mean Square Idle Time = = detik Dari hasil pengumpulan data yang telah diolah, dapat dibuat suatu tabel perbandingan efisiensi performansi untuk masing-masing metode penyeimbangan lini perakitan yang terdiri atas perbandingan nilai efisiensi lini yang menunjukkan performansi stasiun kerja dan perbandingan nilai Mean Square Idle Time yang menunjukkan performansi operator. Tabel 13 Perbandingan Efisiensi Lini Hasil Metode Penyeimbangan Lini Metode Largest Candid ate Rule Ranked Position al Weight J Wagon COMS OAL Jumlah Stasiun Kerja Efisiensi Stasiun Kerja (%) Efisi ensi Lini Total Tabel 14 Perbandingan Mean Square Idle Time Operator Hasil Metode Penyeimbangan Lini Mean Square Idle Time (detik 2 ) Operator Largest Ranked Candidate Positional J Wagon COMSOAL Rule Weight

26 Tabel 14 Perbandingan Mean Square Idle Time Operator Hasil Metode Penyeimbangan Lini (lanjutan) Total Mean Square Idle Time Dilihat dari tabel perbandingan efisiensi lini dan Mean Square Idle Time dari masing-masing metode yang telah dibuat, terlihat bahwa usulan lini perakitan menggunakan metode penyeimbangan lini J-Wagon adalah yang terbaik. Hal itu didasarkan pada hal berikut. Tingkat efisiensi lini yang terbesar, yaitu 96.65%. Performansi operator yang ditunjukkan oleh Mean Square Idle Time operator yang bukan hanya rendah namun juga cukup merata untuk setiap operator. Berikut ini merupakan hasil pembentukan stasiun kerja berdasarkan metode J- Wagon. Stasiun No Nama Operasi Waktu Total Efisiensi I Angkat F/B, check Operasi numbering mesin Scan barcode, check Selipkan barcode, geser Pasang race st top dan bottom Pasang grommet AC case 94.46% II III Operasi press mesin Letakan F/B pada jig Balik F/B Pasang pedal comp brake Pasang pipe Rr brake pivot Pasang stand comp main Kaitkan hook main stand spring Kaitkan spring D ke hook main Pasang ps 3x25 ke main stand Kaitkan spring D ke stand comp % Usulan Design Sub Line (Dyah Budiastuti; Teguh Adhi Pribadi) 55

27 IV V VI VII VIII Pasang ball steel under Pasang rubber stand stopper Balik F/B Pasang unit comp CDI Pasang winker relay Pasang air cleaner assy Pasang wire hearness Pasang magnetic starter Pasang coil assy Pasang NF 6mm Pasang switch assy stop Pasang stay start magnetic switch Pasang tank comp fuel Sambung kabel switch assy ke coil Pasang rectifier comp regulate Kaitkan magnetic starter Pasang grommet cord Pasang case battery Sambung kabel CDI ke winker relay Pasang catch comp seat Rapikan tube tank comp fuel Pasang cushion L rear set Pasang stay CDI unit Pasang cushion R rear set Pasang rod Rr brake Jepit kabel W/H Pasang BF 6mm (air cleaner assy) Sambungkan kabel tube tank Sambungkan W/H ke rectifier comp Pasang BF 6mm (air cleaner assy) Pasang NF 6mm (nut coil assy) Pasang BF 6mm (case battery) Pasang BF 6x12 (catch comp seat) Tempelkan label helmat holder Rapikan kabel pada F/B Angkat engine, letakkan pada jig Pasang bar comp stand Pasang BW 8x % RH 99.87% RH 98.86% 98.96% RH 95.48% 94.93% 56

28 Stasiun Mean Square Idle Time Efisiensi Lini Total = [ (Jumlah total waktu seluruh stasiun kerja/(banyak stasiun x cycle time) ] x 100% Efisiensi Lini total = x X 100% = 96.65% Mean Square Idle Time = = detik PENUTUP Lini perakitan dengan metode J-Wagon ini akan lebih baik, bila dalam pengimplementasiannya memperhatikan aspek sebagai berikut. 1. Pemilihan dan pengaturan peralatan dan prasarana lainnya. 2. Pengaturan material handling. 3. Ergonomi dari masing-masing operator. Usulan Design Sub Line (Dyah Budiastuti; Teguh Adhi Pribadi) 57

29 DAFTAR PUSTAKA Barnes, Ralph M Motion and Time Study: Design and Measurement of Work. Los Angeles, California: John Wiley & Sons, Inc. Bedworth, David D. and James E Bailey Integrated Production Control System: Management, Analysis, Design. New York: John Wiley & Sons, Inc. Buffa, Elwood S. and Rakesh K. Sarin Modern Production/Operations Management. Eight Edition. University of California, Los Angeles: John Wiley & Sons. Groover, Mikell P Automation Production System and Computer-Integrated Manufacture. USA: Prentice Hall, Inc. Sutalaksana, Iftikar Z., Anggawisastra, dan Tjakraatmadja Teknik Tata Cara Kerja. Bandung: Departemen Teknik Industri ITB. Walpole, Ronald E Pengantar Statistika. Edisi ke-3. Jakarta: Gramedia. 58

Analisis Kebutuhan Man Power dan Line Balancing Jalur Supply Body 3 D01N PT. Astra Daihatsu Motor Karawang Assembly Plant (KAP)

Analisis Kebutuhan Man Power dan Line Balancing Jalur Supply Body 3 D01N PT. Astra Daihatsu Motor Karawang Assembly Plant (KAP) Analisis Kebutuhan Man Power dan Line Balancing Jalur Supply Body 3 D01N PT. Astra Daihatsu Motor Karawang Assembly Plant (KAP) Umi marfuah 1), Cholis Nur Alfiat 2) Teknik Industri Universitas Muhammadiyah

Lebih terperinci

APLIKASI PREDETERMINED TIME SYSTEM DAN RANKED POSITIONAL WEIGHT PADA OPTIMALISASI LINTASAN PRODUKSI UPPER-SHOE DI PT. ECCO INDONESIA, SIDOARJO

APLIKASI PREDETERMINED TIME SYSTEM DAN RANKED POSITIONAL WEIGHT PADA OPTIMALISASI LINTASAN PRODUKSI UPPER-SHOE DI PT. ECCO INDONESIA, SIDOARJO B-2- APLIKASI PREDETERMINED TIME SYSTEM DAN RANKED POSITIONAL WEIGHT PADA OPTIMALISASI LINTASAN PRODUKSI UPPER-SHOE DI PT. ECCO INDONESIA, SIDOARJO Rina Lukiandari, Abdullah Shahab ITS Surabaya ABSTRAK

Lebih terperinci

PENINGKATAN EFISIENSI STASIUN KERJA DENGAN PENDEKATAN REGION LINE BALANCING ( STUDI KASUS DI PT. TRIANGLE MOTORINDO )

PENINGKATAN EFISIENSI STASIUN KERJA DENGAN PENDEKATAN REGION LINE BALANCING ( STUDI KASUS DI PT. TRIANGLE MOTORINDO ) PENINGKATAN EFISIENSI STASIUN KERJA DENGAN PENDEKATAN REGION LINE BALANCING ( STUDI KASUS DI PT. TRIANGLE MOTORINDO ) Haryo Santoso ) Abstrak Ketidakseimbangan alokasi elemen-elemen kerja pada Lintasan

