EVALUASI PENGGUNAAN ALAT-ALAT BERAT PROYEK

dokumen-dokumen yang mirip
PRODUKTIVITAS ALAT BERAT PADA PEKERJAAN RIGID PAVEMENT ( STUDI KASUS PELEBARAN JALAN ISIMU-PAGUYAMAN)

METODE PELAKSANAAN PADA PELEBARAN JALAN BARUS BATAS KOTA SIBOLGA

TUGAS AKHIR MUHAMMAD RIDWAN OLEH : PROGRAM STUDI DIPLOMA IV TEKNIK SIPIL INSTITUT TEKNOLOGI SEPULUH NOPEMBER SURABAYA

BAB I PENDAHULUAN 1.1 Latar Belakang

RINTA ANGGRAINI

ANALISA PERHITUNGAN PRODUKTIVITAS ALAT BERAT PADA PELAKSANAAN PEMATANGAN LAHAN UNTUK PEMBUATAN WORK SHOP DI KAB

ANALISIS BIAYA PEMAKAIAN ALAT BERAT PADA PROYEK REKONTRUKSI JALAN BATAS KOTA PARIAMAN MANGGOPOH KABUPATEN PADANG PARIAMAN PROVINSI SUMATERA BARAT

TINJAUAN PENGGUNAAN PERALATAN PADA PELEBARAN RUAS JALAN BIREUEN - TEKENGON KAWASAN COT PANGLIMA

ANALISA PERHITUNGAN PRODUKTIVITAS ALAT BERAT PADA PELAKSANAAN PEMATANGAN LAHAN UNTUK PEMBUATAN WORK SHOP DI KAB

Oleh : 1. Esti Yuvita Rendi Candrawitadi

PERHITUNGAN TEBAL LAPIS PERKERASAN LENTUR PADA RUAS JALAN SISINGAMANGARAJA PADANG SIDEMPUAN (STA ) DENGAN METODE Pt-T B LAPORAN

PERBANDINGAN PRODUKTIVITAS EXCAVATOR PADA PEKERJAAN PASANG/SUSUN BATU GUNUNG UKURAN KG DAN KG

PENERAPAN METODE RSM PADA PENJADWALAN DENGAN AKTIVITAS BERULANG (STUDY KASUS: Proyek jalan tubaan- talisayan/ dumaring, provinsi kalimantan timur)

Abstrak. Kata kunci : Produktivitas, Waktu, Sewa, Biaya

BAB I PENDAHULUAN. berat dengan berbagai fungsi, jenis, bentuk dan merek. Dalam pembangunan

Satrio Agung Wibowo, Harimurti, Achfas Zacoeb

Optimalisasi Pekerjaan Pemindahan Tanah Pada Proyek Embung Begawan Kota Tarakan Dengan Model Antrian

Jurnal Sipil Statik Vol.5 No.7 September 2017 ( ) ISSN:

ANALISA PEMAKAIAN ALAT BERAT PADA PROYEK PEMBANGUNAN JALAN LINGKAR UTARA KOTA SOLOK

ESTIMASI WAKTU DAN BIAYA PERKERASAN KAKU JALAN TOL MOJOKERTO-KERTOSONO STA STA

BAB II TINJAUAN PUSTAKA

OPTIMALISASI PENGGUNAAN ALAT BERAT PADA PROYEK TOL PANDAAN- MALANG. (Optimalization of Using Heavy Equipment on Pandaan-Malang Highway Project)

BAB I PENDAHULUAN. Sehubungan dengan laju pembangunan di Indonesia yang terasa semakin

ANALISIS BIAYA PEMAKAIAN ALAT BERAT PADA PAKET REKONSTRUKSI JALAN PEMATANG REBA SIBERIDA (B)

PERCEPATAN PROYEK DENGAN MENGGUNAKAN METODE WHAT IF

PERHITUNGAN PEMINDAHAN TANAH MEKANIS PADA PEKERJAAN PEMATANAGN LAHAN PERUMAHAN PANORAMA ALAM ASRI II KEC. SUNGAI KUNJANG SAMARINDA

