R E K A P I T U L A S I BILL OF QUANTITY (BOQ) PEKERJAAN KECAMATAN BALAESANG TAHUN ANGGARAN : 2012 NO. URAIAN PEKERJAAN JUMLAH HARGA ( Rp) I. PEKERJAAN PERSIAPAN 750,000.00 II. III. IV. PEKERJAAN JEMBATAN PENGHUBUNG LEBAR 4 M' PEKERJAAN TAMBATAN PERAHU LEBAR 6 M' PEKERJAAN JALAN AKSES SEPANJANG 10 M' 66,926,566.00 189,692,599.08 15,058,732.69 V. PEKERJAAN FINISHING BIAYA KONSTRUKSI PAJAK PERTAMBAHAN NILAI 10 % JUMLAH BIAYA DIBULATKAN 300,000.00 272,727,897.77 27,272,789.78 300,000,687.55 300,000,000.00 Donggala, 2012 Penawar, PT/CV....... Jabatan
BILL OF QUANTITY (BOQ) PEKERJAAN KECAMATAN BALAESANG TAHUN ANGGARAN : 2012 NO. URAIAN PEKERJAAN VOLUME SA- TUAN HARGA SATUAN (Rp) JUMLAH HARGA (Rp) I. 1 PEKERJAAN PERSIAPAN Pengukuran / Pemasangan Bouwplank 1.000 Ls 500,000.00 500,000.00 2 Papan Nama Proyek 1.000 Ls 250,000.00 250,000.00 750,000.00 I. PEKERJAAN JEMBATAN PENGHUBUNG LEBAR 4 M' 1 Pek. Tiang kayu 15 x 15 cm; Lrata-rata = 4 m 18.000 Bh 348,560.00 6,274,080.00 2 Pek. Tiang kayu 15 x 15 cm; Lrata-rata = 7.5 m 18.000 Bh 614,560.00 11,062,080.00 3 Pek. Lantai Papan, Tebal 5 cm 96.000 M² 171,525.00 16,466,400.00 4 Pek. Gelagar Induk, Gelagar Lantai dan Scor Angin 6.980 M³ 4,444,700.00 31,024,006.00 5 Pemasangan Baut dan mur Ø 12 mm 300.000 Set 7,000.00 2,100,000.00 66,926,566.00 II. PEKERJAAN TAMBATAN PERAHU LEBAR 6 M' 1 Pek. Tiang kayu 20 x 20 cm 66.000 Bh 1,253,516.00 82,732,056.00 2 Pek. Lantai Papan, Tebal 5 cm 120.000 M² 171,525.00 20,583,000.00 3 Pek. Gelagar Induk, Gelagar Lantai dan Scor Angin 18.325 M³ 4,444,700.00 81,449,543.08 4 Pemas. Baut dan mur Ø 12 mm 704.000 Set 7,000.00 4,928,000.00 189,692,599.08 III. PEKERJAAN JALAN AKSES SEPANJANG 10 M' 1 Pek. Galian tanah Talud 13.650 M³ 18,000.00 245,700.00 2 Pek. Urugan pasir bawah talud 1.050 M³ 108,500.00 113,925.00 3 Pek. Urugan tasirtu 34.150 M³ 119,250.00 4,072,444.74 4 Pas. Baru Kosong 4.200 M³ 244,830.00 1,028,286.00 5 Pek. Pas. Batu Kali 13.410 M³ 537,020.00 7,201,438.20 6 Pek. Cor jalan beton 1pc : 3Ps : 5 Kr 3.330 M³ 624,055.12 2,078,103.55 7 Pek. Siar 11.500 M³ 27,724.80 318,835.20 15,058,732.69 IV. PEKERJAAN FINISHING 1 Pembersihan Akhir 1.000 Ls 300,000.00 300,000.00 300,000.00