Lebih terperinci

KESEIMBANGAN LINI PRODUKSI PADA PT PAI

KESEIMBANGAN LINI PRODUKSI PADA PT PAI KESEIMBANGAN LINI PRODUKSI PADA PT PAI Citra Palada Staf Produksi Industri Manufaktur, PT ASTRA DAIHATSU MOTOR HEAD OFFICE Jln. Gaya Motor III No. 5, Sunter II, Jakarta 14350 citra.palada@yahoo.com ABSTRACT

Lebih terperinci

BAB 3 METODE PENELITIAN. Berikut ini adalah diagram alir yang digunakan dalam penyelesaian studi kasus ini: Mulai

BAB 3 METODE PENELITIAN. Berikut ini adalah diagram alir yang digunakan dalam penyelesaian studi kasus ini: Mulai BAB 3 METODE PENELITIAN 3.1 Flowchart Metode Penelitian Berikut ini adalah diagram alir yang digunakan dalam penyelesaian studi kasus ini: Mulai Studi Pendahuluan: Pengamatan flow process produksi Assembly

Lebih terperinci

LINE BALANCING LINI PERAKITAN PRODUK TORCH LIGHT (STUDI KASUS PT ARISAMANDIRI PRATAMA)

LINE BALANCING LINI PERAKITAN PRODUK TORCH LIGHT (STUDI KASUS PT ARISAMANDIRI PRATAMA) LINE BALANCING LINI PERAKITAN PRODUK TORCH LIGHT (STUDI KASUS PT ARISAMANDIRI PRATAMA) Ratna Purwaningsih, Prima Hazairin Program Studi Teknik Industri Email : ratna_ti2005@yahoo.com Abstrak Line balancing

Lebih terperinci

BAB 2 LANDASAN TEORI

BAB 2 LANDASAN TEORI 20 BAB 2 LANDASAN TEORI 2.1 Tinjauan Pustaka 2.1.1 Teknik Pengukuran Data Waktu Jam Henti Di dalam penelitian ini, pengukuran waktu setiap proses operasi sangat dibutuhkan dalam penentuan waktu baku setiap

Lebih terperinci

BAB II LANDASAN TEORI

BAB II LANDASAN TEORI BAB II LANDASAN TEORI 2.1 Tinjauan Pustaka 2.1.1 Studi Gerak dan Waktu ( Barnes h.257 ) Studi Gerak dan Waktu merupakan suatu ilmu yang terdiri dari teknik-teknik dan prinsip-prinsip untuk mendapatkan

Lebih terperinci

BAB IV PENGUMPULAN DAN PENGOLAHAN DATA

BAB IV PENGUMPULAN DAN PENGOLAHAN DATA BAB IV PENGUMPULAN DAN PENGOLAHAN DATA 4.1 Gambaran Umum Perusahaan 4.1.1 Profil Perusahaan Nama Perusahaan : Industri Otomotif Sunter Alamat Perusahaan : Jl. Laksda Yos Sudarso, Sunter 1 Jakarta Status

Lebih terperinci

BAB 3 METODOLOGI PENELITIAN

BAB 3 METODOLOGI PENELITIAN 41 BAB 3 METODOLOGI PENELITIAN 3.1 Diagram Alir Observasi Lapangan Identifikasi Masalah Studi Kepustakaan Pengambilan Data Waktu Siklus Pengujian Waktu Siklus : 1. Uji Keseragaman Data 2. Uji Kenormalan

Lebih terperinci

BAB III METODOLOGI PENELITIAN. diperoleh dari hasil kerja praktek di industri otomotif sunter yaitu data cycle time

BAB III METODOLOGI PENELITIAN. diperoleh dari hasil kerja praktek di industri otomotif sunter yaitu data cycle time BAB III METODOLOGI PENELITIAN 3.1 Jenis dan Sumber Data Data yang digunakan adalah data primer dan data sekunder. Data primer diperoleh dari hasil kerja praktek di industri otomotif sunter yaitu data cycle

Lebih terperinci

Kata Kunci : Keseimbangan Lintasan, Metode Ranked Positional Weight, Produktivitas 1. PENDAHULUAN

Kata Kunci : Keseimbangan Lintasan, Metode Ranked Positional Weight, Produktivitas 1. PENDAHULUAN ANALISA PENINGKATAN EFISIENSI DAN PRODUKTIVITAS KERJA DENGAN PENDEKATAN METODE RANKED POSITIONAL WEIGHT (RPW) PADA PRODUK K25-6101 DI PT. BANSHU ELECTIC INDONESIA Edi Susanto 1, Asep Hermawan 1, Andriana

Lebih terperinci

BAB 2 LANDASAN TEORI

BAB 2 LANDASAN TEORI BAB 2 LANDASAN TEORI 2.1 Pengantar Menurut Baroto (2002, p192), aliran proses produksi suatu departemen ke departemen yang lainnya membutuhkan waktu proses produk tersebut. Apabila terjadi hambatan atau

Lebih terperinci

BAB 2 LANDASAN TEORI

BAB 2 LANDASAN TEORI BAB 2 LANDASAN TEORI 2.1 Peta Kerja Peta kerja adalah suatu alat yang menggambarkan kegiatan kerja secara sistematis dan jelas (biasanya kerja produksi). Lewat peta-peta ini kita bisa melihat semua langkah

Lebih terperinci

BAB V ANALISIS HASIL

BAB V ANALISIS HASIL BAB V ANALISIS HASIL Berdasarkan pengumpulan dan pengolahan data yang ada pada bab sebelumnya, maka akan dilakukan analisis guna mengetahui hasil yang lebih optimal. Pembahasan ini dilakukan untuk memberikan

Lebih terperinci

MENINGKATKAN EFISIENSI LINTASAN KERJA MENGGUNAKAN METODE RPW DAN KILLBRIDGE-WESTERN

MENINGKATKAN EFISIENSI LINTASAN KERJA MENGGUNAKAN METODE RPW DAN KILLBRIDGE-WESTERN 2017 Firman Ardiansyah E, Latif Helmy 16 MENINGKATKAN EFISIENSI LINTASAN KERJA MENGGUNAKAN METODE RPW DAN KILLBRIDGE-WESTERN Firman Ardiansyah Ekoanindiyo *, Latif Helmy * * Program Studi Teknik Industri

Lebih terperinci

ANALISIS LINE BALANCING PADA LINI PERAKITAN HANDLE SWITCH DI PT. X

ANALISIS LINE BALANCING PADA LINI PERAKITAN HANDLE SWITCH DI PT. X Profesionalisme Akuntan Menuju Sustainable Business Practice PROCEEDINGS ANALISIS LINE BALANCING PADA LINI PERAKITAN HANDLE SWITCH DI PT. X Didit Damur Rochman, Wiring Respati Caparina. Program Studi Teknik

Lebih terperinci

ANALISIS ASSEMBLY LINE BALANCING PRODUK HEAD LAMP TYPE K59A DENGAN PENDEKATAN METODE HELGESON-BIRNIE Studi Kasus PT. Indonesia Stanley electric

ANALISIS ASSEMBLY LINE BALANCING PRODUK HEAD LAMP TYPE K59A DENGAN PENDEKATAN METODE HELGESON-BIRNIE Studi Kasus PT. Indonesia Stanley electric ANALISIS ASSEMBLY LINE BALANCING PRODUK HEAD LAMP TYPE K59A DENGAN PENDEKATAN METODE HELGESON-BIRNIE Studi Kasus PT. Indonesia Stanley electric Abstrak Heru Saptono 1),Alif Wardani 2) JurusanTeknikMesin,