MANAJEMEN ALAT BERAT PADA PEKERJAAN TANAH PROYEK PEMBANGUNAN JALAN AP-10 BATANG WELERI (III) JATENG

B2 STA STA KM

ANALISIS PRODUKTIVITAS ALAT-ALAT BERAT STUDI KASUS PROYEK PEMBANGUNAN JALAN ANTARTIKA II DI KAWASAN INDUSTRI KRAKATAU STEEL, CILEGON

Jurnal Kontruksi Sekolah Tinggi Teknologi Garut Jl. Mayor Syamsu No.2, Tarogong Kidul, Garut

EVALUASI PELAKSANAAN PROYEK PEMELIHARAAN BERKALA JALAN PRACIMANTORO-GEDANGKLUTUK KABUPATEN WONOGIRI TESIS

BAB III METODOLODI PERHITUNGAN

REKAPITULASI DAFTAR KUANTITAS DAN HARGA

PROYEK AKHIR PU. Perencanaan Pelaksanaan Proyek Pengaspalan Jalan Bungadidi Poreang STA STA Kab. Luwu Utara Prov.

OPTIMALISASI PENGGUNAAN ALAT BERAT PADA PEKERJAAN GALIAN TANAH DI PROYEK TOL NGANJUK - KERTOSONO NASKAH PUBLIKASI TEKNIK SIPIL

OPTIMALISASI PENGGUNAAN ALAT BERAT PADA PEKERJAAN GALIAN TANAH

METODE PELAKSANAAN PEKERJAANPADA PAKET PELEBARAN JALAN SIDIKALANG BATAS PROVINSI NAD LAPORAN

TINJAUAN PELAKSANAAN PEMADATAN TANAH UNTUK PEKERJAAN JALAN DI KABUPATEN PURBALINGGA

ARDYCHA PRAYUDHA NRP

ANALISA KEBUTUHAN PEMAKAIAN ALAT BERAT PADA PROYEK PEMBANGUNAN JALAN TUGU COKLAT PARIT MALINTANG KABUPATEN PADANG PARIAMAN

ABSTRAK. Kata kunci : data insinyur, data material, data excavator, data dump truck, data proyek. vii Universitas Kristen Maranatha

STUDI DAMPAK PEMBEBASAN LAHAN TERHADAP ASPEK BIAYA DAN ASPEK WAKTU PADA PROYEK PEMBANGUNAN JALAN TOL SURABAYA MOJOKERTO SEKSI IA

UNIVERSITAS 17 AGUSTUS 1945 SAMARINDA

Jurnal Teknik Sipil Untag Surabaya 163

ZULFIKAR JAUHARI NRP

ANALISIS KAPASITAS PRODUKSI EXCAVATOR PADA PROYEK PERUMAHAN PERTAMINA CIBUBUR

OPTIMALISASI KOMPOSISI ALAT BERAT PADA PROYEK PEMBANGUNAN PELABUHAN PT. CEMINDO GEMILANG

BAB I PENDAHULUAN 1.1 Latar Belakang

BAB I PENDAHULUAN. 1.1 Latar Belakang

ESTIMASI WAKTU DAN PENENTUAN BIAYA PELAKSANAAN PEMBANGUNAN JALAN RAYA TRENGGALEK PACITAN KM KM PROVINSI JAWA TIMUR

STUDI MONITORING PERCEPATAN WAKTU PELAKSANAAN PADA PROYEK PEMBANGUNAN JALAN SIRTU NYAMA-MOAIN KABUPATEN MALUKU BARAT DAYA

