PROGRESS PROYEK DISTRICT 8 @ LOT 28 SCBD PER OKTOBER 2016
DOKUMENTASI 10 OKTOBER 2016 APT 1 APT 2 APT 1 ETERNITY TOWER Pekerjaan struktural sudah selesai (topping off), dalam proses finishing APT 2 INFINITY TOWER Pekerjaan struktural sudah selesai (topping off), dalam proses finishing
PEKERJAAN FASAD APT 1 & 2 Item AP 1 - Eternity AP 2 - Infinity Window Wall s/d LT. 33 s/d LT. 36 Spandrell Glass s/d LT. 27 s/d LT. 10-16 & 21-23 Grill Balkon s/d LT. 23 s/d LT. 17, 21-23 & 27 Sliding Door s/d LT. 25 s/d LT. 35 Pintu AC Ledge s/d LT. 28 s/d LT. 31 Railing Balkon s/d LT. 21 s/d LT. 10-15 & 21-24 Grill AC Ledge s/d LT. 32 s/d LT. 31 Bullnose s/d LT. 12 s/d LT. 12
PEKERJAAN INSTALASI MEP APT 1 & 2 Item AP 1 - Eternity AP 2 - Infinity Riser s/d LT. 49 s/d LT. 49 MVAC s/d LT. 36 s/d LT. 45 Fire Fighting s/d LT. 39 s/d LT. 45 Plumbing s/d LT. 38 s/d LT. 45 Electronic s/d LT. 38 s/d LT. 45 Electrical s/d LT. 38 s/d LT. 45
PEKERJAAN LIFT APT 1 & 2 Item AP 1 - Eternity AP 2 - Infinity LIFT SERVICE Operasi s/d LT. 46. BA serah terima shaft lift : s/ d LT. 52. DONE (menunggu proses ke permanen), operasi s/d LT. 46. BA serah terima shaft lift : s/ d LT. 51. PASSENGER DONE DONE (Serah Terima ke ACSET).BA serah terima shaft lift : s/ d LT. 51. PRIVATE 1 & 2 Pas. Pintu s/d LT. 26 -> P1-4 : 43%. BA serah terima shaft lift : s/ d LT. 34. DONE (Serah Terima ke ACSET). BA serah terima shaft lift : s/ d LT. 51. PRIVATE 3 & 4 Pas. Pintu s/d LT. 26. BA serah terima shaft lift : s/ d LT. 34. Pas. Pintu s/d LT. 35 & Rail s/d LT. 43 (Target : Okt 2016). BA serah terima shaft lift : s/ d LT. 51
PEKERJAAN DINDING, PLAFOND, WATERPROOFING APT 1 & 2 PEK. DINDING Item AP 1 - Eternity AP 2 - Infinity Pas. ALC DONE s/d LT. 50 Plesteran DONE s/d LT. 49 Acian DONE s/d LT. 47 PEK. PLAFOND Pas. Rangka Plafond s/d LT. 41 s/d LT. 49 Pas. Gypsum s/d LT. 23 s/d LT. 29, 31-37 Ready to Paint s/d LT. 22 s/d LT. 26 & 31 PEK. WATERPROOFING Tes Beton s/d LT. 31 s/d LT. 50 Tes Waterproofing s/d LT. 31 s/d LT. 42
PEKERJAAN MARBLE APT 1 & 2 Item AP 1 - Eternity AP 2 - Infinity Dinding Passenger s/d LT. 27 s/d LT. 49 Dinding Private s/d LT. 29 s/d LT. 49 Dinding Kamar Mandi s/d LT. 26 s/d LT. 48 Lantai Koridor s/d LT. 48 s/d LT. 49 Lantai Kamar Mandi s/d LT. 21 s/d LT. 35 Lantai Unit s/d LT. 32 s/d LT. 49
PEKERJAAN PINTU KAYU & BESI APT 1 & 2 Item AP 1 - Eternity AP 2 - Infinity PEK. PINTU BESI Openingan s/d LT. 33 s/d LT. 41 Frame s/d LT. 29 s/d LT. 41 Daun Pintu s/d LT. 24 s/d LT. 31 Hardware s/d LT. 15 s/d LT. 16 PEK. PINTU KAYU Openingan s/d LT. 29 s/d LT. 29, 31 & 32 Frame s/d LT. 13 LT. 10-18 & 21-25 Daun Pintu s/d LT. 11 s/d LT. 18 & 21-25 Hardware s/d LT. 10 s/d LT. 17
PEKERJAAN FINISHING TANGGA APT 1 & 2 Item AP 1 - Eternity AP 2 - Infinity Tangga #1 s/d LT. 44 s/d LT. 37 Tangga #2 s/d LT. 44 s/d LT. 37