DAFTAR ANALISA HARGA SATUAN PEKERJAAN PEKERJAAN KECAMATAN BALAESANG TAHUN ANGGARAN : 2012 10 M' Pekerjaan Pengukuran dan Pemasangan Bowplank 0.001 M³ Kayu 5/7 kelas III @ Rp. 1,300,000.00 = Rp. 1,560.00 0.020 Kg Paku biasa 2-5 " @ Rp. 18,000.00 = Rp. 360.00 0.007 M³ Papan ukuran 2/30 kelas III @ Rp. 1,300,000.00 = Rp. 9,100.00 0.100 Oh Pekerja @ Rp. 40,000.00 = Rp. 4,000.00 0.100 Oh Tukang @ Rp. 65,000.00 = Rp. 6,500.00 0.010 Oh Kepala Tukang @ Rp. 70,000.00 = Rp. 700.00 0.005 Oh Mandor @ Rp. 50,000.00 = Rp. 250.00 = Rp. 22,470.00 Untuk 1 m' = Rp. 2,247.00 1 M³ Galian tanah biasa sedalam 1 m 0.400 Oh Pembantu tukang @ Rp. 40,000.00 = Rp. 16,000.00 Oh Tukang gali @ Rp. 65,000.00 = Rp. - Oh Kepala tukang @ Rp. 70,000.00 = Rp. - 0.040 Oh Mandor @ Rp. 50,000.00 = Rp. 2,000.00 Rp. 18,000.00 1 M³ Urugan kembali tanah galian 0.192 Oh Pembantu tukang @ Rp. 40,000.00 = Rp. 7,680.00 Oh Tukang gali @ Rp. 65,000.00 = Rp. - Oh Kepala tukang @ Rp. 70,000.00 = Rp. - 0.019 Oh Mandor @ Rp. 50,000.00 = Rp. 950.00 Rp. 8,630.00 1 M³ Urugan Pasir 1.200 M 3 Pasir urug @ Rp. 80,000.00 = Rp. 96,000.00 0.300 Oh Pembantu tukang @ Rp. 40,000.00 = Rp. 12,000.00 Oh Tukang gali @ Rp. 65,000.00 = Rp. - Oh Kepala tukang @ Rp. 70,000.00 = Rp. - 0.010 Oh Mandor @ Rp. 50,000.00 = Rp. 500.00 Rp. 108,500.00 1 M³ Urugan Sirtu 1.200 M 3 Sirtu @ Rp. 90,000.00 = Rp. 108,000.00 0.250 Oh Pembantu tukang @ Rp. 40,000.00 = Rp. 10,000.00 Oh Tukang @ Rp. 65,000.00 = Rp. - Oh Kepala tukang @ Rp. 70,000.00 = Rp. - 0.025 Oh Mandor @ Rp. 50,000.00 = Rp. 1,250.00 Rp. 119,250.00 1 M³ Pasang pondasi batu kali 1 Pc : 4 Psr 1.100 M 3 Batu belah 15/20 cm @ Rp. 133,000.00 = Rp. 146,300.00 0.520 M 3 Pasir pasang @ Rp. 110,000.00 = Rp. 57,200.00 163.000 Kg Semen portland @ Rp. 1,390.00 = Rp. 226,570.00 1.500 Org Pekerja @ Rp. 40,000.00 = Rp. 60,000.00 0.600 Org Tukang batu @ Rp. 65,000.00 = Rp. 39,000.00 0.060 Org Kepala tukang @ Rp. 70,000.00 = Rp. 4,200.00 0.075 Org Mandor @ Rp. 50,000.00 = Rp. 3,750.00 Rp. 537,020.00 BOQ TambatanAnalisa
1 M³ Pasang pondasi batu kosong 1.200 M 3 Batu belah 15/20 cm @ Rp. 133,000.00 = Rp. 159,600.00 0.300 M 3 Pasir urug @ Rp. 80,000.00 = Rp. 24,000.00 0.780 Org Pekerja @ Rp. 40,000.00 = Rp. 31,200.00 0.390 Org Tukang batu @ Rp. 65,000.00 = Rp. 25,350.00 0.039 Org Kepala tukang @ Rp. 70,000.00 = Rp. 2,730.00 0.039 Org Mandor @ Rp. 50,000.00 = Rp. 1,950.00 Rp. 244,830.00 1 M² Plesteran, 1 Pc : 2 Ps tebal 15 mm 8.520 Kg Semen portland @ Rp. 