PENGEMBANGAN TANAH MEKANIK (PTM) & ALAT ALAT BERAT OLEH. FILIYANTI TETA ATETA BANGUN, ST., M.Eng. NIP

MACAM-MACAM ALAT-ALAT BERAT

ANALISA BIAYA PENGGUNAAN ALAT BERAT

Optimasi Biaya Penggunaan Alat Berat Untuk Pekerjaan Pengangkutan Dan Penimbunan Pada Proyek Grand Island Surabaya Dengan Program Linier

PERENCANAAN PEMAKAIAN ALAT BERAT PADA PEKERJAAN TANAH PROYEK PEMBANGUNAN JALAN BANDA ACEH CALANG STA SUMATRA

KAJIAN TEKNIS KERJA ALAT GALI MUAT UNTUK PENGUPASAN LAPISAN TANAH PUCUK PADA LOKASI TAMBANG BATUBARA DI PIT

BAB I PENDAHULUAN 1.1 Latar Belakang

2 Dosen Jurusan Teknik Pertambangan, Sekolah Tinggi Teknologi Nasional.

BAB I PENDAHULUAN. I.1 Latar Belakang

PERHITUNGAN ALAT BERAT UNTUK PEKERJAAN LPB PADA PENINGKATAN JALAN CILIK RIWUT DI KECAMATAN MURUNG KALIMANTAN TENGAH

NAMA MAHASISWA : ADALEA IVANA PRAJWALITA NRP

BAB I PENDAHULUAN. 1.1 Latar Belakang

METODE PELAKSANAAN PENINGKATAN STRUKTUR JALAN TEBINGTINGGI (WATAS SERDANGBEDAGAI) - SIPISPIS DI KABUPATEN SERDANGBEDAGAI

DAFTAR UPAH TENAGA KERJA

RENCANA ANGGARAN BIAYA PEKERJAAN PENINGKATAN JALAN SEKSI II RANCABUAYA KM.BD

METODA PELAKSANAAN PEKERJAAN PAKET 34 (JALAN SERUNAI MALAM II, JALAN SERUNAI MALAM I, JALAN BERSAMA)

STUDI PENANGANAN JALAN RUAS BUNDER LEGUNDI AKIBAT PEKEMBANGAN LALU - LINTAS

EVALUASI PENCAPAIAN TARGET PRODUKSI ALAT MEKANIS UNTUK PEMBONGKARAN OVERBURDEN DI PIT 4 PT DARMA HENWA SITE ASAM-ASAM

EVALUASI KINERJA EXCAVATOR BACKHOE

SIMULASI PERENCANAAN PENGGUNAAN ALAT BERAT PADA PEKERJAAN PENGGALIAN TANAH

BAB VII METODE PELAKSANAAN

JURUSAN SIPIL F AKUL T AS TEKNIK UNIVERSITAS HASANUDDIN 2016

Jurnal Ilmiah Universitas Batanghari Jambi Vol.15 No.3 Tahun 2015

Optimasi Biaya Penggunaan Alat Berat untuk Pekerjaan Pengangkutan dan Penimbunan pada Proyek Grand Island Surabaya dengan Program Linier

Perencanaan Tebal Lapis Tambah Perkerasan Lentur Menggunakan Metode Benkelman Beam Pada Ruas Jalan Kabupaten Dairi-Dolok Sanggul, Sumatera Utara

GAYA SILINDER STICK DAN SILINDER BUCKET PADA EXCAVATOR 320 CATERPILLAR AKIBAT GAYA POTONG

DISTRIBUTION OF HIGHWAY AXLE LOADS IN WEST JAVA AND METHODS OF MEASURING VEHICLE LOADING

PROYEK AKHIR. PERENCANAAN ULANG PENINGKATAN JALAN PASURUAN-PILANG STA s/d STA PROVINSI JAWA TIMUR

ANALISIS PEMENUHAN DAN PEMANFAATAN ALAT BERAT UNTUK PEKERJAAN JALAN

PRODUKTIVITAS ALAT BERAT PADA PEKERJAAN GALIAN GEDUNG P1 P2 UK PETRA

BAB 4 HASIL DAN PEMBAHASAN

ANALISIS EFISIENSI PRODUKTIVITAS WAKTU KERJA ALAT BERAT PADA PEMBANGUNAN JALAN (Studi Kasus : Ruas Jalan Tangkeh Blang Luah Cs, Woyla Timur)