PEKERJAAN CROWN, BAJA GONDOLA, GONDOLA APT 1 & 2 CROWN Item AP 1 - Eternity AP 2 - Infinity Kolom DONE DONE Beam DONE DONE Brace DONE DONE Baja Gondola Kolom DONE DONE Beam DONE DONE Gondola Pas. Rel DONE -9 batang Chasis -1 unit -1 unit Pipa Tower -1 unit -1 unit Arm -2 unit -2 unit Box Drum -1 unit -1 unit
DOKUMENTASI 10 OKTOBER 2016 OFFICE 1 TREASURY TOWER Pekerjaan struktural sudah selesai (topping off), dalam proses finishing OFFICE 2 PROSPERITY TOWER OFFICE 1 - TREASURY TOWER Pekerjaan struktural sudah selesai (topping off),dalam proses finishing OFFICE 2 - PROSPERITY TOWER
PEKERJAAN FASAD OF1 & 2 Description of Work OF1 - Treasury OF2 - Prosperity Install s/d LT. 35 s/d LT. 25 Man Power OF1 & 2 : 86 orang Unitize Terpasang 3857 2638
PEKERJAAN INSTALASI MEP OF 1 & 2 Item OF1 - Treasury OF2 - Prosperity Tray/Ladder s/d LT. 50 s/d LMR Electrical s/d LT. 51 s/d LMR Electronic s/d LT. 49 s/d LMR Fire fighting s/d LT. 50 s/d ROOF MVAC s/d LT. 44 s/d LT. 36 Plumbing s/d LT. 39 s/d LT. 41
PEKERJAAN SHAFT MEP OF 1 & 2 Item OF1 - Treasury OF2 - Prosperity Fresh air fan s/d LT. 55 s/d LMR Plumbing s/d LT. 55 s/d LT. 41 Smoke Extract Fan s/d LT. 55 s/d LMR Pipa FF s/d LT. 55 s/d ROOF Pressurize Fan s/d LT. 55 Electrical s/d LT. 55 s/d LMR Electronic s/d LT. 55 s/d LMR Refrigerant s/d LT. 55 s/d LT. 36 Exhaust Fan s/d LT. 55 s/d LMR
PEKERJAAN DINDING, PLAFOND & WATERPROOFING OF 1 & 2 PEK. DINDING Item OF 1 OF 2 Pas. ALC s/d LT. 55 s/d LT. 41 Plesteran s/d LT. 55 s/d LT. 41 Acian s/d LT. 55 s/d LT. 41 PEK. PLAFOND Pas. Rangka Plafond LT. 3-27, 32-33, 40refugee s/d LT. 24 Pas. Gypsum LT. 3-21, 32-33, 40refugee s/d LT. 24 PEK. WATERPROOFING Tes Beton s/d LT. 28, 30 40 s/d LT. 39 Tes Waterproofing s/d LT. 22, 24-25, 32 34 s/d LT. 36
PEKERJAAN MARBLE OF1 & 2 Item OF 1 OF 2 Wall Marble LT. 3-4, 14, 32-33 LT. 4 (s/d LT. 31 on progress) Floor Marble LT. 3-14, LT. 32 & 33 LT. 4 (s/d LT. 31 on progress)
PEKERJAAN PINTU BESI OF1 & 2 Item OF1 OF 2 PEK. PINTU BESI Openingan LT. 3-8, 15-20 s/d LT. 20 Frame LT. B3-SB, 21, 32 & 33 Yang terpasang baru 124 dari jumlah 559 buah buah di berbagai lantai Daun Pintu LT. 3-8, 26-30, 36-39 Yang terpasang baru 70 dari jumlah 559 buah buah di berbagai lantai Hardware - Yang terpasang baru 16 dari jumlah 559 buah buah di berbagai lantai
PEKERJAAN FINISHING TANGGA OF1 & 2 Item OF1 OF2 OF3 Tangga #1 s/d LMR (plester aci) s/d LT. 41 (plester aci) s/d LMR (plester aci) Tangga #2 s/d LMR (plester aci) s/d LT. 41 (plester aci) s/d LMR (minus pasang pintu besi) Railing Tangga 1 on going s/d LT. 39, tangga 2 LT. 39 On going s/d LT. 32 s/d LMR
DOKUMENTASI 10 OKTOBER 2016 THE LANGHAM RESIDENCES Pekerjaan struktural mencapai lantai atap (roof deck)