Lebih terperinci

BAB 4 METODOLOGI PEMECAHAN MASALAH

BAB 4 METODOLOGI PEMECAHAN MASALAH BAB 4 METODOLOGI PEMECAHAN MASALAH 4.1. Model Rumusan Masalah dan Pengambilan Keputusan Di dalam memecahkan masalah yang sedang dihadapi perusahaan, maka sebelumnya harus dilakukan pengamatan dan penelitian

Lebih terperinci

BAB II LANDASAN TEORI

BAB II LANDASAN TEORI BAB II LANDASAN TEORI 2.1 Pengertian Keseimbangan Lini Keseimbangan lini merupakan suatu metode penugasan sejumlah pekerjaan ke dalam stasiun kerja yang saling berkaitan dalam satu lini produksi sehingga

Lebih terperinci

PENULISAN ILMIAH SUGIANTO

PENULISAN ILMIAH SUGIANTO MEMPELAJARI KESEIMBANGAN LINI PERAKITAN (PROCESS ASSY WELDING) PEMBUATAN PART BOX ASSY BATTERY TIPE KVBS VARIO TECHNO 110CC DI PT ADHI WIJAYACITRA PENULISAN ILMIAH SUGIANTO 36409942 Diajukan Guna Melengkapi

Lebih terperinci

ANALISIS KESEIMBANGAN LINTASAN LINE PRODUKSI DRIVE ASSY DI PT. JIDECO INDONESIA

ANALISIS KESEIMBANGAN LINTASAN LINE PRODUKSI DRIVE ASSY DI PT. JIDECO INDONESIA ANALISIS KESEIMBANGAN LINTASAN LINE PRODUKSI DRIVE ASSY DI PT. JIDECO INDONESIA Sutarjo, ST. Sekolah Tinggi Teknologi Wastukancana Purwakarta Email : Sutarjo06@gmail.com Risris Nurjaman, MT. Dosen Universitas

Lebih terperinci

Analisa Keseimbangan Lintasan Dengan Menggunakan Metode Helgeson-Birnie (Ranked Positional Weight) Studi Kasus PT. D

Analisa Keseimbangan Lintasan Dengan Menggunakan Metode Helgeson-Birnie (Ranked Positional Weight) Studi Kasus PT. D Analisa Keseimbangan Lintasan Dengan Menggunakan Metode Helgeson-Birnie (Ranked Positional Weight) Studi Kasus PT. D Adi Kristianto Program Studi Teknik Industri, Fakultas Teknik, Universitas Sarjanawiyata

Lebih terperinci

Penulisan Ilmiah Anggit Setiyadi

Penulisan Ilmiah Anggit Setiyadi ANALISA KESEIMBANGAN LINTASAN PADA PROSES PERAKITAN BOX ASSY BATTERY TYPE KZRA FUEL INJECTION DI PT ADHI WIJAYACITRA Penulisan Ilmiah Anggit Setiyadi 30409425 Diajukan Guna Melengkapi Sebagian Syarat Dalam

Lebih terperinci

BAB 3 METODOLOGI PEMECAHAN MASALAH

BAB 3 METODOLOGI PEMECAHAN MASALAH BAB 3 METODOLOGI PEMECAHAN MASALAH 3.1 Diagram Alir Observasi lapangan Identifikasi masalah Pengumpulan data : 1. Data komponen. 2. Data operasi perakitan secara urut. 3. Data waktu untuk menyelesaikan

Lebih terperinci

BAB 2 LANDASAN TEORI

BAB 2 LANDASAN TEORI BAB 2 LANDASAN TEORI 2.1 Penelitian kerja dalam kaitannya dengan upaya peningkatan produktifitas. Analisa dan penelitian kerja adalah suatu aktifitas yang ditujukan untuk mempelajari prinsip-prinsip atau

Lebih terperinci

BAB V ANALISA DAN HASIL PEMBAHASAN

BAB V ANALISA DAN HASIL PEMBAHASAN 125 BAB V ANALISA DAN HASIL PEMBAHASAN 5.1 Hasil Analisis Dari Ketiga Metode Tabel 5.1 Hasil Perbandingan dari ketiga Metode METODE OBJEK PERCOBAAN 1 PERCOBAAN 2 Line Efficiency 91.37% 94.41% RPW Balance

Lebih terperinci

PERBAIKAN LINI FINISHING DRIVE CHAIN AHM OEM PADA PT FEDERAL SUPERIOR CHAIN MANUFACTURING DENGAN METODE KESEIMBANGAN LINI DAN METHODS TIME MEASUREMENT

PERBAIKAN LINI FINISHING DRIVE CHAIN AHM OEM PADA PT FEDERAL SUPERIOR CHAIN MANUFACTURING DENGAN METODE KESEIMBANGAN LINI DAN METHODS TIME MEASUREMENT Jurnal Teknik dan Ilmu Komputer PERBAIKAN LINI FINISHING DRIVE CHAIN AHM OEM PADA PT FEDERAL SUPERIOR CHAIN MANUFACTURING DENGAN METODE KESEIMBANGAN LINI DAN METHODS TIME MEASUREMENT Lina Gozali *, Lamto

Lebih terperinci

BAB 3 LANGKAH PEMECAHAN MASALAH

BAB 3 LANGKAH PEMECAHAN MASALAH BAB 3 LANGKAH PEMECAHAN MASALAH 3.1 Penetapan Kriteria Optimasi Optimasi adalah persoalan yang sangat penting untuk diterapkan dalam segala sistem maupun organisasi. Dengan optimalisasi pada sebuah sistem

Lebih terperinci

BAB III METODE PENELITIAN

BAB III METODE PENELITIAN 41 BAB III METODE PENELITIAN 3.1 Jenis Data dan Informasi Data yang diperoleh dan dikumpulkan dalam penelitian ini bersumber dari data primer dan data sekunder, yaitu:tabel 3.1 Jenis Data dan Informasi

Lebih terperinci

PERANCANGAN SISTEM KESEIMBANGAN LINTASAN PRODUKSI UNTUK MENGURANGI BALANCE DELAY GUNA MENINGKATKAN OUTPUT PRODUKSI

PERANCANGAN SISTEM KESEIMBANGAN LINTASAN PRODUKSI UNTUK MENGURANGI BALANCE DELAY GUNA MENINGKATKAN OUTPUT PRODUKSI PERANCANGAN SISTEM KESEIMBANGAN LINTASAN PRODUKSI UNTUK MENGURANGI BALANCE DELAY GUNA MENINGKATKAN OUTPUT PRODUKSI Jaka Purnama Laboratorium Sistem Produksi Jurusan Teknik Industri Institut Teknologi Adhi

Lebih terperinci

ANALISIS KESEIMBANGAN LINI PADA LINTASAN TRANSMISI MF06 DENGAN PENERAPAN METODE RANKED POSITIONAL WEIGHT

ANALISIS KESEIMBANGAN LINI PADA LINTASAN TRANSMISI MF06 DENGAN PENERAPAN METODE RANKED POSITIONAL WEIGHT ANALISIS KESEIMBANGAN LINI PADA LINTASAN TRANSMISI MF06 DENGAN PENERAPAN METODE RANKED POSITIONAL WEIGHT Disusun oleh: Nama : Rizki Ari Sandi Npm : 36412550 Jurusan : Teknik Industri Dosen Pembimbing :

Lebih terperinci

BAB VI LINE BALANCING

BAB VI LINE BALANCING BAB VI LINE BALANCING 6.1 Landasan Teori Keseimbangan lini perakitan (line balancing) merupakan suatu metode penugasan pekerjaan ke dalam stasiun kerja-stasiun kerja yang saling berkaitan dalam satu lini