LOADER Alat untuk memuat material ke dump truck, atau memindahkan material, penggalian ringan. Produksi per jam (Q)

BIAYA DAN KEBUTUHAN ALAT BERAT UNTUK PEMINDAHAN TANAH (Studi Kasus :Pekerjaan Timbunan Tanah di Baturetno, Wonogiri) Dian Arumningsih D.P.

HARGA PERKIRAAN SENDIRI (HPS)

Manajemen Pelaksanaan Pembangunan Konsolidasi Dam di Hilir Syphon Lemurung Kabupaten Kediri

HARGA PERKIRAAN SENDIRI (HPS)

STUDI KASUS : PROYEK PELEBARAN JALAN BATU AJI KUARO, KALIMANTAN TIMUR, MULTIYEARS CONTRACT (MYC) MUHAMMAD HAYKAL NIP

PERATAAN SUMBER DAYA BIAYA TENAGA KERJA DENGAN MENGGUNAKAN PROGRAM MICROSOFT OFFICE PROJECT 2007

BAB VIII RENCANA ANGGARAN BIAYA

OPTIMASI PENGGUNAAN ALAT BERAT DILIHAT DARI WAKTU DAN BIAYA

EFISIENSI PENGGUNAAN ECOMIX PADA KONSTRUKSI FLEXIBLE PAVEMENT

Majalah Ilmiah, Vol. 23, No. 2, Oktober 2016, Hal ISSN : Copyright 2016 by LPPM UPI YPTK Padang

TAHAP PELAKSANAAN PEKERJAAN TANAH

STUDI KASUS : PROYEK PELEBARAN JALAN BATU AJI KUARO, KALIMANTAN TIMUR, MULTIYEARS CONTRACT (MYC) MUHAMMAD HAYKAL NIP

DAFTAR KUANTITAS DAN HARGA

PEMERINTAH KOTA KUPANG UNIT LAYANAN PENGADAAN (ULP) KOTA KUPANG Kelompok Kerja Pengadaan Konstruksi

HARGA PERKIRAAN SENDIRI (HPS)

FORMULIR STANDAR UNTUK PEREKAMAN ANALISA MASING-MASING HARGA SATUAN PERKIRAAN HARGA JUMLAH NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA

Transkripsi:

