PT MEDCO POWER INDONESIA

Ukuran: px
Mulai penontonan dengan halaman:

Download "PT MEDCO POWER INDONESIA"

Transkripsi

1 PT MEDCO POWER INDONESIA

2 BUSINESS OVERVIEW BUSINESS OVERVIEW INDEPENDENT POWER PRODUCER Thermal Energy Electricity Generation Renewable Energy Electricity Generation Hydro & Geothermal POWER PLANT SERVICES Operations & Maintenance Services 2

3 3 MPI Portfolio OPERATING ASSETS IPP Fuel Type MW MEB Combine Cycle Gas 85 DEB Combine Cycle Gas 85 TM 2500 Gas 20 ELB Simple Cycle Gas 76 EPE Gas 12 MPE Gas 12 Singa Gas 7 TOTAL CAPACITY 297 O&M Services COMMITTED PROJECTS IPP COD MW ELB Combined Cycle Mini Hydro Sarulla Geothermal Ijen Geothermal CCPP Riau TOTAL 795 Coal Fired TJBPS Coal 1320 Geothermal Sarulla Geothermal 330 MEB PLN Batam scattered Gas 500 Total Capacity MW Operating Asset MW asset under construction 2150 MW 3 rd party O&M business

4 MPI Working Area TM2500 Gas 75 MW (O&M) Duri MEB Gas 85 MW Batam Island 2004 Riau CCPP 275 MW Riau 2021 TM2500 Gas 75 MW (O&M) Paya Pasir Sarulla Geothermal 330 MW North Sumatera DEB Gas 85 MW Batam Island 2006 TM2500 Gas 20 MW Batam Island 2007 ELB Gas 76 MW Batam Island 2015 TM2500 Gas 100 MW (O&M) Pontianak Sarulla Geothermal 330 MW (O&M) North Sumatera TM2500 Gas 25 MW (O&M) Nias Island NES Mini Hydro 8 MW West Sumatera 2019 TM2500 Gas 50 & 25 MW (O&M) Bangka - Belitung TJBPS Coal 1320 MW (O&M) Central Java 2006 Ijen Geothermal 110 MW East Java TM2500 Gas 50 MW (O&M) Lombok EPE Gas 12 MW South Sumatera 2006 MPE Gas 12 MW South Sumatera 2008 Singa Gas 7 MW South Sumatera 2010 TM2500 Gas 100 MW (O&M) Lampung BJI Mini Hydro 9 MW West Java PPP Mini Hydro 9 MW West Java 2017 SHB Mini Hydro 13 MW West Java 2019 Own & operate by MPI 3 rd party power plant operate by MPI 4 4

5 OPERATING ASSETS - IPP Mitra Energi Batam (MEB) Panaran, Batam Dalle Energy Batam (DEB) Panaran, Batam TM 2500 Panaran, Batam ELB Tanjung Uncang, Batam PPA to 2034 Natural gas fueled Combined Cycle (Rolls Royce Aero Derivative RB211) Cap 85MW PPA to 2025 Natural gas fueled Combined Cycle (Rolls Royce Aero Derivative RB211.) Total Cap 85 MW Back up unit Natural gas fueled General Electrics Truck Mounted Derivative. Cap 20 MW PPA to 2036 Natural gas fueled Simple Cycle (GE Frame 6 B). Total Cap 76 MW Energi Prima Elektrika Prabumulih, S. Sumatra Multidaya Prima Elektrindo Sako, S. Sumatra Singa Palembang, S. Sumatra PPA to 2026 Natural gas fueled Wartsilla 18V 34 SG Gas Engine. Cap 12 MW PPA to 2028 Natural gas fueled Wartsilla 18V 34 SG Gas Engine. Cap 12MW PPA to 2017 Natural gas fueled Turbomach Gas Turbine Cap 7 MW

6 UNDER CONSTRUCTION PROJECTS BJI Mini Hydro 9 MW West Java Construction progress: 86% COD expected in 2017 Sarulla Geothermal 330 MW North Sumatera In process of commissioning unit MW COD expected in Riau Gas Fired Combined Cycle 275 MW Riau PPA negotiation process, expected signing by Q COD expected in 2021 Ijen Geothermal 110 MW East Java In process of slim hole drilling COD expected in

7 General Investor Concern Resiko Proyek dan Investor Return (IRR) : Required return (IRR Proyek) tergantung dari besarnya resiko. Semakin besar resiko suatu proyek maka akan semakin besar pula profit yang diharapkan proyek tersebut. Untuk mendapatkan harga yang lebih ekonomis, adalah bagaimana kita bisa menurunkan resiko tersebut. Kemudahan perizinan Kemudahan pengadaan tanah

8 Resiko Pembangkit Listrik Tenaga Gas Mismatch antara periode GSA (Gas Supply Agreement ) dan PPA (Power Purchase Agreement) Sampel untuk beberapa kasus di anak perusahaan PT Medco Power Indonesia : IPP Location Gas Volume GSA Expired PPA Expired MEB Batam 13.2 mmscfd DEB Batam 14.5 mmscfd ELB Batam 24 mmscfd MPE South Sumatera 2 mmscfd EPE South Sumatera 2 mmscfd

9 Resiko Geothermal Resiko Eksplorasi / Sub Surface Setelah Pengeboran eksplorasi selesai baru diketahui feasibility dari proyek, antara lain : Besaran Reserve / Cadangan Panas Bumi Biaya Produksi Resource Parameter : Fluid ph, Temperature & H2S Resiko Sumber Daya Manusia Sebagai negara dengan potensial reserve terbesar di dunia, kita memiliki sedikit expert/expertise di bidang geothermal Di negara lain ternyata expert/expertise yang ada juga sangat terbatas

10 THANK YOU

KATA PENGANTAR FOREWORD

KATA PENGANTAR FOREWORD KATA PENGANTAR Buku Statistik Ketenagalistrikan No. 29-2016 disusun berdasarkan data ketenagalistrikan hingga akhir 2015 dari beberapa unit di lingkungan Kementerian Energi dan Sumber Daya Mineral dan

Lebih terperinci

KATA PENGANTAR. Saran dan kritik membangun untuk penerbitan selanjutnya dapat disampaikan melalui e- mail : go.id

KATA PENGANTAR. Saran dan kritik membangun untuk penerbitan selanjutnya dapat disampaikan melalui e- mail : go.id KATA PENGANTAR Buku Statistik Ketenagalistrikan No. 25-2012 disusun berdasarkan data ketenagalistrikan hingga akhir 2011 dari beberapa unit di lingkungan Kementerian Energi dan Sumber Daya Mineral dan

Lebih terperinci

KEBIJAKAN DALAM PENGUSAHAAN PANAS BUMI PASCA UU NOMOR 27 TAHUN 2003 DEPARTEMEN ENERGI DAN SUMBER DAYA MINERAL

KEBIJAKAN DALAM PENGUSAHAAN PANAS BUMI PASCA UU NOMOR 27 TAHUN 2003 DEPARTEMEN ENERGI DAN SUMBER DAYA MINERAL KEBIJAKAN DALAM PENGUSAHAAN PANAS BUMI PASCA UU NOMOR 27 TAHUN 2003 Dr. Ir. Simon Felix Sembiring DIREKTUR JENDERAL SUMBER DAYA MINERAL, BATUBARA DAN PANAS BUMI Jl. Prof. Dr. Soepomo, SH. No. 10, Jakarta