Lebih terperinci

ANALISA PENINGKATAN EFISIENSI ASSEMBLY LINE B PADA BAGIAN MAIN LINE DENGAN METODE RANKED POSITIONAL WEIGHTS DI PT. X

ANALISA PENINGKATAN EFISIENSI ASSEMBLY LINE B PADA BAGIAN MAIN LINE DENGAN METODE RANKED POSITIONAL WEIGHTS DI PT. X ANALISA PENINGKATAN EFISIENSI ASSEMBLY LINE B PADA BAGIAN MAIN LINE DENGAN METODE RANKED POSITIONAL WEIGHTS DI PT. X Constance Dorthea Renata, Sevenpri Candra, Rida Zuraida Binus University, Jl. K.H. Syahdan,

Lebih terperinci

BAB 4 PEMBAHASAN HASIL

BAB 4 PEMBAHASAN HASIL BAB 4 PEMBAHASAN HASIL 4.1 Profil Perusahaan 4.1.1 Sejarah Perusahaan PT. Asia Dwimitra Industri merupakan perusahaan yang bergerak dalam bidang industri manufaktur yang berdiri sejak tahun 2008 dan berlokasi

Lebih terperinci

Perbaikan Keseimbangan Lintasan di Lini Produksi ECOSS Perusahaan Heat Exchanger

Perbaikan Keseimbangan Lintasan di Lini Produksi ECOSS Perusahaan Heat Exchanger Perbaikan Keseimbangan Lintasan di Lini Produksi ECOSS Perusahaan Heat Exchanger Ardityo Irawan 1 Abstract: PT XYZ is one of the company that produce heat exchanger in Indonesia. The Company developing

Lebih terperinci

DAFTAR ISI ABSTRAK... ABSTRACT... KATA PENGANTAR. DAFTAR ISI... DAFTAR TABEL... DAFTAR GAMBAR DAFTAR LAMPIRAN Latar Belakang Penelitian..

DAFTAR ISI ABSTRAK... ABSTRACT... KATA PENGANTAR. DAFTAR ISI... DAFTAR TABEL... DAFTAR GAMBAR DAFTAR LAMPIRAN Latar Belakang Penelitian.. DAFTAR ISI ABSTRAK... ABSTRACT...... KATA PENGANTAR. DAFTAR ISI... DAFTAR TABEL... DAFTAR GAMBAR DAFTAR LAMPIRAN... i ii iii vi x xii xiii BAB I BAB II PENDAHULUAN.. 1.1 Latar Belakang Penelitian.. 1.2

Lebih terperinci

TCW097 Pacific II TCW097. Dimensions in mm

TCW097 Pacific II TCW097. Dimensions in mm Waterproof Luminaire TCW097 Pacific II TCW097 TCW097 Pacific II Functional impact-, dust-, and jetproof luminaire for single and twin TL D and TL 5 fluorescent lamps for indoor applications. Housing and

Lebih terperinci

PERANCANGAN LINE BALANCING DALAM UPAYA PERBAIKKAN LINI PRODUKSI DENGAN SIMULASI PROMODEL DI PT CATERPILLAR INDONESIA

PERANCANGAN LINE BALANCING DALAM UPAYA PERBAIKKAN LINI PRODUKSI DENGAN SIMULASI PROMODEL DI PT CATERPILLAR INDONESIA PERANCANGAN LINE BALANCING DALAM UPAYA PERBAIKKAN LINI PRODUKSI DENGAN SIMULASI PROMODEL DI PT CATERPILLAR INDONESIA Renty Anugerah Mahaji Puteri 1*, Wiwik Sudarwati 2 1,2 Jurusan Teknik Industri, Fakultas

Lebih terperinci

MENINGKATKAN KAPASITAS PRODUKSI LINE REAR AXLE ASSY DENGAN METODE LINE BALANCING DI PT. XYZ

MENINGKATKAN KAPASITAS PRODUKSI LINE REAR AXLE ASSY DENGAN METODE LINE BALANCING DI PT. XYZ MENINGKATKAN KAPASITAS PRODUKSI LINE REAR AXLE ASSY DENGAN METODE LINE BALANCING DI PT. XYZ Margono Sugeng 1) dan Ari Setyawan 2) Program Studi Teknik Industri, Institut Sains dan Teknologi Nasional email:

Lebih terperinci

BAB 3 METODOLOGI PENELITIAN

BAB 3 METODOLOGI PENELITIAN BAB 3 METODOLOGI PENELITIAN 3.1 Flowchart Metodologi Penelitian adalah langkah-langkah yang dibuat untuk memudahkan Pemecahkan suatu masalah dalam sebuah Penelitian. Berikut ini adalah Flow Chart Pemecahan

Lebih terperinci

pekerja normal untuk menyelesaikan suatu pekerjaan yang dijalankan dalam sistem

pekerja normal untuk menyelesaikan suatu pekerjaan yang dijalankan dalam sistem 24 pekerja normal untuk menyelesaikan suatu pekerjaan yang dijalankan dalam sistem kerja terbaik. Pengertian dari waktu baku yang normal,wajar, dan terbaik dimaksudkan untuk menunjukkan bahwa waktu baku

Lebih terperinci

PENENTUAN JUMLAH TENAGA KERJA DAN STANDARD PENUGASAN BAGIAN PENGEPAKAN PADA PT X DENGAN METODA LINI KESEIMBANGAN KILBRIDGE DAN WESTER

PENENTUAN JUMLAH TENAGA KERJA DAN STANDARD PENUGASAN BAGIAN PENGEPAKAN PADA PT X DENGAN METODA LINI KESEIMBANGAN KILBRIDGE DAN WESTER PENENTUAN JUMLAH TENAGA KERJA DAN STANDARD PENUGASAN BAGIAN PENGEPAKAN PADA PT X DENGAN METODA LINI KESEIMBANGAN KILBRIDGE DAN WESTER Lina Gozali, I Wayan Sukania dan Lamto Widodo Program Studi Teknik

Lebih terperinci

PENENTUAN JUMLAH TENAGA KERJA DENGAN METODE KESEIMBANGAN LINI PADA DIVISI PLASTIC PAINTING PT. XYZ

PENENTUAN JUMLAH TENAGA KERJA DENGAN METODE KESEIMBANGAN LINI PADA DIVISI PLASTIC PAINTING PT. XYZ PENENTUAN JUMLAH TENAGA KERJA DENGAN METODE KESEIMBANGAN LINI PADA DIVISI PLASTIC PAINTING PT. XYZ Lina Gozali, Andres dan Feriyatis Program Studi Teknik Industri Universitas Tarumanagara e-mail: linag@ft.untar.ac.id

Lebih terperinci

BAB III METODOLOGI PENELITIAN

BAB III METODOLOGI PENELITIAN 28 BAB III METODOLOGI PENELITIAN Dalam melakukan penelitian diperlukan adanya tahapan-tahapan yang jelas agar penelitian yang dilakukan terarah, tahapan ini disusun ringkas dalam sebuah metodologi penelitian.

Lebih terperinci

BAB 2 LANDASAN TEORI

BAB 2 LANDASAN TEORI BAB 2 LANDASAN TEORI 2.1 Pembebanan Pembebanan (loading) dapat diartikan pekerjaan yang diberikan kepada mesin atau operator. Pembebanan menyangkut jadwal waktu kerja operator dalam kurun waktu satu hari

Lebih terperinci

BAB 4 PENGUMPULAN DAN ANALISA DATA. General Assy. Stay Body Cover. Permanent 1. Permanent 2. Permanent 3. Permanent 4. Inspeksi. Repair.