EVALUASI PENGGUNAAN ALAT-ALAT BERAT PROYEK Studi Kasus : Proyek Pembangunan Jalan Sei Rakyat Labuhan Bilik Sei Berombang Kecamatan Panai Tengah Panai Hilir Kabupaten Labuhan Batu Syafriani 1, Ir. Joni Harianto 2 1Mahasiswa Departemen Teknik Sipil, Universitas Sumatera Utara, Jl. Perpustakaan No. 1 Kampus USU Medan Email: anie.nasution@yahoo.co.id 2 Staf Pengajar Departemen Teknik Sipil, Universitas Sumatera Utara, Jl. Perpustakaan No. 1 Kampus USU Medan ABSTRAK Ruas jalan Sei Rakyat Labuhan Bilik Sei Berombang Kecamatan Panai Tengah- Panai Hilir yang berada di Kabupaten Labuhan Batu, menghubungkan Labuhan Bilik dengan Sei Berombang yang mempunyai peranan penting sebagai penghubung lalu lintas dan juga sebagai penunjang pertumbuhan ekonomi di daerah Labuhan Batu dalam sektor kehidupan sehari-hari masyarakat Labuhan Batu. Dalam melaksanakan pekerjaaan pembangunan jalan ini, diperlukan alat-alat berat seperti: Penggilas Roda Besi (6-9 ton), Penggilas Bervibrasi (1.5-3.0 PK), Penggilas Roda Karet ( 8-10 ton), Alat Penggali (Excavator Backhoe), Motor Grader, Dump truk. Dalam penelitian ini yang akan dibahas adalah evaluasi penggunaan dan pemanfaatan alat-alat berat pada Proyek tersebut dengan Metode Bina Marga dan Metode Caterpillar. Hasil perhitungan evaluasi dengan metode Caterpillar menunjukkan hasil yang lebih efektif dibandingkan dengan menggunakan metode Bina Marga. Dimana hasil perhitungan Bina Marga untuk Excavator 67 hari, Motor Grader 27 hari, Penggilas Roda Besi 2 hari, Penggilas bervibrasi 16 hari, dan penggilas roda karet 1 hari. Sedangkan hasil perhitungan dengan menggunakan metode Caterpillar untuk Excavator 57 hari, Motor Grader 12 hari, Penggilas Roda Besi 4 hari, Pemggilas Bervibrasi 4 hari, dan Penggilas Roda karet 4 hari, adapun pelaksanaan proyek ini dapat diselesaikan dalam waktu 120 hari. Kata Kunci: Evaluasi, Alat Berat, Bina Marga, Caterpillar. ABSTRACK Sei Rakyat - Labuhan Bilik - Sei Berombang roads district Panai Tengan Panai Hilir its Labuhan Batu district, Labuhan Bilik connect with Sei Berombang that has an important role as the link traffic and also to support economic growth in the life sector in Labuhan Batu. In carrying out the occupation of road construction would require heavy equipment such as: Steel Wheels roller (6-9 tons), vibration roller (1.5-3.0 PK), rubber wheels roller (8-10 ton), Excavator (Backhoe), Motor Grader, Dump truck. In this research will be discussed is the evaluation of the use and utilization of heavy equipment on the project with the method of Bina Marga and Caterpillar Methods. The results of the evaluation by the method of calculation Caterpillar showed results more effective than using the methods of Bina Marga. Where the calculation results of Bina Marga for 67 days Excavators, Motor Graders 27 days, Steel Wheels roller 2 days, 16 days vibrating roller, and rubber wheels roller one day. While the results of the calculation using the Caterpillar for 57 days Excavators, Motor Graders 12 days, steel wheels roller 4 days, 4 days vibration roller, and rubber wheels roller 4 days, while the implementation of this project can be completed within 120 days. Keywords: Evaluation, Heavy of Equipment, Bina Marga, Carterpillar. 1. PENDAHULUAN Proyek Pembangunan Jalan adalah salah satu proyek yang bertujuan untuk memperlancar arus lalu lintas pada arus jalan yaitu dengan melakukan pembangunan, pengaspalan dan penyediaan fasilitas