Lebih terperinci

Paparan Publik Memberikan Nilai

Paparan Publik Memberikan Nilai Paparan Publik 2017 Memberikan Nilai www.medcoenergi.com November 2017 Daftar Isi 2 Pembukaan 3 Direksi MedcoEnergi 4 Tonggak Pencapaian Perseroan 5 Kinerja 1H17 Ikhtisar 2017 6 Kinerja Operasi 7 Kinerja

Lebih terperinci

KATA PENGANTAR FOREWORD

KATA PENGANTAR FOREWORD ii KATA PENGANTAR Buku Statistik Ketenagalistrikan No. 30-2017 disusun berdasarkan data ketenagalistrikan hingga akhir 2016 dari beberapa unit di lingkungan Kementerian Energi dan Sumber Daya Mineral dan

Lebih terperinci

Statistik Ketenagalistrikan

Statistik Ketenagalistrikan KEMENTERIAN ENERGI DAN SUMBER DAYA MINERAL Statistik Ketenagalistrikan 2014 Edisi No. 28 Tahun Anggaran 2015 Statistik Ketenagalistrikan 2014 Edisi No. 28 Tahun Anggaran 2015 KEMENTERIAN ENERGI DAN SUMBER

Lebih terperinci

PPPs PRIORITY PROJECTS

PPPs PRIORITY PROJECTS PPPs PRIORITY PROJECTS Financial Overview (in million) No Project Title Type of Project Proposal Contracting Agency Project Location Estimated Project Value Land Acquisition Construction 1 MedanBinjai

Lebih terperinci

DRAFT BUKU STATISTIK

DRAFT BUKU STATISTIK DRAFT BUKU STATISTIK ii DIREKTORAT JENDERAL KETENAGALISTRIKAN KATA PENGANTAR Buku Statistik Ketenagalistrikan No. 27-2014 disusun berdasarkan data ketenagalistrikan hingga akhir 2013 dari beberapa unit

Lebih terperinci

PLTU SURALAYA BANTEN

PLTU SURALAYA BANTEN PLTU SURALAYA BANTEN KATA PENGANTAR Buku Statistik Ketenagalistrikan No. 26-2013 disusun berdasarkan data ketenagalistrikan hingga akhir 2012 dari beberapa unit di lingkungan Kementerian Energi dan Sumber

Lebih terperinci

PERKEMBANGAN PENGELOLAAN KEWAJIBAN KONTINJENSI TRIWULAN III TAHUN 2015

PERKEMBANGAN PENGELOLAAN KEWAJIBAN KONTINJENSI TRIWULAN III TAHUN 2015 PERKEMBANGAN PENGELOLAAN KEWAJIBAN KONTINJENSI TRIWULAN III TAHUN 2015 A. POSISI EKSPOSUR KEWAJIBAN PENJAMINAN PEMERINTAH (PER 30 SEPTEMBER 2015) 1. Program Penjaminan berdasarkan Jenis Penjaminan: Pihak

Lebih terperinci

KATA PENGANTAR. Saran dan kritik membangun untuk penerbitan selanjutnya dapat disampaikan melalui go.id

KATA PENGANTAR. Saran dan kritik membangun untuk penerbitan selanjutnya dapat disampaikan melalui   go.id KATA PENGANTAR Buku Statistik Ketenagalistrikan dan Energi No. 23 2010 disusun berdasarkan data dari beberapa unit di lingkungan Kementerian Energi dan Sumber Daya Mineral dan stakeholders terkait. Data

Lebih terperinci

xunaa [printed: ] [saved: ] Presentation2

xunaa [printed: ] [saved: ] Presentation2 www.truba-manunggal.com Profil Bisnis Perusahaan jasa konstruksi dan tenaga listrik yang terintegrasi EPC IPP O&M Lebih dari 30 tahun berpengalaman di bidang teknik, disain, pengadaan, konstruksi dan pemeliharaan

Lebih terperinci

KATA PENGANTAR. Saran dan kritik membangun untuk penerbitan selanjutnya dapat disampaikan melalui go.id

KATA PENGANTAR. Saran dan kritik membangun untuk penerbitan selanjutnya dapat disampaikan melalui   go.id KATA PENGANTAR Buku Statistik Ketenagalistrikan dan Energi No. 24 2011 disusun berdasarkan data dari beberapa unit di lingkungan Kementerian Energi dan Sumber Daya Mineral dan stakeholders terkait. Data

Lebih terperinci

Operational Region of PLN

Operational Region of PLN Operational Region of PLN Data Over Nine Years 2003-2011 Operational Regions and Location of PLN Region Of ces 80 PLN Statistics 2011 STK 310512 PLN Statistics 2011 81 PLN Region Offices and Subsidiaries

Lebih terperinci

ANALISIS DAMPAK KENAIKAN HARGA MINYAK MENTAH DAN BATUBARA TERHADAP SISTEM PEMBANGKIT DI INDONESIA

ANALISIS DAMPAK KENAIKAN HARGA MINYAK MENTAH DAN BATUBARA TERHADAP SISTEM PEMBANGKIT DI INDONESIA ANALISIS DAMPAK KENAIKAN HARGA MINYAK MENTAH DAN BATUBARA TERHADAP SISTEM PEMBANGKIT DI INDONESIA Hari Suharyono ABSTRACT Power generation in Indonesia relies on coal and refined products, more than 60%

Lebih terperinci

PT Nusantara Infrastructure, Tbk Paparan Publik Jakarta, 24 Mei PT Nusantara Infrastructure Tbk

PT Nusantara Infrastructure, Tbk Paparan Publik Jakarta, 24 Mei PT Nusantara Infrastructure Tbk PT Nusantara Infrastructure, Tbk Paparan Publik Jakarta, 24 Mei 2013 Total Volume Traffic 2012 Total Volume Traffic 2012 : 78.254.020 kendaraan 12% dari 2011 2 Volume Kendaraan Jalan Tol 2012 11,240,302

Lebih terperinci

Dr. Unggul Priyanto Kepala Badan Pengkajian dan Penerapan Teknologi

Dr. Unggul Priyanto Kepala Badan Pengkajian dan Penerapan Teknologi Dr. Unggul Priyanto Kepala Badan Pengkajian dan Penerapan Teknologi 1 Pendahuluan Energi Primer Kelistrikan 3 Energy Resources Proven Reserve Coal 21,131.84 million tons Oil Natural Gas (as of 2010) 3,70

Lebih terperinci

Perkembangan Pengelolaan Kewajiban Kontinjensi Triwulan II Tahun 2015

Perkembangan Pengelolaan Kewajiban Kontinjensi Triwulan II Tahun 2015 Perkembangan Pengelolaan Kewajiban Kontinjensi Triwulan II Tahun 2015 A. Jumlah Eksposur Kewajiban Kontijensi Penjaminan Pemerintah Jumlah eksposur yang timbul dari program penjaminan yang telah diterbitkan

Lebih terperinci

ESDM untuk Kesejahteraan Rakyat

ESDM untuk Kesejahteraan Rakyat KEMENTERIAN ENERGI DAN SUMBER DAYA MINERAL DIREKTORAT JENDERAL ENERGI BARU, TERBARUKAN DAN KONSERVASI ENERGI DIREKTORAT ANEKA ENERGI BARU DAN ENERGI TERBARUKAN (DEA) Jakarta, November 2013 1. CURRENT CONDITION

Lebih terperinci

HARGA LISTRIK PEMBANGKIT LISTRIK TENAGA PANAS BUMI (PLTP) SKALA KECIL. Hasan Maksum, Charles Lambok, Hari Soekarno, Benny FD