BAB 4 PENGUMPULAN DAN ANALISA DATA. General Assy. Stay Body Cover. Permanent 1. Permanent 2. Permanent 3. Permanent 4. Inspeksi. Repair. BAB 4 PENGUMPULAN DAN ANALISA DATA 4.1 Pengumpulan Data 4.1.1 Diagram Proses Pembuatan Frame Body Comp Marking Front Frame Rear Frame General Assy Stay Body Cover Permanent 1 Permanent 2 Permanent 3 Permanent

Lebih terperinci

PERBAIKAN SISTEM KERJA DAN ALIRAN MATERIAL PADA PT. M MOTORS AND MANUFACTURING

PERBAIKAN SISTEM KERJA DAN ALIRAN MATERIAL PADA PT. M MOTORS AND MANUFACTURING PERBAIKAN SISTEM KERJA DAN ALIRAN MATERIAL PADA PT. M MOTORS AND MANUFACTURING Niken Parwati¹, Ibnu Sugandi². Program Studi Teknik Industri, Universitas Al Azhar Indonesia, Jakarta 12110 niken.parwati@uai.ac.id

Lebih terperinci

BAB 3 METODOLOGI PENELITIAN

BAB 3 METODOLOGI PENELITIAN BAB 3 METODOLOGI PENELITIAN Gambar 3.1 Flowchart Penulisan Laporan Tugas Akhir Metode penelitian yang digunakan dalam laporan Tugas Akhir ini adalah dengan metode kuntitatif. Dimana penelitian yang dilakukan

Lebih terperinci

Metode Dasar Group Technology Karakteristik Metode-Metode Group Technology Metode Rank Order Clustering 2...

Metode Dasar Group Technology Karakteristik Metode-Metode Group Technology Metode Rank Order Clustering 2... ABSTRAK PT Stallion merupakan perusahaan manufaktur yang bergerak dalam bidang pembuatan komponen otomotif, antara lain: brake pedal (Suzuki), pipe frame head (Suzuki), shock breaker (Showa), stay head

Lebih terperinci

BAB III TINJAUAN PUSTAKA

BAB III TINJAUAN PUSTAKA BAB III TINJAUAN PUSTAKA 3.1 Definisi Line Balancing Line Balancing merupakan metode penugasan sejumlah pekerjaan ke dalam stasiun-stasiun kerja yang saling berkaitan/berhubungan dalam suatu lintasan atau

Lebih terperinci

BAB V HASIL ANALISA DATA

BAB V HASIL ANALISA DATA BAB V HASIL ANALISA DATA 5.1 Hasil Pembahasan CPM Hasil diagram gambar 4.1 (CPM proyek pembuatan truk tipe OF 2528 C tersebut terlihat hubungan ketergantungan antara satu kegiatan dengan kegiatan yang

Lebih terperinci

BAB 2 LANDASAN TEORI

BAB 2 LANDASAN TEORI BAB 2 LANDASAN TEORI 2.1 Definisi Line Balancing Keseimbangan lini produksi bermula dari lini produksi massal, dimana dalam proses produksinya harus dibagikan pada seluruh operator sehingga beban kerja

Lebih terperinci

BAB II TINJAUAN PUSTAKA

BAB II TINJAUAN PUSTAKA BAB II TINJAUAN PUSTAKA 2.1 Pengertian Line Balancing Line balancing merupakan penyeimbangan penugasan elemen-elemen tugas dari suatu assembly line ke work stations untuk meminimumkan banyaknya work station

Lebih terperinci

MINIMALISASI BOTTLENECK PROSES PRODUKSI DENGAN MENGGUNAKAN METODE LINE BALANCING

MINIMALISASI BOTTLENECK PROSES PRODUKSI DENGAN MENGGUNAKAN METODE LINE BALANCING MINIMALISASI BOTTLENECK PROSES PRODUKSI DENGAN MENGGUNAKAN METODE LINE BALANCING Yayan Indrawan, Ni Luh Putu Hariastuti Jurusan Teknik Industri Institut Teknologi Adhi Tama Surabaya Putu_hrs@yahoo.com

Lebih terperinci

Lina Gozali, Lamto Widodo, Wendy Program Studi Teknik Industri Fakultas Teknik Universitas Tarumanagara Jl. S Parman no.1, Jakarta

Lina Gozali, Lamto Widodo, Wendy Program Studi Teknik Industri Fakultas Teknik Universitas Tarumanagara Jl. S Parman no.1, Jakarta 1 2 USULAN PENJADWALAN JOB DENGAN METODE CAMPBELL, DUDEK AND SMITH (CDS) DAN METODE NAWAZ, ENSCORE AND HAM (NEH) UNTUK MEMINIMASI MAKESPAN PROSES STAMPING PART ISUZU DI LINE B PT. XYZ Lina Gozali, Lamto

Lebih terperinci

Peningkatan Kapasitas Produksi pada PT. Adicitra Bhirawa

Peningkatan Kapasitas Produksi pada PT. Adicitra Bhirawa Peningkatan Kapasitas Produksi pada PT. Adicitra Bhirawa Karine Santoso Putri, I Gede Agus Widyadana 2, Herry Christian Palit 3 Abstract: Currently, PT. Adicitra Bhirawa wants to increase their production

Lebih terperinci

BAB 1 PENDAHULUAN. untuk terus bertahan dan berkembang. Perusahaan yang mampu bertahan dan

BAB 1 PENDAHULUAN. untuk terus bertahan dan berkembang. Perusahaan yang mampu bertahan dan BAB 1 PENDAHULUAN 1.1 Latar Belakang Masalah Perkembangan industri manufaktur yang begitu pesat menuntut perusahaan untuk terus bertahan dan berkembang. Perusahaan yang mampu bertahan dan berkembang dengan

Lebih terperinci

Improvement Proses Screwing pada Lini Kaleng Kopi di PT Sinar Djaja Can

Improvement Proses Screwing pada Lini Kaleng Kopi di PT Sinar Djaja Can Improvement Proses Screwing pada Lini Kaleng Kopi di PT Sinar Djaja Can Billy Sutjiono 1 dan I Nyoman Sutapa 2 Abstract: PT Sinar Djaja Can is a manufacturing company which produces cans with 2 categories,

Lebih terperinci

Analisis Line Efficiency Produk Wall Fan pada Proses Final Assembly (Studi Kasus di PT Panasonic Manufacturing Indonesia)

Analisis Line Efficiency Produk Wall Fan pada Proses Final Assembly (Studi Kasus di PT Panasonic Manufacturing Indonesia) Analisis Line Efficiency Produk Wall Fan pada Proses Final Assembly (Studi Kasus di PT Panasonic Manufacturing Indonesia) Carinda Adistiara *1), Susy Susmartini *2) 1,2) Program Studi Teknik Industri,

Lebih terperinci

BAB II LANDASAN TEORI

BAB II LANDASAN TEORI 8 BAB II LANDASAN TEORI Keseimbangan lini produksi bermula dari lini produksi masal, dimana tugas-tugas yang dikerjakan dalam proses harus dibagi kepada seluruh operator agar beban kerja dari para operator

Lebih terperinci

Perbaikan Tata Letak Fasilitas dengan Mempertimbangkan Keseimbangan Lintasan (Studi Kasus)

Perbaikan Tata Letak Fasilitas dengan Mempertimbangkan Keseimbangan Lintasan (Studi Kasus) Perbaikan Tata Letak Fasilitas dengan Mempertimbangkan Keseimbangan Lintasan (Studi Kasus) Priscilla Gandasutisna 1, Tanti Octavia 2 Abstract: PT. X is a job-order plastic packaging industry using line