jalan.dalam melaksanakan pekerjaaan ini diperlukan alat-alat berat seperti: Penggilas Roda Besi (6-9 ton), Penggilas Bervibrasi (1.5-3.0 PK), Penggilas Roda Karet ( 8-10 ton), Alat Penggali (Excavator Backhoe), Motor Grader, Dump truk. 2. TUJUAN DAN MANFAAT PENELITIAN Tujuan penelitian ini adalah: 1) Mengetahui waktu yang di butuhkan alat alat berat pada pengerjaan proyek. 2) Mengetahui Produktivitas dari alat alat berat pada pengerjaan proyek Manfaat penelitian ini adalah: 1) Menambah wawasan bagi peneliti mengenai optimalisasi pengelolaan dan pemanfaatan alat berat pada pengerjaan proyek pembangunan jalan. 2) Memberikan sumbangan pemikiran bagi para kontraktor dalam pemilihan alat berat sesuai dengan kondisi medan. 3) Menambah referensi bagi pembaca/pengamat tentang wacana manajemen proyek alat berat pengelolaan dan pemamfaatan yang lebih baik pada pekerjaan sipil, sesuai dengan tujuan penelitian dalam kasus ini 3. PEMBATASAN MASALAH Dari permasalahan yang ada diatas maka masalah dibatasi pada alat-alat berat yang digunakan pada pengerjaan Proyek Pembangunan Jalan Sei Rakyat Labuhan Bilik Sei Berombang Kecamatan Panai Tengah Panai Hilir Kabupaten Labuhan Batu. 1) Mengetahui waktu yang akan dibutuhkan alat-alat berat pada pengerjaan proyek pembangunan jalan. 2) Menghitung produktivitas dari alat-alat berat pada pengerjaan proyek pembangunan jalan. 3) Mengevaluasi penggunaan alat alat berat yang digunakan dengan alat berat lain yang sejenis. 4) Galian pada perhitungan tugas akhir ini dibatasi pada galian yang ada pada daftar kuantitas yaitu galian struktur, dan timbunan yang dihitung adalah timbunan pilihan, sesuai dengan daftar kuantitas Proyek Pembangunan Jalan Sei Rakyat Labuhan Bilik Sei Berombang Kecamatan Panai Tengah Panai Hilir Kabupaten Labuhan Batu 4. METODE PENELITIAN Metodologi yang digunakan pada penulisan ini adalah : 1) Pengambilan data-data perencanaan di lapangan dari dinas Pekerjaan Umum 2) Studi literature dan referensi diperoleh dari buku-buku jalan raya, alat-alat berat, ringkasan perencanaan proyek dan buku-buku literature lainnya yang mendukung dan menyangkut tentang masalah yang berkaitan dengan tugas akhir ini. 3) Studi dokumentasi dimaksudkan untuk mendapatkan data-data dokumentasi dalam pelaksanaan pengerjaan proyek. 4) Menganalisis produktivitas dari alat-alat berat yang digunakan 5. PENYAJIAN DATA Dari pengolahan data dalam penelitian ini diharapkan dapat meningkatkan kualitas, efisiensi waktu dan biaya sehingga dapat dievaluasi penggunaan alat berat pada proyek ini 5.1 DATA PENGAMATAN WAKTU SIKLUS ALAT Berikut ini adalah data pengamatan waktu siklus alat berat yang digunakan pada proyek pembangunan jalan Sei Rakyat Labuhan Bilik Sei Berombang Kecamatan Panai Tengah Panai Hilir Kabupaten Labuhan Batu, sebagai berikut:

Tabel III.1 Pengamatan Waktu Siklus excavator Waktu meluncurkan bucket ketempat galian 7 8 6 5 9 7 Waktu menggali 12 11 13 13 12 13 Waktu mengangkat dan menarik bucket 5 7 6 6 6 6 Waktu membuang 6 7 6 5 6 6 Siklus: 32 detik Tabel III.2 Kecepatan Operasi Penggilas Roda Besi Jarak lintasan (m) 20 20 20 20 20 20 Waktu pengamatan (detik) 44 42 42 43 33 43 Kecepatan operasi (m 2/ detik) 0,455 0,476 0,476 0,476 0,488 0,4742 Tabel III.3 Kecepatan Operasi Penggilas Bervibrasi Jarak lintasan (m) 20 20 20 20 20 22 Waktu pengamatan (detik) 32 30 32 33 34 30 Kecepatan operasi (m/detik) 0,625 0,67 0,625 0,689 0,741 0,67 Tabel III.4 Kecepatan operasi penggilas roda karet Jarak lintasan (m) 20 20 20 20 20 20 Waktu pengamatan (detik) 31 30 32 29 27 32 Kecepatan operasi (m/detik) 0,625 0,67 0,625 0,689 0,741 0,67 Tabel III.5 Pengamatan waktu siklus dump truck Waktu mengambil posisi loading 1'20" 1'17" 1'18" 1'21" 1'19" 1'19" Waktu Loading 15'11' 14'55' 14'35' 14'42' 15'15' 15'18" Waktu angkut 57'20" 59'12" 55'58" 58'55" 58'16" 57'71" Waktu mengambil posisi unloading 57" 52" 50" 58" 56" 54,6" Waktu unloading 13'52" 12'45" 12'15" 13'23" 12'37" 13'23" Waktu kembali 25'41" 24'35" 24'15" 23'48" 24'17" 24'31" Waktu siklus: 166,4

