LAPORAN KERJA BULANAN DIVISI ENGINEERING APARTEMENT TAMAN KEMAYORAN CONDOMINIUM DIVISI ENGINEERING
LAPORAN BULANAN ENGINEERING APARTEMENT TAMAN KEMAYORAN CONDOMINIUM Proses Perbaikan Lift Error yang dilakukan oleh engineering di tower bougenville P1 dengan mereset Inverter yang berada diatas Car Lift The Repair Of process elevator error at the bougenville P1 tower that s by Engineer with a step on Reset the inverter there s above in the elevator car Proses Penyettingan kartu akses baru yang dilakukan oleh engineering pada lift ebony atas permintaan penghuni The Setting A card new acess that s by engineer in the ebony elevator on tenant request 2
Proses perbaikan saluran drain yang mampet pada balkon hunian tower ebony lantai 22/03 The Repair Of process drain line isn t going on the tenant of balcony at the ebony tower on the floor twenty two zero three Proses perbaikan pipa induk air kotor dilakukan oleh engineering dikarenakan pipa induk mampet dan bocor yang terjadi dilantai dasar cendana The Repair Of Process in the mainpipe dirty water that s by engineer cause it s the mainpipe isn t going and leaking it happening on the cendana base floor 3
Proses Pengerjaan Aspal Yang Dilakukan oleh Vendor pada Lapangan Tenis dan diawasi oleh Engineering The Working Of Asphalt Process That s By Vendor On the Tennis Field And The Surveilance Of Engineer 4
Proses Perbaikan Lift Error yang dilakukan oleh engineering di tower Ebony P2 dengan mereset Panel lift yang berada diruang Mesin Lift Ebony The Repair Of process elevator error at the Ebony tower P2 that s by Engineer with a step on the Reset Elevator Panel in the Machine Elevator Room Ebony Proses Pengisian Air Accu untuk Genzet Akasia-Bougenville,Aster- Flamboyan dan Ebony-Cendana The fill of process Accu Water to Genzet Akasia-Bougenville,Aster- Flamboyan And Ebony-Cendana 5
Proses Perbaikan Kitchen Yang Mampet di Tower Ebony Lantai 20/07 dikarenakan terdapat kotoran pada Instalasi pipa cucian piring The Repair Of process Kitchen Isn t Going at ebony tower on the floor twelve zero seven cause it s get a motion in the Pipe dishwater Installation Proses Penggantian Kran Yang baru untuk Fasilitas Cucian Mobil dikarenakan kran yang lama telah rusak The Changing of process it s a New Sink to Car of Diswash Factility cause it The past of sink has broken 6
Proses Pekerjaan Pembuatan Parkir sepeda untuk semua penghuni Apartement Tkc yang dilakukan oleh Engineering di Basement Ebony The Working of Made Bicycle Parking Process to All Tenant Of Tkc Apartement That s by Engineer in Ebony Basement Proses Pemasangan Lampu Untuk Area Parkir Sepeda di Basement Ebony The Fixing of Lamp Process to Parking Of Bicycle Area in Ebony Basement 7
Proses Pengerjaan Modernisasi Lift Akasia P1 dan Ebony P2 yang dilakukan oleh Tekhnisi Louserindo dan diawasi Oleh Engineering The Working Of Modernisation Elevator Akasia P1 And Ebony P2 That s By Louserindo Technician And The Surveillance of Engineer 8
Proses Pengerjaan Perbaikan Mesin Gondola Aster,Bougenville dan Cendana yang dilakukan oleh Tekhnisi Omni dan diawasi oleh Engineering The Working Of Service Gondola Machine Aster,Bougenville dan Cendana Process That s By Omni Technician And The Surveillance of Engineer 9
Proses Penggantian Instalasi Kran yang baru Untuk Fasilitas Kolam Renang The Changing Of Process a New Sink Installation to Swimming Pool Factility Proses Pemasangan Kwh/M Listrik Yang Baru Untuk Lantai Dasar Flamboyan 01 dikarenakan Kwh/M Listrik Yang Lama Bermasalah The Fixing of Process A New Kwh/M Electricity On The Base Floor Flamboyan Zero One Cause It s the Past Of Kwh/M Electricity Has Trouble 10
Proses Perbaikan Kipas Angin di Tower Bougenville lantai 05/03 The Service Of Fan process At the Bougenville Tower On The Floor Five Zero Three Proses Pemasangan Shower Baru Untuk Fasilitas Toilet Pria di Ruang Fitness The Fixing Of Process A New Shower To Factility in Male Toilet At the Fitness Room Proses Penggantian Karet Kopel Yang Baru Untuk Pompa Booster di Roof Akasia The Changing Of Process is A New Copling Rubber to Booster Pump in Akasia Roof 11
Proses Perbaikan Pipa Radiator Yang Bocor di Ruang Genzet Ebony The Repair Of Process Radiator pipe is Leaking In The Genzet Room Ebony Proses Pemasangan Lampu Pls Yang Baru di Tower Aster Lantai 22 The Fixing Of Process A New Pls Lamp in Aster Tower On the Floor Twenty Two Proses Pemasangan Lampu Pls Yang Baru di Tower Cendana Lantai 10/06 The Fixing Of Process A New Pls Lamp in Cendana Tower On The Floor Ten Zero Six 12