HARGA LISTRIK PEMBANGKIT LISTRIK TENAGA PANAS BUMI (PLTP) SKALA KECIL. Hasan Maksum, Charles Lambok, Hari Soekarno, Benny FD HARGA LISTRIK PEMBANGKIT LISTRIK TENAGA PANAS BUMI (PLTP) SKALA KECIL Hasan Maksum, Charles Lambok, Hari Soekarno, Benny FD Pusat Penelitian dan Pengembangan Teknologi Ketenagalistrikan, Energi Baru Terbarukan,

Lebih terperinci

BAB I PENDAHULUAN 1.1. Latar Belakang

BAB I PENDAHULUAN 1.1. Latar Belakang 1 BAB I PENDAHULUAN 1.1. Latar Belakang Listrik merupakan salah satu energi yang sangat dibutuhkan oleh manusia pada era modern ini. Tak terkecuali di Indonesia, negara ini sedang gencargencarnya melakukan

Lebih terperinci

PROFIL PLTS 1,6 MW JAKABARING

PROFIL PLTS 1,6 MW JAKABARING PD. PERTAMBANGAN DAN ENERGI Gedung Bank Sumselbabel Lt.2 Suite 602 Jl. Gubernur HA Bastari No. 07 Jakabaring Palembang, Indonesia Email : pdpde@pdpde.co.id GROUP & HOLDINGs Gedung Bank Sumselbabel Lt.6

Lebih terperinci

ANALISIS SISTEM PEMBANGKIT LISTRIK DI JAWA TERHADAP PENYEDIAAN BATUBARA YANG TIDAK TERBATAS ( )

ANALISIS SISTEM PEMBANGKIT LISTRIK DI JAWA TERHADAP PENYEDIAAN BATUBARA YANG TIDAK TERBATAS ( ) ANALISIS SISTEM PEMBANGKIT LISTRIK DI JAWA TERHADAP PENYEDIAAN BATUBARA YANG TIDAK TERBATAS (2000 2030) Adhi D. Permana dan Muchammad Muchlis ABSTRACT This paper discusses the impact of coal supply capacity

Lebih terperinci

PLTMG/PLTD Dual Fuel. By: Eko Sarwono 14 April 2016

PLTMG/PLTD Dual Fuel. By: Eko Sarwono 14 April 2016 PLTMG/PLTD Dual Fuel By: Eko Sarwono 14 April 2016 Tujuan Mengetahui perbedaan antara PLTMG dan PLTD dual Fuel Memahami prinsip kerja engine untuk memutar generator Mengetahui pembakuan Skala PLTMG/PLTD

Lebih terperinci

BAB V. SIMPULAN, KETERBATASAN, & SARAN

BAB V. SIMPULAN, KETERBATASAN, & SARAN BAB V. SIMPULAN, KETERBATASAN, & SARAN 5.1 Simpulan Dari hasil analisis yang dilakukan, maka dapat ditarik kesimpulan sebagai berikut: 1. Sumber-sumber energi primer di Indonesia yang terutama meliputi

Lebih terperinci

POKOK-POKOK PENGATURAN PEMANFAATAN BATUBARA UNTUK PEMBANGKIT LISTRIK DAN PEMBELIAN KELEBIHAN TENAGA LISTRIK (Permen ESDM No.

POKOK-POKOK PENGATURAN PEMANFAATAN BATUBARA UNTUK PEMBANGKIT LISTRIK DAN PEMBELIAN KELEBIHAN TENAGA LISTRIK (Permen ESDM No. Kementerian Energi dan Sumber Daya Mineral POKOK-POKOK PENGATURAN PEMANFAATAN BATUBARA UNTUK PEMBANGKIT LISTRIK DAN PEMBELIAN KELEBIHAN TENAGA LISTRIK (Permen ESDM No. 19 Tahun 2017) Direktur Pembinaan

Lebih terperinci

BAB I PENDAHULUAN. serta alasan penulis memilih obyek penelitian di PT. X. Setelah itu, sub bab

BAB I PENDAHULUAN. serta alasan penulis memilih obyek penelitian di PT. X. Setelah itu, sub bab BAB I PENDAHULUAN Bab pendahuluan dalam tesis ini menguraikan latar belakang dilakukannya penelitian dimana akan dibahas mengenai potensi sumber daya panas bumi di Indonesia, kegiatan pengembangan panas

Lebih terperinci

BAB V KESIMPULAN DAN SARAN. Bagian Selatan dengan PT. Muba Daya Pratama sehubungan dengan

BAB V KESIMPULAN DAN SARAN. Bagian Selatan dengan PT. Muba Daya Pratama sehubungan dengan BAB V KESIMPULAN DAN SARAN 5.1. Kesimpulan Perjanjian antara PT. PLN (Persero) Pembangkitan Sumatera Bagian Selatan dengan PT. Muba Daya Pratama sehubungan dengan Proyek Pembangkit Listrik Berbahan Bakar

Lebih terperinci

PERANAN MIGAS DALAM MENDUKUNG KETAHANAN ENERGI

PERANAN MIGAS DALAM MENDUKUNG KETAHANAN ENERGI PERANAN MIGAS DALAM MENDUKUNG KETAHANAN ENERGI Oleh : A. Edy Hermantoro Direktur Pembinaan Usaha Hulu Migas disampaikan pada : DISKUSI EVALUASI BLUE PRINT ENERGI NASIONAL PETROGAS DAYS 2010 Jakarta, 11

Lebih terperinci

SMI s Insight Triwulan II

SMI s Insight Triwulan II SMI s Insight 2016 - Triwulan II Untuk memenuhi pertumbuhan kebutuhan listrik sebagai pendorong pertumbuhan ekonomi nasional dan mencapai target rasio elektrifikasi, diperlukan tambahan kapasitas sekitar

Lebih terperinci

ADLN PERPUSTAKAAN UNIVERSITAS AIRLANGGA BAB I PENDAHULUAN. terus dilaksanakan. Pembangungan Pusat Listrik Tenaga Uap (PLTU), Pusat

ADLN PERPUSTAKAAN UNIVERSITAS AIRLANGGA BAB I PENDAHULUAN. terus dilaksanakan. Pembangungan Pusat Listrik Tenaga Uap (PLTU), Pusat 1 BAB I PENDAHULUAN 1.1. Latar Belakang Masalah Sejak bulan Juni 2010 pemerintah Indonesia telah mencanangkan program Indonesia bebas dari pemadaman bergilir. Sehingga kehadiran industri tenaga listrik

Lebih terperinci

4/28/2015 PERSEBARAN LOKASI SASARAN NAWACITA PERCEPATAN PEMBANGUNAN PEMBANGKIT LISTRIK KALIMANTAN SELATAN SULAWESI BARAT PAPUA BARAT KALIMANTAN TENGAH SUMATERA UTARA JAWA TENGAH SASARAN NAWACITA LOKASI

Lebih terperinci

KATA PENGANTAR Analisis Penggunaan Bahan Bakar dengan Fluktuasi Beban pada Mesin Gas Rolls Royce Kapasitas 8,5 MW di PLTMG Panaran-Batam

KATA PENGANTAR Analisis Penggunaan Bahan Bakar dengan Fluktuasi Beban pada Mesin Gas Rolls Royce Kapasitas 8,5 MW di PLTMG Panaran-Batam KATA PENGANTAR Puji dan syukur penulis ucapkan kepada Tuhan Yang Maha Esa atas rahmat dan karunia yang diberikan-nya kepada penulis sehingga dapat menyelesaikan Tugas Akhir ini, mulai dari awal penyusunan