5.2 DAFTAR KEGIATAN 1) Galian untuk drainase dan saluran air = 5.062,50 m 3 2) Galian struktur dengan kedalaman 0-2 meter = 200,00 m 3 3) Timbunan pilihan = 37.073,25 m 3 4) Penyiapan badan jalan = 60.750,00 m 2 5) Lapis pondasi aggregat kelas C = 2.193,75 m 3 6. HASIL PERHITUNGAN Dari hasil perhitungan sebelumnya, didapat produktivitas untuk masing-masing alat berat yang digunakan sebagai berikut: A. Metode Bina Marga 1) Excavator = 64,23 m 3 /jam 2) Motor Grader = 491,54 jam 3) Penggilas roda besi (Smooth Steel Roller) = 117,65 m 3 /jam 4) Penggilas bervibrasi (Vibrating Roller) = 239,04 m 3 /jam 5) Penggilas roda karet (Pneumatic Tired Roller) = 280,13 m 3 /jam 6) Dump truck = 14,1 m 3 /jam B. Metode Caterpillar 1. Excavator = 65 m 3 /jam 2. Motor Grader = 12,15 m 3 /jam 3. Penggilas roda besi (Smooth Steel Roller) = 61,84 m 3 /jam 4. Penggilas bervibrasi (Vibrating Roller) = 239,04 m 3 /jam 5. Penggilas roda karet (Pneumatic Tired Roller) = 280,13 m 3 /jam 6. Dump truck = 39,76 m 3 /jam Berdasarkan time schedule pada pekerjaan dilapangan, jam kerja dalam satu hari adalah 10 jam. Jadi dalam hal ini yang dimaksud dalam perhitungan hanyalah Excavator, Penggilas roda besi (Smooth Steel Roller), Penggilas bervibrasi (Vibrating Roller), dan Penggilas roda karet (Pneumatic Tired Roller). Maka total produktivitas alat alat berat perhari adalah: Kapasitas produksi perhari = kapasitas produksi perjam x waktu kerja perhari - Excavator = 65 m 3 /jam x 10 jam = 650 m 3 /hari - Penggilas roda besi = 61,84 m 3 /jam x 10 jam = 618,4 m 3 /hari - Penggilas bervibrasi = 61,84 m 3 /jam x 10 jam = 618,4 m 3 /hari - Penggilas roda karet = 61,84 m 3 /jam x 10 jam = 618,4 m 3 /hari Waktu yang dibutuhkan alat untuk pekerjaan pelapisan jalan raya pada lapisan aggregat kelas C: - Panjang penanganan jalan = 22,78 km - Lebar jalan yang dilapisi = 6 m