Lebih terperinci

PENYEIMBANGAN LINI PERAKITAN MENGGUNAKAN METODE GENETIC ALGORITHM UNTUK MENINGKATKAN KAPASITAS PRODUKSI

PENYEIMBANGAN LINI PERAKITAN MENGGUNAKAN METODE GENETIC ALGORITHM UNTUK MENINGKATKAN KAPASITAS PRODUKSI PENYEIMBANGAN LINI PERAKITAN MENGGUNAKAN METODE GENETIC ALGORITM UNTUK MENINGKATKAN KAPASITAS PRODUKSI Sumiharni Batubara 1), Fikri Nuradhi 2) Laboratorium Sistem Produksi Jurusan Teknik Industri, Fakultas

Lebih terperinci

Analisis Line Efficiency pada Proses Assembly Produk F-25TGU pada Business Unit Fan PT Panasonic Manufacturing Indonesia

Analisis Line Efficiency pada Proses Assembly Produk F-25TGU pada Business Unit Fan PT Panasonic Manufacturing Indonesia Analisis Line Efficiency pada Proses Assembly Produk F-25TGU pada Business Unit Fan PT Panasonic Manufacturing Indonesia Stephani Diesya Floratiara 1), Ilham Priadythama 2) 1,2) Program Studi Teknik Industri,

Lebih terperinci

PENINGKATAN PRODUKSI DENGAN METODE KESEIMBANGAN LINI PADA PD TEGAS

PENINGKATAN PRODUKSI DENGAN METODE KESEIMBANGAN LINI PADA PD TEGAS PENINGKATAN PRODUKSI DENGAN METODE KESEIMBANGAN LINI PADA PD TEGAS Landjono Josowidagdo 1 ; Novira Primatari ; Sarah Sahputri Perdana 3 1, Peneliti BPPT, Jln. MH. Thamrin, Jaarta, landjonoj@yahoo.com 3

Lebih terperinci

UNIVERSITAS BINA NUSANTARA PENGUKURAN EFISIENSI PROSES PEMBUATAN HANGER TIPE TAC 6212 PADA PT. BIGGY CEMERLANG DENGAN ANALISIS LINE BALANCING

UNIVERSITAS BINA NUSANTARA PENGUKURAN EFISIENSI PROSES PEMBUATAN HANGER TIPE TAC 6212 PADA PT. BIGGY CEMERLANG DENGAN ANALISIS LINE BALANCING UNIVERSITAS BINA NUSANTARA Jurusan Teknik Industri Skripsi Sarjana Semester Ganjil 2005/2006 PENGUKURAN EFISIENSI PROSES PEMBUATAN HANGER TIPE TAC 6212 PADA PT. BIGGY CEMERLANG DENGAN ANALISIS LINE BALANCING

Lebih terperinci

ANALISIS KESEIMBANGAN LINTASAN PRODUKSI DENGAN MENGGUNAKAN METODE RANKED POSITION WEIGHT (RPW) (STUDI KASUS: PT. KRAKATAU STEEL, Tbk.

ANALISIS KESEIMBANGAN LINTASAN PRODUKSI DENGAN MENGGUNAKAN METODE RANKED POSITION WEIGHT (RPW) (STUDI KASUS: PT. KRAKATAU STEEL, Tbk. ANALISIS KESEIMBANGAN LINTASAN PRODUKSI DENGAN MENGGUNAKAN METODE RANKED POSITION WEIGHT (RPW) (STUDI KASUS: PT. KRAKATAU STEEL, Tbk. CILEGON, BANTEN) Herlina Putri W, Ahmad Sidiq, dan Reza Maulana Program

Lebih terperinci

BAB 1 PENDAHULUAN. selalu berusaha meningkatkan daya saingnya melalui peningkatan. efisiensi, kualitas dan produktivitas perusahaannya dalam rangka

BAB 1 PENDAHULUAN. selalu berusaha meningkatkan daya saingnya melalui peningkatan. efisiensi, kualitas dan produktivitas perusahaannya dalam rangka BAB 1 PENDAHULUAN 1.1. Latar Belakang Masalah. Dewasa ini persaingan di dunia industri makin ketat. Permintaan pasarpun sering berubah-ubah. Kenyataan ini membuat para pengusaha selalu berusaha meningkatkan

Lebih terperinci

BAB 2 LANDASAN TEORI

BAB 2 LANDASAN TEORI BAB 2 LANDASAN TEORI 2.1. Penelitian Cara Kerja Pada laporan skripsi ini penelitian cara kerja menggunakan metode penelitian yang dilakukan melalui operation process chart. Dan dalam perhitungan untuk

Lebih terperinci

FRAME F - 1. Dimention (mm) No. Notes. l/w (_ ) HARNESS, WIRE

FRAME F - 1. Dimention (mm) No. Notes. l/w (_ ) HARNESS, WIRE F - AME No..... Part Number Part Name Qty HP F-R&X F 00 00 BODY COMP, AME RANGKA HP F-R&X F 0068 00 HARNESS, WIRE KABEL BODY HP F-R&X F 00 00 COVER SET, RR. STANDING PANGKON TUTUP COVER, BODY HP F-R&X

Lebih terperinci

BAB V ANALISA HASIL Kondisi Keseimbangan Lintasan Produksi Aktual

BAB V ANALISA HASIL Kondisi Keseimbangan Lintasan Produksi Aktual BAB V ANALISA HASIL 5.1. Kondisi Keseimbangan Lintasan Produksi Aktual Berdasarkan pengamatan yang dilakukan, kondisi aktual saat ini tidak seimbang penyebab utama terjadinya ketidak seimbangan lintasan

Lebih terperinci

BAB I PENDAHULUAN. internasional semakain meningkat. Hal tersebut menuntut perusahaan-perusahaan

BAB I PENDAHULUAN. internasional semakain meningkat. Hal tersebut menuntut perusahaan-perusahaan BAB I PENDAHULUAN 1.1 Latar Belakang Masalah Pada era globalisasi sekarang ini, persaingan antara perusahaanperusahaan industri manufaktur baik di pasar nasional maupun di pasar internasional semakain

Lebih terperinci

MEMPELAJARI KESEIMBANGAN LINI PADA PROSES COUNTER LINE MESIN TIPE XD833 CD3 MOTOR SATRIA F150 DI PT. SUZUKI INDOMOBIL MOTOR PLANT CAKUNG

MEMPELAJARI KESEIMBANGAN LINI PADA PROSES COUNTER LINE MESIN TIPE XD833 CD3 MOTOR SATRIA F150 DI PT. SUZUKI INDOMOBIL MOTOR PLANT CAKUNG MEMPELAJARI KESEIMBANGAN LINI PADA PROSES COUNTER LINE MESIN TIPE XD833 CD3 MOTOR SATRIA F150 DI PT. SUZUKI INDOMOBIL MOTOR PLANT CAKUNG Nama : Syaiful Ma arif NPM : 37412250 Jurusan : Teknik Industri

Lebih terperinci

BAB 2 TINJAUAN PUSTAKA

BAB 2 TINJAUAN PUSTAKA BAB 2 TINJAUAN PUSTAKA 2.1 Teknik Pengukuran Kerja Pengukuran kerja adalah metoda penetapan keseimbangan antara kegiatan manusia yang dikontribusikan dengan unit output yang dihasilkan. Teknik pengukuran

Lebih terperinci

ABSTRAK Universitas Kristen Maranatha

ABSTRAK Universitas Kristen Maranatha ABSTRAK ABSTRAK PT. Stallion adalah perusahaan yang membuat komponen-komponen untuk mobil dan motor. Komponen-komponen yang diproduksinya adalah komponen-komponen untuk perusahaan-perusahaan terkemuka,