Lebih terperinci

ANALISIS INDUSTRI GAS NASIONAL

ANALISIS INDUSTRI GAS NASIONAL ANALISIS INDUSTRI GAS NASIONAL Biro Riset BUMN Center LM FEUI Meningkatnya beban subsidi Bahan Bakar Minyak (BBM) belakangan ini membuat pemerintah berupaya menekan subsidi melalui penggunaan energi alternatif,

Lebih terperinci

Sambutan Presiden RI - Pembangunan 6 Mobile Power Plant di Sumatera, Bangka Belitung, 1 Juni 2016 Rabu, 01 Juni 2016

Sambutan Presiden RI - Pembangunan 6 Mobile Power Plant di Sumatera, Bangka Belitung, 1 Juni 2016 Rabu, 01 Juni 2016 Sambutan Presiden RI - Pembangunan 6 Mobile Power Plant di Sumatera, Bangka Belitung, 1 Juni 2016 Rabu, 01 Juni 2016 SAMBUTAN PRESIDEN REPUBLIK INDONESIA PEMBANGUNAN ENAM MOBILE POWER PLANT DI SUMATERA

Lebih terperinci

Gambar 3.1. Struktur Perusahaan

Gambar 3.1. Struktur Perusahaan BAB 3 GAMBARAN UMUM PERUSAHAAN 3.1. Sejarah Singkat PT. X Berdasarkan data yang diperoleh melalui Laporan Tahunan 2009, PT. X didirikan pada 9 Juni 1980 di bawah hukum Republik Indonesia dan memulai usahanya

Lebih terperinci

Rencana Pengembangan Energi Baru Terbarukan dan Biaya Pokok Penyediaan Tenaga Listrik Dialog Energi Tahun 2017

Rencana Pengembangan Energi Baru Terbarukan dan Biaya Pokok Penyediaan Tenaga Listrik Dialog Energi Tahun 2017 Rencana Pengembangan Energi Baru Terbarukan dan Biaya Pokok Penyediaan Tenaga Listrik Dialog Energi Tahun 2017 Jakarta, 2 Maret 2017 Pengembangan Energi Nasional Prioritas pengembangan Energi nasional

Lebih terperinci

Komisi Pengawas Persaingan Usaha Republik Indonesia PENDAPAT KOMISI PENGAWAS PERSAINGAN USAHA NOMOR 14/KPPU/PDPT/VI/2013

Komisi Pengawas Persaingan Usaha Republik Indonesia PENDAPAT KOMISI PENGAWAS PERSAINGAN USAHA NOMOR 14/KPPU/PDPT/VI/2013 Komisi Pengawas Persaingan Usaha Republik Indonesia PENDAPAT KOMISI PENGAWAS PERSAINGAN USAHA NOMOR 14/KPPU/PDPT/VI/2013 TENTANG PENILAIAN TERHADAP PENGAMBILALIHAN (AKUISISI) SAHAM PERUSAHAAN PT PEMBANGKITAN

Lebih terperinci

Disampaikan pada: Komunikasi Nasional Jogjakarta, 5 Desember 2007 Persero) Electricity For A Better Life

Disampaikan pada: Komunikasi Nasional Jogjakarta, 5 Desember 2007 Persero) Electricity For A Better Life Disampaikan pada: Seminar Nasional Energi dan Kelistrikan serta Teknologi Informasi Komunikasi Nasional Jogjakarta, 5 Desember 2007 Oleh : Eddie Widiono Msc. - Dirut PT PLN (Persero( Persero) 1 PT PLN

Lebih terperinci

BAB I PENDAHULUAN. Tidak dapat disanggah lagi jika di era sekarang ini segala aktivitas yang

BAB I PENDAHULUAN. Tidak dapat disanggah lagi jika di era sekarang ini segala aktivitas yang BAB I PENDAHULUAN 1.1. Latar Belakang Permasalahan Tidak dapat disanggah lagi jika di era sekarang ini segala aktivitas yang dilakukan masyarakat modern sangat tergantung kepada ketersediaan 1nergy. Hampir

Lebih terperinci

Methodology for TWG II Renewable Energy Action Plan

Methodology for TWG II Renewable Energy Action Plan Methodology for TWG II Renewable Energy Action Plan Outline of Final Report 1. Introduction 2. Current Situation of Renewable Energy Utilization Current Policy National Policy Regional Policy Current Implementation

Lebih terperinci

EKSPOSE DINAS PERTAMBANGAN & ENERGI PROVINSI SUMATERA UTARA

EKSPOSE DINAS PERTAMBANGAN & ENERGI PROVINSI SUMATERA UTARA EKSPOSE DINAS PERTAMBANGAN & ENERGI PROVINSI SUMATERA UTARA KONDISI KELISTRIKAN SUMATERA UTARA Berikut ini data pembangkit terpasang di Sumatera Utara yang memasok listrik ke sistem SUMBAGUT: No Lokasi

Lebih terperinci

Pre High Level Meeting FIT Energi Angin. Jakarta, 31 st January 2013 WHyPGen Project

Pre High Level Meeting FIT Energi Angin. Jakarta, 31 st January 2013 WHyPGen Project Pre High Level Meeting FIT Energi Angin Jakarta, 31 st January 2013 WHyPGen Project 1 The Project aims to promote the adoption of Wind Hybrid Power Generation (WHyPGen) Technology through the facilitation,

Lebih terperinci

Perkembangan Kelistrikan Indonesia dan Kebutuhan Sarjana Teknik Elektro

Perkembangan Kelistrikan Indonesia dan Kebutuhan Sarjana Teknik Elektro Perkembangan Kelistrikan Indonesia dan Kebutuhan Sarjana Teknik Elektro Dr. HERMAN DARNEL IBRAHIM Direktur Transmisi dan Distribusi PLN I MADE RO SAKYA Ahli Operasi Sistem - PLN Electricity For A Better

Lebih terperinci

MODUL 5A PEMBANGKIT LISTRIK TENAGA UAP (PLTU)

MODUL 5A PEMBANGKIT LISTRIK TENAGA UAP (PLTU) MODUL 5A PEMBANGKIT LISTRIK TENAGA UAP (PLTU) Definisi dan Pengantar Pembangkit Listrik Tenaga Uap (PLTU) adalah pembangkit listrik yang memanfaatkan energi panas dari uap (steam) untuk memutar turbin

Lebih terperinci

Keekonomian Pengembangan PLTP Skala Kecil

Keekonomian Pengembangan PLTP Skala Kecil EL-07 Keekonomian Pengembangan PLTP Skala Kecil Agus Sugiyono* 1 1 Bidang Perencanaan Energi, Badan Pengkajian dan Penerapan Teknologi, Jakarta, Indonesia *E-mail: agussugiyono@yahoo.com A B S T R A K

Lebih terperinci

HASIL PEMERIKSAAN BPK RI TERKAIT INFRASTRUKTUR KELISTRIKAN TAHUN 2009 S.D Prof. Dr. Rizal Djalil

HASIL PEMERIKSAAN BPK RI TERKAIT INFRASTRUKTUR KELISTRIKAN TAHUN 2009 S.D Prof. Dr. Rizal Djalil HASIL PEMERIKSAAN BPK RI TERKAIT INFRASTRUKTUR KELISTRIKAN TAHUN 2009 S.D. 2014 Prof. Dr. Rizal Djalil DEPOK, 30 MARET 2015 LANDASAN HUKUM PERENCANAAN BIDANG ENERGI DAN KETENAGALISTRIKAN UU 30/2007 (Energi)

Lebih terperinci

SPONSOR AGREEMENT PT. PLN (PERSERO) DENGAN KONSORSIUM PLT BAYU SIDRAP. Kementerian ESDM Republik Indonesia