- Tebal timbunan pilihan = 27 cm - Volume total pekerjaan = 22780 m x 6 m x 0,27 m = 37.073,25 m 3 volume total pekerjaan - Waktu pelaksanaan = produktivitas alat per hari - Excavator = 37.273,25m3 650 m3/hari = 57 hari - Penggilas roda besi = 2.193,75m3 618,4 m3/hari = 4 hari 2.193,75m3 - Penggilas bervibrasi = 618,4 m3/hari = 4 hari 2.193,75m3 - Penggilas roda karet = 618,4 m3/hari = 4 hari Pekerjaan pembangunan jalan Sei Rakyat Labuhan Bilik Sei Berombang Kecamatan Panai Tengah Panai Hilir Kabupaten Labuhan Batu, keempat alat-alat berat bekerja secara seri dan berkaitan secara langsung maka total waktu yang dibutuhkan selama pekerjaan pembangunan jalan dengan metode bina marga adalah 113 hari dan dengan metode caterpillar adalah 79 hari. 7. KESIMPULAN DAN SARAN 7.1 KESIMPULAN 1. Dari hasil perhitungan yang dilakukan terhadap waktu pemakaian alat-alat berat: Excavator, Motor Grader, Penggilas roda besi, Penggilas bervibrasi, Penggilas roda karet pada pelaksanaan Proyek Pembangunan Jalan Sei Rakyat Labuhan Bilik Sei Berombang Kecamatan Panai Tengah Panai Hilir Kabupaten Labuhan Batu. A. Metode Bina Marga Excavator : 67 hari Motor Grader : 27 hari Penggilas roda besi : 2 hari Penggilas bervibrasi : 16 hari Penggilas roda karet : 1 hari Maka total waktu yang digunakan adalah 113 hari B. Metode Caterpillar 1. Excavator : 57 hari 2. Motor Grader : 12 hari 3. Penggilas roda besi : 4 hari 4. Penggilas bervibrasi : 4 hari 5. Penggilas roda karet : 4 hari Maka total waktu yang digunakan adalah 79 hari 2. Total waktu yang dibutuhkan selama pekerjaan pembangunan jalan dengan metode Bina Marga adalah 113 hari dan dengan Metode Caterpillar adalah 79 hari dan secara seri berkaitan langsung satu sama lain. 3. Maka penggunaan alat-alat berat pada proyek ini belum efisien, disebabkan oleh kondisi alat yang tidak baik lagi jadi memperlambat kecepatan operasi alat. 7.2 SARAN Untuk pemakaian waktu seefisien mungkin perlu diperhatikan : 1. Rencana pemakaian alat-alat berat, sebaiknya terlebih dahulu dilakukan perhitungan yang teliti agar pemanfaatannya lebih efisien 2. Untuk proyek besar seperti Proyek Pembangunan Jalan Sei Rakyat Labuhan Bilik Sei Berombang Kecamatan Panai Tengah Panai Hilir Kabupaten Labuhan Batu ini perlu

dipertimbangkan untuk mempergunakan peralatan sendiri, bukan dengan menggunakan alat sewa, karena biaya sewa yang sangat tinggi. 3. Untuk proyek besar seperti Proyek Pembangunan Jalan Sei Rakyat Labuhan Bilik Sei Berombang Kecamatan Panai Tengah Panai Hilir Kabupaten Labuhan Batu ini lebih menguntugkan menggunakan Metode Caterpillar dibandingkan dengan menggunakan Metode Bina Marga 8. DAFTAR PUSTAKA - Agustia, P., R., (2008), Pemilihan Alat Berat untuk Pekerjaan Tanah Pada Proyek Pembangunan Jalan Tol Susun Waru Bandara Juanda Sta 0+816 Sta 1+214 Tinjauan Biaya dan Waktu, Tugas Akhir Mahasiswa, Institut Teknologi Sebelas Maret, Surabaya. - Bangun, F.,T.,A., (2009), Diktat Kuliah Pengembangan Tanah Mekanik dan Alat Alat Berat Bagian I - VI, Tidak dipublikasi. - Anonim, (2010), Caterpillar Performance Handbook, Caterpillar Inc, Illinois, USA. - Anonim, (2010), Analisa Harga Satuan Spec. Edisi 2010, Direktorat Jenderal Bina Marga, Jakarta. - Sumardikatmodjo, Igig, (2003), Alat Alat Berat, Tidak dipublikasi. - Rasyid, M., R., (2008), Analisis Prodiuktifitas Alat Alat Berat Proyek (Studi Kasus: Proyek Pengembangan Bandar Udara Hasanuddin, Maros, Makassar, Tugas Akhir Mahasiswa, Universitas Islam Indonesia, Yogyakarta. - Rochmanhadi, (2000), Kapasitas dan Produksi Alat Alat Berat, Departemen Pekerjaan Umum, Jakarta