Lebih terperinci

ANALISIS PENINGKATAN PRODUKTIVITAS DAN EFISIENSI KERJA DENGAN PENERAPAN KAIZEN (Studi Kasus pada PT Beiersdorf Indonesia PC Malang)

ANALISIS PENINGKATAN PRODUKTIVITAS DAN EFISIENSI KERJA DENGAN PENERAPAN KAIZEN (Studi Kasus pada PT Beiersdorf Indonesia PC Malang) ANALISIS PENINGKATAN PRODUKTIVITAS DAN EFISIENSI KERJA DENGAN PENERAPAN KAIZEN (Studi Kasus pada PT Beiersdorf Indonesia PC Malang) ANALYSIS OF PRODUCTIVITY AND WORK EFFICIENCY IMPROVEMENT WITH KAIZEN

Lebih terperinci

BAB 3 METODOLOGI PENELITIAN

BAB 3 METODOLOGI PENELITIAN BAB 3 METODOLOGI PENELITIAN 3.1 Diagram Alir Metodologi Penelitian Dalam melakukan proses penulisan laporan tugas akhir mengenai perancangan sistem kerja dari proses perakitan engine, penulis melakukan

Lebih terperinci

BAB 4 PENGUMPULAN, PENGOLAHAN DAN ANALISIS DATA

BAB 4 PENGUMPULAN, PENGOLAHAN DAN ANALISIS DATA BAB 4 PENGUMPULAN, PENGOLAHAN DAN ANALISIS DATA 4.1 Sejarah Perusahaan (Sumber: Company Profil PT.IGP) Gambar 4.1 Layout IGP Group IGP Group dimulai dengan berdirinya PT.GKD pada tahun 1980 dengan frame

Lebih terperinci

PERANCANGAN SISTEM INFORMASI MANUFAKTUR DI LABORATORIUM PLASTIK INJEKSI POLITEKNIK MANUFAKTUR ASTRA

PERANCANGAN SISTEM INFORMASI MANUFAKTUR DI LABORATORIUM PLASTIK INJEKSI POLITEKNIK MANUFAKTUR ASTRA PERANCANGAN SISTEM INFORMASI MANUFAKTUR DI LABORATORIUM PLASTIK INJEKSI POLITEKNIK MANUFAKTUR ASTRA Mada Jimmy Fonda Arifianto 1 ; Edi Santoso 2 ABSTRACT Article presents manufacture information system

Lebih terperinci

UNIVERSITAS BINA NUSANTARA

UNIVERSITAS BINA NUSANTARA UNIVERSITAS BINA NUSANTARA Jurusan Teknik Industri Tugas Akhir Sarjana Semester Genap tahun 2006/2007 STUDI KESEIMBANGAN LINI PERAKITAN DENGAN MENGGUNAKAN METODE-METODE HEURISTIK SERTA PERENCANAAN KEGIATAN

Lebih terperinci

PENENTUAN KESEIMBANGAN LINTASAN OPTIMAL DENGAN MENGGUNAKAN METODE HEURISTIK

PENENTUAN KESEIMBANGAN LINTASAN OPTIMAL DENGAN MENGGUNAKAN METODE HEURISTIK PENENTUAN KESEIMBANGAN LINTASAN OPTIMAL DENGAN MENGGUNAKAN METODE HEURISTIK Taufiqur Rachman Program Studi Teknik Industri, Fakultas Teknik Universitas Esa Unggul, Jakarta Jln Arjuna Utara No.9 Kebon Jeruk

Lebih terperinci

CYLINDER HEAD E HP GASKET CARBURETOR INSULATOR HP WASHER, PLAIN 8 X 6 X

CYLINDER HEAD E HP GASKET CARBURETOR INSULATOR HP WASHER, PLAIN 8 X 6 X E - CYLINDER HEAD see E- 0 0 0 0 HP 0 000 HEAD COMP CYLINDER 0 HP 0 000 HOLDER CAMSHAFT. HP 0 000 GUIDE IN VALVE HP 0 000 GUIDE EX VALVE HP 0 000 GASKET CYLINDER HEAD HP 0 000 GASKET CARBURETOR INSULATOR

Lebih terperinci

Seminar Tugas Akhir Statistika ITS, 12 Januari 2011

Seminar Tugas Akhir Statistika ITS, 12 Januari 2011 Tabel ringkasan hasil perhitungan waktu normal (lanjutan) No 6 7 Proses Operasi Proses penggabungan bagian-bagian dompet Proses penjahitan 8 Proses finishing 9 Proses pengkilapan Variabel Rata-rata Waktu

Lebih terperinci

Yulia Diah Dinanty dan Sumiharni Batubara

Yulia Diah Dinanty dan Sumiharni Batubara PERANCANGAN SISTEM P-KANBAN DAN C-KANBAN UNTUK MEMINIMASI KETERLAMBATAN MATERIAL PADA LINI PRODUKSI PERAKITAN LAUNDRY SYSTEM BUSINESS UNIT (LSBU) DI PT. Y Yulia Diah Dinanty dan Sumiharni Batubara Laboratorium

Lebih terperinci

PROSES WELDING FRONT CHASSIS NISSAN X-TRAIL DI PT. NISSAN MOTOR INDONESIA. Nama : Bernie Fauzan Mochamad Npm : Kelas : 4 IC 04

PROSES WELDING FRONT CHASSIS NISSAN X-TRAIL DI PT. NISSAN MOTOR INDONESIA. Nama : Bernie Fauzan Mochamad Npm : Kelas : 4 IC 04 PROSES WELDING FRONT CHASSIS NISSAN X-TRAIL DI PT. NISSAN MOTOR INDONESIA Nama : Bernie Fauzan Mochamad Npm : 21410394 Kelas : 4 IC 04 ABSTRAKSI Front chassis merupakan salah satu komponen utama pada sebuah

Lebih terperinci

USULAN PERBAIKAN LINI BERDASARKAN METODE KESEIMBANGAN LINI DAN PREDETERMINED TIME SYSTEMS PADA PERAKITAN UPPER NCVS1.06 DI PT.ASIA DWIMITRA INDUSTRI

USULAN PERBAIKAN LINI BERDASARKAN METODE KESEIMBANGAN LINI DAN PREDETERMINED TIME SYSTEMS PADA PERAKITAN UPPER NCVS1.06 DI PT.ASIA DWIMITRA INDUSTRI USULAN PERBAIKAN LINI BERDASARKAN METODE KESEIMBANGAN LINI DAN PREDETERMINED TIME SYSTEMS PADA PERAKITAN UPPER NCVS1.06 DI PT.ASIA DWIMITRA INDUSTRI Diana Tjan 1, Muhamad Fadhli Farhan 2, Sanidhya Nurwulan

Lebih terperinci

Usulan Perbaikan Performansi Lini Produksi PT. XYZ

Usulan Perbaikan Performansi Lini Produksi PT. XYZ Jurnal Metris, 15 (2014): 41 46 Jurnal Metris ISSN: 1411-3287 Usulan Perbaikan Performansi Lini Produksi PT. XYZ Trifenaus Prabu Hidayat, Adiyatma Program Studi Teknik Industri, Universitas Katolik Indonesia

Lebih terperinci

BAB 2 LANDASAN TEORI

BAB 2 LANDASAN TEORI 12 BAB 2 LANDASAN TEORI 2.1 Tinjauan Pustaka 2.1.1 Studi Gerak dan Waktu (Barnes h. 257) Studi gerak dan waktu merupakan suatu ilmu yang terdiri dari teknik dan prinsip-prinsip untuk mendapatkan rancangan