SPONSOR AGREEMENT PT. PLN (PERSERO) DENGAN KONSORSIUM PLT BAYU SIDRAP. Kementerian ESDM Republik Indonesia PEMBANGKIT LISTRIK TENAGA BAYU (PLTB) PPA/PJBL : PT. UPC SIDRAP BAYU ENERGI DAN PT. PLN (PERSERO) Kapasitas 70MW Lokasi di Sidrap Sulawesi Selatan Investasi US$ 180 juta (±Rp. 2.43T), Tenaga kerja 325

Lebih terperinci

POKOK-POKOK PM ESDM 45/2017, PM ESDM 49/2017 DAN PM ESDM 50/2017

POKOK-POKOK PM ESDM 45/2017, PM ESDM 49/2017 DAN PM ESDM 50/2017 Direktorat Jenderal Ketenagalistrikan Kementerian Energi dan Sumber Daya Mineral POKOK-POKOK PM ESDM 45/2017, PM ESDM 49/2017 DAN PM ESDM 50/2017 1) Pemanfaatan Gas Bumi untuk Pembangkit Tenaga Listrik

Lebih terperinci

PEMANFAATAN LOW RANK COAL UNTUK SEKTOR KETENAGA LISTRIKAN

PEMANFAATAN LOW RANK COAL UNTUK SEKTOR KETENAGA LISTRIKAN PEMANFAATAN LOW RANK COAL UNTUK SEKTOR KETENAGA LISTRIKAN Di Prersentasikan pada : SEMINAR NASIONAL BATUBARA Hotel Grand Melia,, 22 23 Maret 2006 DJUANDA NUGRAHA I.W PH DIREKTUR PEMBANGKITAN DAN ENERGI

Lebih terperinci

ANALISA EFISIENSI PERFORMA HRSG ( Heat Recovery Steam Generation ) PADA PLTGU. Bambang Setyoko * ) Abstracts

ANALISA EFISIENSI PERFORMA HRSG ( Heat Recovery Steam Generation ) PADA PLTGU. Bambang Setyoko * ) Abstracts ANALISA EFISIENSI PERFORMA HRSG ( Heat Recovery Steam Generation ) PADA PLTGU Bambang Setyoko * ) Abstracts Heat Recovery Steam Generator ( HRSG ) is a construction in combine cycle with gas turbine and

Lebih terperinci

BAB III SISTEM PLTGU UBP TANJUNG PRIOK

BAB III SISTEM PLTGU UBP TANJUNG PRIOK BAB III SISTEM PLTGU UBP TANJUNG PRIOK 3.1 Konfigurasi PLTGU UBP Tanjung Priok Secara sederhana BLOK PLTGU UBP Tanjung Priok dapat digambarkan sebagai berikut: deaerator LP Header Low pressure HP header

Lebih terperinci

BAB I PENDAHULUAN 1.1 Latar Belakang Masalah

BAB I PENDAHULUAN 1.1 Latar Belakang Masalah BAB I PENDAHULUAN 1.1 Latar Belakang Masalah Energi listrik merupakan salah satu kebutuhan pokok yang cukup penting bagi manusia dalam kehidupan. Saat ini, hampir setiap kegiatan manusia membutuhkan energi

Lebih terperinci

... Hubungi Kami : Studi POWER PLANT MW di Indonesia, & Pelaku Utamanya. Mohon Kirimkan. eksemplar. Posisi : Nama (Mr/Mrs/Ms)

... Hubungi Kami : Studi POWER PLANT MW di Indonesia, & Pelaku Utamanya. Mohon Kirimkan. eksemplar. Posisi : Nama (Mr/Mrs/Ms) Hubungi Kami 021 31930 108 021 31930 109 021 31930 070 marketing@cdmione.com I ndonesia dibawah kepemimpinan Presiden Joko Widodo menyadari akan ketertinggalan di sektor ketenaga listrikan. Hal inilah

Lebih terperinci

Vol.13 No.2. Agustus 2012 Jurnal Momentum ISSN : X

Vol.13 No.2. Agustus 2012 Jurnal Momentum ISSN : X Analisis Penjadwalan Unit-Unit Pembangkit Listrik Dengan Menggunakan Metode Unit Decommitment (PT.PLN Wilayah Riau) Oleh: Zulfatri Aini Jurusan Teknik Elektro, Fakultas Sains dan Teknologi Universitas

Lebih terperinci

KEMENTERIAN ENERGI DAN SUMBER DAYA MINERAL DIREKTORAT JENDERAL ENERGI BARU, TERBARUKAN DAN KONSERVASI ENERGI. Disampaikan oleh

KEMENTERIAN ENERGI DAN SUMBER DAYA MINERAL DIREKTORAT JENDERAL ENERGI BARU, TERBARUKAN DAN KONSERVASI ENERGI. Disampaikan oleh KEMENTERIAN ENERGI DAN SUMBER DAYA MINERAL DIREKTORAT JENDERAL ENERGI BARU, TERBARUKAN DAN KONSERVASI ENERGI REGULASI DAN KEBIJAKAN PENGEMBANGAN ENERGI ANGIN Disampaikan oleh Abdi Dharma Saragih Kasubdit

Lebih terperinci

BAB I PENDAHULUAN Latar Belakang Penelitian Arief Hario Prambudi, 2014

BAB I PENDAHULUAN Latar Belakang Penelitian Arief Hario Prambudi, 2014 1 BAB I PENDAHULUAN A. Latar Belakang Penelitian Pembangkit Listrik Tenaga Uap (PLTU) adalah suatu pembangkit listrik dimana energi listrik dihasilkan oleh generator yang diputar oleh turbin uap yang memanfaatkan

Lebih terperinci

QUESTION & ANSWER. MCA-Indonesia Community Renewable Energy Grant (Window 3A)

QUESTION & ANSWER. MCA-Indonesia Community Renewable Energy Grant (Window 3A) QUESTION & ANSWER MCA-Indonesia Community Renewable Energy Grant (Window 3A) CfP Reference : CfP/GP-W3A/001/2014 Question No. : 1 Received Date : 5 Dec 2014 Release Date : 17 Dec 2014 No Reference Instructions

Lebih terperinci

PERATURAN PRESIDEN REPUBLIK INDONESIA NOMOR 59 TAHUN 2009 TENTANG

PERATURAN PRESIDEN REPUBLIK INDONESIA NOMOR 59 TAHUN 2009 TENTANG PERATURAN PRESIDEN NOMOR 59 TAHUN 2009 TENTANG PERUBAHAN ATAS PERATURAN PRESIDEN NOMOR 71 TAHUN 2006 TENTANG PENUGASAN KEPADA PT PERUSAHAAN LISTRIK NEGARA (PERSERO) UNTUK MELAKUKAN PERCEPATAN PEMBANGUNAN

Lebih terperinci

STUDI PERENCANAAN SISTEM KELISTRIKAN SUMATERA BAGIAN UTARA DENGAN OPSI NUKLIR

STUDI PERENCANAAN SISTEM KELISTRIKAN SUMATERA BAGIAN UTARA DENGAN OPSI NUKLIR STUDI PERENCANAAN SISTEM KELISTRIKAN SUMATERA BAGIAN UTARA DENGAN OPSI NUKLIR Rizki Firmansyah Setya Budi, Masdin (PPEN) BATAN Jl. Kuningan Barat, Mampang Prapatan, Jakarta12710 Telp./Fax: (021) 5204243,