Proses Pemasangan Lampu Pls Yang Baru di tower Cendana Lantai 10/03 The Fixing Of Process A New Pls Lamp In Cendana Tower On The Floor Ten Zero Three Proses Pemasangan Lampu Pls Yang Baru di Tower Ebony Lantai 01/03 The Fixing Of Process A New Pls Lamp in Ebony Tower On the Floor One Zero Three Proses Pemasangan Lampu Hias Ruang Tamu di Tower Ebony Lantai 09/01 The Fixing Of Ornamental Lamp Process At Guest Room In The Ebony Tower On The Floor Nine Zero One 13
Proses Pemasangan Kran Shower Untuk Fasilitas Toilet Wanita di Ruang Fitness The Fixing Of Process Shower Sink to Toilet Female Factility in The Fitness Room Proses Perbaikan Listrik Yang Bermasalah di Koridor Ebony Lantai 8 The Repair Of Process Electricity Has Trouble At Corridor Ebony On The Eight Floor 14
Proses Pemasangan Bracket Tv di Ruang Tamu Tower Ebony Lantai 09/01 The Fixing Of Process Tv Bracket at Guest Room In The Ebony On The Floor Nine Zero One Proses Pemasangan Lampu TL di Lobby Koridor Cendana Lantai 3 The Fixing Of Process TL Lamp at The Corridor Cendana Lobby On The Three Floor Proses Pemasangan Lampu Emergency di Exit Luar Tower Flamboyan Lantai 16 The Fixing Of Process Emergency Lamp At The Exit In Flamboyan Tower On The Sixteen Floor 15
Proses Pemasangan Lampu TL di Lobby Koridor Cendana Lantai 6 The Fixing Of Process TL Lamp at The Corridor Cendana Lobby On The Six Floor Proses Pemasangan Lampu Emergency di Exit Luar Tower Flamboyan Lantai 15 The Fixing Of Process Emergency Lamp At The Exit In Flamboyan Tower On The Fiveteen Floor Proses Pemasangan Lampu Emergency di Exit Luar Tower Flamboyan Lantai 14 The Fixing Of Process Emergency Lamp At The Exit In Flamboyan Tower On The Fourteen Floor 16
Proses Penggantian Kran Cucian Piring Yang Baru dikarenakan Kran Yang Lama Telah Rusak di Tower Cendana Lantai 16/05 The Changing Of Process A New Sink Of Diswashing Cause It s Sink Has Broken In The Cendana Tower On The Floor Sixteen Zero Five Proses Perbaikan Kitchen Mampet di Tower Ebony Lantai 14/06 The Repair Of Process Kitchen Isn t Going In The Ebony Tower On The Floor Fourteen Zero Six Proses Menghidupkan Ac di Ruang Mesin Lift Cendana Yang Mati Akibat Listrik Padam The Switch On Air Conditioner Off At Machine Room Cendana Is Effecting Of Burnout Electricity 17
Proses Pemasangan Lampu TL di Koridor Lobby Cendana Lantai 10 The Fixing Of TL Lamp Process At The Lobby Cendana Corridor On The Ten Floor Proses Pemasangan Jet Shower Baru Untuk Closed Kamar Mandi Pembantu Tower Bougenville Lantai 03/07 The Fixing Of A New Jet Shower Process To Closed Housemaid Bathroom In The Bougenville Tower On The Floor Three Zero Seven Proses Pemasangan Lampu Tl di Lobby Koridor Cendana Lantai 12 The Fixing Of TL Lamp Process At The Corridor Lobby Cendana On The Twelve Floor 18
Proses Perbaikan Pintu Yang Terkunci di Kamar Tidur Tower Cendana Lantai 16/05 The Repair Of Door is Locked Process At The Bed Room In Cendana Tower On The Floor Sixteen Zero Five Proses Perbaikan Shifon Kitchen Yang Rusak di Tower Aster Lantai 15/06 The Repair Of Shifon is Broken Process In Aster Tower On The Floor Fiveteen Zero Six Proses Perbaikan Flexible Pada Wastafel Yang Bocor di Tower Aster Lantai 15/06 The Repair Of Flexible Processs is Leaking In Aster Tower On The Floor Fiveteen Zero Six 19
Proses Perbaikan Stopkontak yang Rusak di koridor Tower Ebony Lantai 8 The Repair Of Outlet Process Is Broken At Corridor Ebony Tower On The Eight Floor Proses Perbaikan Shower Kamar Mandi Yang Rusak di Tower Ebony Lantai 16/05 The Repair Of Bathroom Shower Process Is Broken In The Ebony Tower On The Floor Sixteen Zero Five Proses Perbaikan Saluran Drain Yang Mampet di kamar mandi Pembantu Tower Bougenville Lantai 17/07 The Repair Of Line Drain Process Isn t Going At Housemaid Bathroom In The Bougenville Tower On The Floor Seventeen Zero Seven 20
Proses Pemasangan Tombol Akses Baru Untuk Pintu Lobby Basement Bougenville The Fixing Of A New Acsess Switch Process To Door Lobby Basement Bougenville Proses Perbaikan Plafon Dan Pembuatan Talang di Ruang Mesin Lift Bougenville The Repair Of Ceiling And The Making Of Talang Process In The Elevator Machine Room Bougenville 21