Lebih terperinci

MANAJEMEN PRODUKSI DAN OPERASI

MANAJEMEN PRODUKSI DAN OPERASI MANAJEMEN PRODUKSI DAN OPERASI MATERI 1. Konsep dasar operasi dan produktivitas 2. Strategi Operasi 3. Perencanaan pengendalian operasi, Perencanaan dan 4. persediaan 5. Perencanaan Kebutuhan Bahan (MRP)

Lebih terperinci

IMPLEMENTASI SHOJINKA PADA PERENCANAAN PRODUKSI AGREGAT DENGAN PENGATURAN TENAGA KERJA DAN PEMBAGIAN KERJA FLEKSIBEL

IMPLEMENTASI SHOJINKA PADA PERENCANAAN PRODUKSI AGREGAT DENGAN PENGATURAN TENAGA KERJA DAN PEMBAGIAN KERJA FLEKSIBEL Hal I - 173 IMPLEMENTASI SHOJINKA PADA PERENCANAAN PRODUKSI AGREGAT DENGAN PENGATURAN TENAGA KERJA DAN PEMBAGIAN KERJA FLEKSIBEL Arif Rahman Program Studi Teknik Industri, Fakultas Teknik Universitas Brawijaya

Lebih terperinci

ANALISA PENURUNAN WAKTU PROSES BARITORI CAMSHAFT DENGAN METODE 6 STEP STANDARDIZED WORK DI PT.TMMIN

ANALISA PENURUNAN WAKTU PROSES BARITORI CAMSHAFT DENGAN METODE 6 STEP STANDARDIZED WORK DI PT.TMMIN ANALISA PENURUNAN WAKTU PROSES BARITORI CAMSHAFT DENGAN METODE 6 STEP STANDARDIZED WORK DI PT.TMMIN Anak Agung Gede Ngurah Arika Dwiyana Binus University, Jakarta, DKI Jakarta, Indonesia Abstrak PT. Toyota

Lebih terperinci

UNIVERSITAS BINA NUSANTARA. Jurusan Teknik Industri Tugas Akhir Sarjana Semester Ganjil tahun 2007 / 2008

UNIVERSITAS BINA NUSANTARA. Jurusan Teknik Industri Tugas Akhir Sarjana Semester Ganjil tahun 2007 / 2008 iv UNIVERSITAS BINA NUSANTARA Jurusan Teknik Industri Tugas Akhir Sarjana Semester Ganjil tahun 2007 / 2008 ANALISIS KESEIMBANGAN LINI PERAKITAN MODEL CJM 1.5 DENGAN METODE RANK POSITIONAL WEIGHT DI PT.

Lebih terperinci

e-jurnal Teknik Industri FT USU Vol 3, No. 4, November 2013 pp

e-jurnal Teknik Industri FT USU Vol 3, No. 4, November 2013 pp PENYEIMBANGAN LINTASAN PADA PERAKITAN TRANSFORMATOR DENGAN METODE MOODIE YOUNG DAN COMSOAL PADA PT. XYZ Lidia Natalia 1, Sukaria Sinulingga 2, Ikhsan Siregar 2 Departemen Teknik Industri, Fakultas Teknik,

Lebih terperinci

APLIKASI BINARY INTEGER PROGRAMMING UNTUK PENINGKATAN EFISIENSI LINTASAN SEBAGAI FUNGSI OUTPUT PRODUKSI DI PT INDOJAYA PRIMA SEMESTA-PASURUAN

APLIKASI BINARY INTEGER PROGRAMMING UNTUK PENINGKATAN EFISIENSI LINTASAN SEBAGAI FUNGSI OUTPUT PRODUKSI DI PT INDOJAYA PRIMA SEMESTA-PASURUAN APLIKASI BINARY INTEGER PROGRAMMING UNTUK PENINGKATAN EFISIENSI LINTASAN SEBAGAI FUNGSI OUTPUT PRODUKSI DI PT INDOJAYA PRIMA SEMESTA-PASURUAN Husin 1) dan Abdullah Shahab 2) 1) Program Studi Magister Manajemen

Lebih terperinci

BAB II LANDASAN TEORI

BAB II LANDASAN TEORI BAB II LANDASAN TEORI 2.1. Efektifitas 2.1.1. Pengertian Efektifitas Pengertian efektifitas secara umum menunjukan sampai seberapa jauh tercapainya suatu tujuan yang terlebih dahulu ditentukan. Hal tersebut

Lebih terperinci

NEW LINE 1 WELDING FRAME BODY COMP DALAM PENINGKATAN KINERJA DAN OPTIMALISASI LINE

NEW LINE 1 WELDING FRAME BODY COMP DALAM PENINGKATAN KINERJA DAN OPTIMALISASI LINE NEW LINE 1 WELDING FRAME BODY COMP DALAM PENINGKATAN KINERJA DAN OPTIMALISASI LINE M. Afandy Staf Produksi Industri Manufaktur Automotive, PT ASTRA DAIHATSU MOTOR HEAD OFFICE Jln. Gaya Motor III No. 5,

Lebih terperinci

BAB 1 PENDAHULUAN. rupa sehingga tidak ada waktu dan tenaga yang terbuang sia-sia sehingga dapat

BAB 1 PENDAHULUAN. rupa sehingga tidak ada waktu dan tenaga yang terbuang sia-sia sehingga dapat BAB 1 PENDAHULUAN 1.1 Latar Belakang Masalah Efisien dalam dunia industri berarti memanfaatkan sumber daya sedemikian rupa sehingga tidak ada waktu dan tenaga yang terbuang sia-sia sehingga dapat menghasilkan

Lebih terperinci

Lina Gozali, Lamto Widodo, Wendy. Fakultas Teknik Program Studi Teknik Industri Universitas Tarumanagara Jakarta. Abstrak

Lina Gozali, Lamto Widodo, Wendy. Fakultas Teknik Program Studi Teknik Industri Universitas Tarumanagara Jakarta. Abstrak Jurnal Teknik dan Ilmu Komputer USULAN PENJADWALAN JOB DENGAN METODE CAMPBELL, DUDEK AND SMITH (CDS) DAN METODE NAWAZ, ENSCORE AND HAM (NEH) UNTUK MEMINIMASI MAKESPAN PROSES STAMPING PART ISUZU DI LINE

Lebih terperinci

PENGARUH FAKTOR LINGKUNGAN FISIK TERHADAP WAKTU PERAKITAN STICK PLAYSTATION

PENGARUH FAKTOR LINGKUNGAN FISIK TERHADAP WAKTU PERAKITAN STICK PLAYSTATION PENGARUH FAKTOR LINGKUNGAN FISIK TERHADAP WAKTU PERAKITAN STICK PLAYSTATION Resa Taruna Suhada dan Ricky Reza Adhavi Program Studi Teknik Industri, Fakultas Teknologi Industri - Universitas Mercu Buana

Lebih terperinci

Universitas Bina Nusantara. Jurusan Teknik Industri Skripsi Sarjana Teknik Industri Semester Genap tahun 2006/2007

Universitas Bina Nusantara. Jurusan Teknik Industri Skripsi Sarjana Teknik Industri Semester Genap tahun 2006/2007 Universitas Bina Nusantara Jurusan Teknik Industri Skripsi Sarjana Teknik Industri Semester Genap tahun 2006/2007 Optimalisasi Proses Produksi Dengan Usulan Lini Keseimbangan Pada CV. Teluk Harapan Alexander

Lebih terperinci