Lebih terperinci

ANALISA SISTEM SUPLAI ENERGI LISTRIK DITINJAU DARI KEANDALAN SISTEM GENERATOR DI PERTAMINA PRABUMULIH

ANALISA SISTEM SUPLAI ENERGI LISTRIK DITINJAU DARI KEANDALAN SISTEM GENERATOR DI PERTAMINA PRABUMULIH ANALISA SISTEM SUPLAI ENERGI LISTRIK DITINJAU DARI KEANDALAN SISTEM GENERATOR DI PERTAMINA PRABUMULIH Antonius Hamdadi Rio Oktafian Aryansyah Universitas Sriwijaya Abstract In this thesis aims to analyze

Lebih terperinci

Perkembangan Pengelolaan Kewajiban Kontinjensi Triwulan I 2014

Perkembangan Pengelolaan Kewajiban Kontinjensi Triwulan I 2014 Perkembangan Pengelolaan Kewajiban Kontinjensi Triwulan I 2014 A. Jumlah Eksposur Yang Dimiliki Jumlah eksposur yang timbul dari keempat program penjaminan yang telah diterbitkan Pemerintah adalah sebagai

Lebih terperinci

SISTEM KELISTRIKAN LUAR JAMALI TAHUN 2003 S.D. TAHUN 2020

SISTEM KELISTRIKAN LUAR JAMALI TAHUN 2003 S.D. TAHUN 2020 SISTEM KELISTRIKAN LUAR JAMALI TAHUN 23 S.D. TAHUN 22 Agus Nurrohim dan Erwin Siregar ABSTRACT In national electricity plan, there are Jawa-Madura-Bali (Jamali) and Non Jamali systems. Those two systems

Lebih terperinci

BAB 1 PENDAHULUAN Latar Belakang

BAB 1 PENDAHULUAN Latar Belakang BAB 1 PENDAHULUAN 1.1. Latar Belakang Kondisi kelistrikan nasional berdasarkan catatan yang ada di Kementerian Energi dan Sumber Daya Mineral hingga akhir 2014 menunjukkan total kapasitas terpasang pembangkit

Lebih terperinci

BAB 4 HASIL DAN PEMBAHASAN PENELITIAN

BAB 4 HASIL DAN PEMBAHASAN PENELITIAN BAB 4 HASIL DAN PEMBAHASAN PENELITIAN 4.1 Profil Perusahaan Pada 1992 Pemerintah Indonesia mengeluarkan deregulasi sector ketenagalistrikan. Proses ini berawal dengan diterbitkannya Keputusan Presiden

Lebih terperinci

BAB I PENDAHULUAN. Dengan semakin menipisnya cadangan energi yang ada saat ini dan semakin

BAB I PENDAHULUAN. Dengan semakin menipisnya cadangan energi yang ada saat ini dan semakin BAB I PENDAHULUAN A. Latar Belakang Masalah Dengan semakin menipisnya cadangan energi yang ada saat ini dan semakin meningkatnya kebutuhan energi termasuk energi panas, pemikiran mengenai sumber energi

Lebih terperinci

Paparan Publik PT ABM Investama Tbk

Paparan Publik PT ABM Investama Tbk Paparan Publik 2015 PT ABM Investama Tbk Disclaimer Presentasi ini telah disiapkan oleh PT ABM Investama Tbk ( "ABMM" atau "Perseroan") semata-mata untuk informasi umum. Presentasi ini adalah untuk tujuan

Lebih terperinci

Proses Pengadaan dan Standar Kontrak Pembangkit Tenaga Listrik Yang Memanfaatkan Sumber Energi Terbarukan

Proses Pengadaan dan Standar Kontrak Pembangkit Tenaga Listrik Yang Memanfaatkan Sumber Energi Terbarukan Proses Pengadaan dan Standar Kontrak Pembangkit Tenaga Listrik Yang Memanfaatkan Sumber Energi Terbarukan Dipresentasikan oleh : Tohari Hadiat KDIV EBT PT. PLN (Persero) Jakarta, 10 Agustus 2017 Prosedur

Lebih terperinci

GEOTHERMAL SEBAGAI ENERGI ALTERNATIF

GEOTHERMAL SEBAGAI ENERGI ALTERNATIF GEOTHERMAL SEBAGAI ENERGI ALTERNATIF Makalah ini diajukan untuk memenuhi tugas MID AMISCA 2008 Disusun oleh: Kelompok 1 Kelompok 2 Fazri Azhar (10507001) Dinda Husna (10507057) Mila Vanesa (10507013) Sukmawati

Lebih terperinci

BAB II DESKRIPSI PERUSAHAAN

BAB II DESKRIPSI PERUSAHAAN BAB II DESKRIPSI PERUSAHAAN 2.1. Sejarah Perusahaan Chevron didirikan pada tahun 1879 di Pico Canyon, California. Saat ini, Chevron Corporation yang berkantor pusat di San Ramon, California, Amerika Serikat

Lebih terperinci

STUDI PEMANFAATAN KOTORAN SAPI UNTUK GENSET LISTRIK BIOGAS, PENERANGAN DAN MEMASAK MENUJU DESA NONGKOJAJAR (KECAMATAN TUTUR) MANDIRI ENERGI.

STUDI PEMANFAATAN KOTORAN SAPI UNTUK GENSET LISTRIK BIOGAS, PENERANGAN DAN MEMASAK MENUJU DESA NONGKOJAJAR (KECAMATAN TUTUR) MANDIRI ENERGI. STUDI PEMANFAATAN KOTORAN SAPI UNTUK GENSET LISTRIK BIOGAS, PENERANGAN DAN MEMASAK MENUJU DESA NONGKOJAJAR (KECAMATAN TUTUR) MANDIRI ENERGI. OLEH : Dhika Fitradiansyah Riliandi 2205 100 003 Dosen Pembimbing

Lebih terperinci

PERATURAN PRESIDEN REPUBLIK INDONESIA NOMOR 71 TAHUN 2006 TENTANG

PERATURAN PRESIDEN REPUBLIK INDONESIA NOMOR 71 TAHUN 2006 TENTANG PERATURAN PRESIDEN REPUBLIK INDONESIA NOMOR 71 TAHUN 2006 TENTANG PENUGASAN KEPADA PT. PERUSAHAAN LISTRIK NEGARA (PERSERO) UNTUK MELAKUKAN PERCEPATAN PEMBANGUNAN PEMBANGKIT TENAGA LISTRIK YANG MENGGUNAKAN

Lebih terperinci

STUDY DAN ANALISA SISTEM TENAGA LISTRIK DI LEX POWERHOUSETERMINAL SANTAN CHEVRON INDONESIA COMPANY

STUDY DAN ANALISA SISTEM TENAGA LISTRIK DI LEX POWERHOUSETERMINAL SANTAN CHEVRON INDONESIA COMPANY STUDY DAN ANALISA SISTEM TENAGA LISTRIK DI LEX POWERHOUSETERMINAL SANTAN CHEVRON INDONESIA COMPANY BAB. I PENDAHULUAN 1.1 Latar Belakang Terminal Santan merupakan salah satu fasilitas produksi minyak bumi

Lebih terperinci

BAB 4 IMPLEMENTASI SISTEM KOGENERASI

BAB 4 IMPLEMENTASI SISTEM KOGENERASI 24 BAB 4 IMPLEMENTASI SISTEM KOGENERASI 4.1. Metodologi Dalam penelitian ini, mencakup pemilihan sistem kogenerasi dan evaluasi nilai ekonomi. Pemilihan sistem kogenerasi yang diimplementasikan mempertimbangkan