1,390.00 = Rp. 11,842.80 0.017 M 3 Pasir pasang @ Rp. 110,000.00 = Rp. 1,870.00 0.200 Oh Pembantu tukang @ Rp. 40,000.00 = Rp. 8,000.00 0.150 Oh Tukang batu @ Rp. 65,000.00 = Rp. 9,750.00 0.015 Oh Kepala tukang @ Rp. 70,000.00 = Rp. 1,050.00 0.010 Oh Mandor @ Rp. 50,000.00 = Rp. 500.00 Rp. 33,012.80 1 M² Plesteran, 1 Pc : 5 Ps tebal 15 mm 4.320 Kg Semen portland @ Rp. 1,390.00 = Rp. 6,004.80 0.022 M 3 Pasir pasang @ Rp. 110,000.00 = Rp. 2,420.00 0.200 Oh Pembantu tukang @ Rp. 40,000.00 = Rp. 8,000.00 0.150 Oh Tukang batu @ Rp. 65,000.00 = Rp. 9,750.00 0.015 Oh Kepala tukang @ Rp. 70,000.00 = Rp. 1,050.00 0.010 Oh Mandor @ Rp. 50,000.00 = Rp. 500.00 Rp. 27,724.80 1 M² Acian plesteran 0.520 Kg Semen Pc @ Rp. 1,390.00 = Rp. 722.80 0.038 Oh Pembantu tukang @ Rp. 40,000.00 = Rp. 1,520.00 0.075 Oh Tukang batu @ Rp. 65,000.00 = Rp. 4,875.00 0.008 Oh Kepala tukang @ Rp. 70,000.00 = Rp. 525.00 0.002 Oh Mandor @ Rp. 50,000.00 = Rp. 95.00 = Rp. 7,737.80 1 M³ Membuat beton f'c 9,8 Mpa (K 125 ) 276.000 Kg Semen portland @ Rp. 1,390.00 = Rp. 383,640.00 828.000 Kg Pasir beton @ Rp. 85.71 = Rp. 70,967.88 1012.000 Kg Kerikil @ Rp. 78.52 = Rp. 79,462.24 1.650 Org Pekerja @ Rp. 40,000.00 = Rp. 66,000.00 0.275 Org Tukang batu @ Rp. 65,000.00 = Rp. 17,875.00 0.028 Org Kepala tukang @ Rp. 70,000.00 = Rp. 1,960.00 0.083 Org Mandor @ Rp. 50,000.00 = Rp. 4,150.00 Rp. 624,055.12 1 Bh Tiang Kayu Uk. 15 x 15 x 400 cm Dipancangkan Sedalam 1,0 Meter 4.000 M' Kayu ukuran 15 x 15 cm @ Rp. 76,000.00 = Rp. 304,000.00 1.000 Set Alat bantu pancang @ Rp. 15,000.00 = Rp. 15,000.00 0.645 Oh Pekerja @ Rp. 40,000.00 = Rp. 25,800.00 0.030 Oh Tukang Kayu @ Rp. 65,000.00 = Rp. 1,950.00 0.003 Oh Kepala Tukang @ Rp. 70,000.00 = Rp. 210.00 0.032 Oh Mandor @ Rp. 50,000.00 = Rp. 1,600.00 = Rp. 348,560.00 BOQ TambatanAnalisa
1 Bh Tiang Kayu Uk. 15 x 15 x 750 cm Dipancangkan Sedalam 1,0 Meter 7.500 M' Kayu ukuran 15 x 15 cm @ Rp. 76,000.00 = Rp. 570,000.00 1.000 Set Alat bantu pancang @ Rp. 15,000.00 = Rp. 15,000.00 0.645 Oh Pekerja @ Rp. 40,000.00 = Rp. 25,800.00 0.030 Oh Tukang Kayu @ Rp. 65,000.00 = Rp. 1,950.00 0.003 Oh Kepala Tukang @ Rp. 70,000.00 = Rp. 210.00 0.032 Oh Mandor @ Rp. 50,000.00 = Rp. 1,600.00 = Rp. 614,560.00 1 Bh Tiang Kayu Uk. 20 x 20 x 1000 cm Dipancangkan Sedalam 1,5 Meter 9.000 M' Kayu ukuran 20 x 20 cm @ Rp. 134,000.00 = Rp. 1,206,000.00 1.000 Set Alat bantu pancang @ Rp. 15,000.00 = Rp. 15,000.00 0.710 Oh Pekerja @ Rp. 40,000.00 = Rp. 28,380.00 0.033 Oh Tukang Kayu @ Rp. 65,000.00 = Rp. 2,145.00 0.003 Oh Kepala Tukang @ Rp. 70,000.00 = Rp. 231.00 0.035 Oh Mandor @ Rp. 50,000.00 = Rp. 1,760.00 = Rp. 1,253,516.00 1 M² Lantai Papan Tebal 5 cm 0.055 M³ Kayu Klas II, Papan @ Rp. 2,450,000.00 = Rp. 134,750.00 0.400 Kg Paku Biasa @ Rp. 18,000.00 = Rp. 7,200.00 0.133 Oh Pekerja @ Rp. 40,000.00 = Rp. 5,320.00 0.333 Oh Tukang Kayu @ Rp. 65,000.00 = Rp. 21,645.00 0.033 Oh Kepala Tukang @ Rp. 70,000.00 = Rp. 2,310.00 0.006 Oh Mandor @ Rp. 50,000.00 = Rp. 300.00 = Rp. 171,525.00 1 M³ Balok Gelagar, Sandaran / Skor Angin 1.100 M³ Kayu klas I, Balok @ Rp. 3,350,000.00 = Rp. 3,685,000.00 0.400 Kg Paku Biasa @ Rp. 18,000.00 = Rp. 7,200.00 5.000 Oh Pekerja @ Rp. 40,000.00 = Rp. 200,000.00 7.500 Oh Tukang Kayu @ Rp. 65,000.00 = Rp. 487,500.00 0.750 Oh Kepala Tukang @ Rp. 70,000.00 = Rp. 52,500.00 0.250 Oh Mandor @ Rp. 50,000.00 = Rp. 12,500.00 = Rp. 4,444,700.00 BOQ TambatanAnalisa
DAFTAR HARGA SATUAN UPAH PEKERJAAN KECAMATAN BALAESANG TAHUN ANGGARAN : 2012 NO. U R A I A N SATUAN UPAH VOLUME (Rp.) 1 Mandor Orang - Hari 50,000.00 2 Pekerja Orang - Hari 40,000.00 3 Kepala Tukang Gali Orang - Hari 70,000.00 4 Tukang Batu Orang - Hari 65,000.00 5 Kepala Tukang Batu Orang - Hari 70,000.00 6 Tukang Kayu Orang - Hari 65,000.00 7 Kepala Tukang Kayu Orang - Hari 70,000.00 8 Tukang Besi Orang - Hari 65,000.00 9 Kepala Tukang Besi Orang - Hari 70,000.00 10 Tukang Cat Orang - Hari 65,000.00 11 Kepala Tukang Cat Orang - Hari 70,000.00 12 Tukang Listrik Orang - Hari 65,000.00 13 Kepala Tukang Listrik Orang - Hari 70,000.00 14 Laden Tukang Orang - Hari 35,000.00 15 Tukang Pipa Orang - Hari 65,000.00 16 Kepala Tukang Pipa Orang - Hari 70,000.00 17 Operator Orang - Hari 80,000.00 18 Sopir Orang - Hari 45,000.00 19 Penjaga Malam Orang - Hari 35,000.00 KETERANGAN
DAFTAR HARGA SATUAN PERALATAN PEKERJAAN KECAMATAN BALAESANG TAHUN ANGG. : 2012 HARGA NO. JENIS PERALATAN SATUAN SATUAN KETERANGAN Rp. 1 Vibrator Concrete Jam 35,000.00 2 Stamper Jam 65,000.00 3 Wheel loader Jam 385,000.00 4 Tandem Roller Jam 315,000.00 5 Dump Truck Jam 250,000.00 6 Water Tank Truck Jam 225,000.00 7 Pan Pencampur Latasir Jam 50,000.00