Lebih terperinci

PERBANDINGAN BIAYA PEMBANGKITAN LISTRIK NUKLIR DAN FOSIL DENGAN MEMPERTIMBANGKAN ASPEK LINGKUNGAN. Mochamad Nasrullah, Suparman

PERBANDINGAN BIAYA PEMBANGKITAN LISTRIK NUKLIR DAN FOSIL DENGAN MEMPERTIMBANGKAN ASPEK LINGKUNGAN. Mochamad Nasrullah, Suparman PERBANDINGAN BIAYA PEMBANGKITAN LISTRIK NUKLIR DAN FOSIL DENGAN MEMPERTIMBANGKAN ASPEK LINGKUNGAN ABSTRAK Mochamad Nasrullah, Suparman Pusat Pengembangan Energi Nuklir - BATAN Jl. Kuningan Barat, Mampang

Lebih terperinci

SENSITIVITAS ANALISIS POTENSI PRODUKSI PEMBANGKIT LISTRIK RENEWABLE UNTUK PENYEDIAAN LISTRIK INDONESIA

SENSITIVITAS ANALISIS POTENSI PRODUKSI PEMBANGKIT LISTRIK RENEWABLE UNTUK PENYEDIAAN LISTRIK INDONESIA SENSITIVITAS ANALISIS POTENSI PRODUKSI PEMBANGKIT LISTRIK RENEWABLE UNTUK PENYEDIAAN LISTRIK INDONESIA La Ode Muhammad Abdul Wahid ABSTRACT Electricity demand has been estimated to grow in the growth rate

Lebih terperinci

SOLAR PV DIESEL HYBRID POWER FOR MICRO/MINI GRIDS IN INDONESIA

SOLAR PV DIESEL HYBRID POWER FOR MICRO/MINI GRIDS IN INDONESIA SOLAR PV DIESEL HYBRID POWER FOR MICRO/MINI GRIDS IN INDONESIA JAKARTA, 15 SEPTEMBER 2017 TOHARI HADIAT TABLE OF CONTENTS ELECTRIC POWER SYSTEM DEVELOPMENT PLAN 2017-2026 ENERGY MIX in 2017-2026 RENEWABLE

Lebih terperinci

BAB 1 PENDAHULUAN Latar Belakang Masalah

BAB 1 PENDAHULUAN Latar Belakang Masalah 1 BAB 1 PENDAHULUAN 1.1. Latar Belakang Masalah Indonesia yang terletak di lingkar Pasifik, yang juga dikenal sebagai Cincin Api, dikaruniai sejumlah besar sumber daya energi panas bumi. Perkiraan potensinya

Lebih terperinci

PENGAMANAN FISKAL MELALUI POLA PEMBAGIAN RISIKO ANTARA PEMERINTAH DAN SWASTA

PENGAMANAN FISKAL MELALUI POLA PEMBAGIAN RISIKO ANTARA PEMERINTAH DAN SWASTA PENGAMANAN FISKAL MELALUI POLA PEMBAGIAN RISIKO ANTARA PEMERINTAH DAN SWASTA Oleh: Prof. Bambang P.S. Brodjonegoro, Ph.D Kepala Badan Kebijakan Fiskal, Kementerian Keuangan Pendahuluan Investasi di bidang

Lebih terperinci

PT DIAN SWASTATIKA SENTOSA TBK

PT DIAN SWASTATIKA SENTOSA TBK PT DIAN SWASTATIKA SENTOSA TBK PAPARAN PUBLIK TAHUNAN Jumat, 28 Desember 2012 Plaza BII, Tower II Lantai 39 0 AGENDA Tinjauan Umum Perusahaan Tinjauan Keuangan 3Q12 Kejadian Penting Prospek Usaha 1 AGENDA

Lebih terperinci

Konservasi Energi: Melalui Aplikasi Teknologi Kogenerasi

Konservasi Energi: Melalui Aplikasi Teknologi Kogenerasi Konservasi Energi: Melalui Aplikasi Teknologi Kogenerasi B2TE BPPT, Energy Partner Gathering Hotel Borobudur Jakarta, 4 Desember 2013 www.mctap-bppt.com INTENSITAS ENERGI SEKTOR INDUSTRI DI INDONESIA (dan

Lebih terperinci

OPTIMASI SUPLAI ENERGI DALAM MEMENUHI KEBUTUHAN TENAGA LISTRIK JANGKA PANJANG DI INDONESIA

OPTIMASI SUPLAI ENERGI DALAM MEMENUHI KEBUTUHAN TENAGA LISTRIK JANGKA PANJANG DI INDONESIA OPTIMASI SUPLAI ENERGI DALAM MEMENUHI KEBUTUHAN TENAGA LISTRIK JANGKA PANJANG DI INDONESIA M. Sidik Boedoyo dan Agus Sugiyono Abstract Energy supply optimation is aimed to meet electricity demand for domestic

Lebih terperinci

Memperkuat Landasan Menetapkan Haluan

Memperkuat Landasan Menetapkan Haluan Paparan Publik Tahunan PT Samindo Resurces Tbk ( Perseroan ) Memperkuat Landasan Menetapkan Haluan 4 Mei 2018, Gran Melia Jakarta Daftar Isi 01 Profil Perseroan Informasi Umum Layanan & Kompetensi Struktur

Lebih terperinci

Anatomi Sumber Daya Batubara Serta Asumsi Pemanfaatan Untuk PLTU di Indonesia

Anatomi Sumber Daya Batubara Serta Asumsi Pemanfaatan Untuk PLTU di Indonesia Anatomi Sumber Daya Batubara Serta Asumsi Pemanfaatan Untuk PLTU di Indonesia DR. Ir. Hadiyanto M.Sc. Pusat Sumber Daya Geologi Badan Geologi Departemen Energi dan Sumber Daya Mineral COAL PRODUCTION FROM

Lebih terperinci

PELUANG PANAS BUMI SEBAGAI SUMBER ENERGI ALTERNATIF DALAM PENYEDIAAN TENAGA LISTRIK NASIONAL

PELUANG PANAS BUMI SEBAGAI SUMBER ENERGI ALTERNATIF DALAM PENYEDIAAN TENAGA LISTRIK NASIONAL PELUANG PANAS BUMI SEBAGAI SUMBER ENERGI ALTERNATIF DALAM PENYEDIAAN TENAGA LISTRIK NASIONAL OLEH : SUGIHARTO HARSOPRAYITNO, MSc DIREKTUR PEMBINAAN PENGUSAHAAN PANAS BUMI DAN PENGELOLAAN AIR TANAH DIREKTORAT

Lebih terperinci

PLN STATISTICS Catalogue in Publication. Catalogue No. : 31:621.3 ISSN : Publication No. :

PLN STATISTICS Catalogue in Publication. Catalogue No. : 31:621.3 ISSN : Publication No. : i Catalogue in Publication PLN STATISTICS 2013 Catalogue No. : 31:621.3 ISSN : 0852-8179 Publication No. : 02601.140722 Book Size : 20 cm x 27 cm Number of Pages : 100 Editor : Corporate Secretary PT PLN

Lebih terperinci

BAB 1 PENDAHULUAN. Besarnya konsumsi listrik di Indonesia semakin lama semakin meningkat.

BAB 1 PENDAHULUAN. Besarnya konsumsi listrik di Indonesia semakin lama semakin meningkat. BAB 1 PENDAHULUAN 1.1. Latar Belakang Besarnya konsumsi listrik di Indonesia semakin lama semakin meningkat. Kenaikan konsumsi tersebut terjadi karena salah satu faktornya yaitu semakin meningkatnya jumlah

Lebih terperinci

POKOK-POKOK PM ESDM 45/2017, PM ESDM 49/2017 DAN PM ESDM 50/2017

POKOK-POKOK PM ESDM 45/2017, PM ESDM 49/2017 DAN PM ESDM 50/2017 Direktorat Jenderal Ketenagalistrikan Kementerian Energi dan Sumber Daya Mineral POKOK-POKOK PM ESDM 45/2017, PM ESDM 49/2017 DAN PM ESDM 50/2017 1) Pemanfaatan Gas Bumi untuk Pembangkit Tenaga Listrik

Lebih terperinci

Ketersediaan Pasokan Listrik Dorong Pertumbuhan Ekonomi Minggu, 19 Maret 2017

Ketersediaan Pasokan Listrik Dorong Pertumbuhan Ekonomi Minggu, 19 Maret 2017 Ketersediaan Pasokan Listrik Dorong Pertumbuhan Ekonomi Minggu, 19 Maret 2017 Pemerintah terus menunjukkan keseriusannya memenuhi kebutuhan pasokan listrik di Tanah Air. Terkini, Presiden Joko Widodo pada

Lebih terperinci

KONVERSI ENERGI DI PT KERTAS LECES

KONVERSI ENERGI DI PT KERTAS LECES KONVERSI ENERGI DI PT KERTAS LECES 1. Umum Subagyo Rencana dan Evaluasi Produksi, PT. Kertas Leces Leces-Probolinggo, Jawa Timur e-mail: ptkl@idola.net.id Abstrak Biaya energi di PT. Kertas Leces (PTKL)

Lebih terperinci

... Hubungi Kami : Studi Potensi Bisnis dan Pelaku Utama Industri POWER PLANT di Indonesia, Mohon Kirimkan. eksemplar.

... Hubungi Kami : Studi Potensi Bisnis dan Pelaku Utama Industri POWER PLANT di Indonesia, Mohon Kirimkan. eksemplar. Hubungi Kami 021 31930 108 021 31930 109 021 31930 070 marketing@cdmione.com K ondisi kelistrikan Indonesia saat ini sangat memprihatinkan karena kapasitas yang dimiliki masih kalah jauh dengan negara

Lebih terperinci

ANALISIS PENGARUH PEMAKAIAN BAHAN BAKAR TERHADAP EFISIENSI HRSG KA13E2 DI MUARA TAWAR COMBINE CYCLE POWER PLANT

ANALISIS PENGARUH PEMAKAIAN BAHAN BAKAR TERHADAP EFISIENSI HRSG KA13E2 DI MUARA TAWAR COMBINE CYCLE POWER PLANT ANALISIS PENGARUH PEMAKAIAN BAHAN BAKAR TERHADAP EFISIENSI HRSG KA13E2 DI MUARA TAWAR COMBINE CYCLE POWER PLANT Anwar Ilmar Ramadhan 1,*, Ery Diniardi 1, Hasan Basri 2, Dhian Trisnadi Setyawan 1 1 Jurusan

Lebih terperinci

Perkembangan Pengelolaan Kewajiban Kontinjensi Triwulan I Tahun 2015

Perkembangan Pengelolaan Kewajiban Kontinjensi Triwulan I Tahun 2015 Perkembangan Pengelolaan Kewajiban Kontinjensi Triwulan I Tahun 2015 A. Jumlah Eksposur Kewajiban Kontijensi Penjaminan Pemerintah Jumlah eksposur yang timbul dari program penjaminan yang telah diterbitkan

Lebih terperinci

KINERJA SEKTOR HULU MIGAS YTD SEPTEMBER 2017 (Q3) Jakarta, 27 Oktober 2017

KINERJA SEKTOR HULU MIGAS YTD SEPTEMBER 2017 (Q3) Jakarta, 27 Oktober 2017 KINERJA SEKTOR HULU MIGAS YTD SEPTEMBER 2017 (Q3) Jakarta, 27 Oktober 2017 1 I. KINERJA UTAMA HULU MIGAS (Q3 2017) 2 2017 SKK Migas All rights reserved Wilayah Kerja Migas Konvensional & NonKonvensional

Lebih terperinci

DRAFT GENERAL PLAN OF ELECTRICITY (RUKN)

DRAFT GENERAL PLAN OF ELECTRICITY (RUKN) MINISTRY OF ENERGY AND MINERAL RESOURCES DIRECTORAT GENERAL OF ELECTRICITY DRAFT GENERAL PLAN OF ELECTRICITY (RUKN) 2012-2031 PRESENTED BY: Hasril Nuzahar Director of Electricity Program Supervision on

Lebih terperinci

KEBIJAKAN PENGELOLAAN LISTRIK DARI ENERGI TERBARUKAN

KEBIJAKAN PENGELOLAAN LISTRIK DARI ENERGI TERBARUKAN KEMENTERIAN ENERGI DAN SUMBER DAYA MINERAL DIREKTORAT JENDERALKETENAGALISTRIKAN KEBIJAKAN PENGELOLAAN LISTRIK DARI ENERGI TERBARUKAN Direktur Jenderal Ketenagalistrikan Dialog Energi Tahun 2017 DEWAN ENERGI

Lebih terperinci

ANALISIS EXERGOECONOMIC PADA RUANG BAKAR PEMBANGKIT LISTRIK TENAGA GAS UAP (PLTGU) TELUK LEMBU 30 MW

ANALISIS EXERGOECONOMIC PADA RUANG BAKAR PEMBANGKIT LISTRIK TENAGA GAS UAP (PLTGU) TELUK LEMBU 30 MW ANALISIS EXERGOECONOMIC PADA RUANG BAKAR PEMBANGKIT LISTRIK TENAGA GAS UAP (PLTGU) TELUK LEMBU 30 MW Putri Wahyuni 1 1, Awaludin Martin 1 2 Laboratorium Konversi Energi, Jurusan Teknik Mesin, Fakultas

Lebih terperinci

STRATEGI KEN DALAM MEWUJUDKAN KETAHANAN ENERGI NASIONAL

STRATEGI KEN DALAM MEWUJUDKAN KETAHANAN ENERGI NASIONAL STRATEGI KEN DALAM MEWUJUDKAN KETAHANAN ENERGI NASIONAL SEMINAR OPTIMALISASI PENGEMBANGAN ENERGI BARU DAN TERBARUKAN MENUJU KETAHANAN ENERGI YANG BERKELANJUTAN Oleh: DR. Sonny Keraf BANDUNG, MEI 2016 KETAHANAN

Lebih terperinci

DENGAN RAHMAT TUHAN YANG MAHA ESA PRESIDEN REPUBLIK INDONESIA,

DENGAN RAHMAT TUHAN YANG MAHA ESA PRESIDEN REPUBLIK INDONESIA, PERATURAN PRESIDEN REPUBLIK INDONESIA NOMOR 71 TAHUN 2006 TENTANG PENUGASAN KEPADA PT PERUSAHAAN LISTRIK NEGARA (PERSERO) UNTUK MELAKUKAN PERCEPATAN PEMBANGUNAN PEMBANGKIT TENAGA LISTRIK YANG MENGGUNAKAN

Lebih terperinci

Perkembangan Pengelolaan Kewajiban Kontinjensi Triwulan IV Tahun 2014

Perkembangan Pengelolaan Kewajiban Kontinjensi Triwulan IV Tahun 2014 Perkembangan Pengelolaan Kewajiban Kontinjensi Triwulan IV Tahun 2014 A. Jumlah Eksposur Kewajiban Kontijensi Penjaminan Pemerintah Jumlah eksposur yang timbul dari program penjaminan yang telah diterbitkan

Lebih terperinci