DAFTAR HARGA SATUAN BAHAN PEKERJAAN KECAMATAN BALAESANG TAHUN ANGGARAN : 2012 No JENIS MATERIAL & BAHAN FABRIKASI Satuan HARGA SATUAN KETERANGAN I. Batu Pecah Manual Kerikil Split 1 / 2 m³ Rp. 212,000.00 Kerikil Split 2 / 3 m³ Rp. 212,000.00 Kerikil Split 3 / 5 m³ Rp. 212,000.00 Kerikil Split 5 / 7 m³ Rp. 212,000.00 Kerikil Sungai m³ Rp. 106,000.00 Kerikil (gs = 1,35 ton/m3) Kg Rp. 78.52 II. Tanah dan Pasir 1 Pasir Pasang m³ Rp. 110,000.00 2 Pasir Beton / Cor m³ Rp. 120,000.00 3 Pasir Plesteran m³ Rp. 110,000.00 4 Pasir Urug m³ Rp. 80,000.00 5 Sirtu m³ Rp. 90,000.00 6 Tanah Timbunan m³ Rp. 80,000.00 III. B a t u 1 Batu Kali / Batu Sungai m³ Rp. 133,000.00 2 Batu Belah m³ Rp. - IV. K a y u 1 Kayu Kelas I m³ Rp. 3,350,000.00 2 Kayu Kelas II m³ Rp. 2,450,000.00 3 Kayu Kelas III m³ Rp. 1,300,000.00 4 Kayu Bakar / Ikat Rp. 1,500.00 5 Tiang pancang kayu ukuran 15 x 15 cm (kayu kelas I) m' Rp. 76,000.00 6 Tiang pancang kayu ukuran 20 x 20 cm (Kayu kelas I) m' Rp. 134,000.00 V. Batu Cetak 1 Batu bata Bh Rp. 900.00 2 Batako Pres Bh Rp. 2,800.00 3 Paving Blok Bh Rp. 2,800.00 4 Roster Beton 20/20 Bh Rp. - 5 Roster Beton 25/25 Bh Rp. - VI. K a p u r 1 Kapur Pasang ( Mill ) Sak Rp. 35,000.00 VII. S e m e n 1 Tonasa ( 50 Kg ) Zak Rp. 69,500.00 2 Tiga Roda Zak Rp. - 3 Semen Warna / Putih Kg Rp. 4,400.00 4 AM - 30 Mortar Flex Kg Rp. - VIII. BUIS BETON A. BUIS BETON BERTULANG 1 Dia. 60 Cm Panjang 1 m' Bh Rp. 250,000.00 2 Dia. 80 Cm Panjang 1 m' Bh Rp. 300,000.00 3 Dia. 100 Cm Panjang 1 m' Bh Rp. 350,000.00 B. BUIS BETON TIDAK BERTULANG 1 Dia. 25 Cm Panjang 1 m' Bh Rp. 85,000.00 2 Dia. 40 Cm Panjang 1 m' Bh Rp. 125,000.00 3 Dia. 60 Cm Panjang 1 m' Bh Rp. - 4 Dia. 80 Cm Panjang 1 m' Bh Rp. -
No JENIS MATERIAL & BAHAN FABRIKASI Satuan HARGA SATUAN KETERANGAN IX. B E S I A. BESI BETON POLOS 1 Besi Beton Polos Uk. Ø 4 mm Btg Rp. - 2 Besi Beton Polos Uk. Ø 6 mm Btg Rp. 32,000.00 3 Besi Beton Polos Uk. Ø 8 mm Btg Rp. 35,000.00 4 Besi Beton Polos Uk. Ø 10 mm Btg Rp. 45,000.00 5 Besi Beton Polos Uk. Ø 12 mm Btg Rp. 70,000.00 6 Besi Beton Polos Uk. Ø 14 mm Btg Rp. 110,000.00 7 Besi Beton Polos Uk. Ø 16 mm Btg Rp. 150,000.00 8 Besi Beton Polos Uk. Ø 18 mm Btg Rp. 240,000.00 9 Besi Beton Polos Uk. Ø 20 mm Btg Rp. - 10 Harga satuan rata-rata besi per kg Kg Rp. 10,600.00 B. BESI BETON ULIR 1 Besi Beton Ulir Uk. Ø 10 mm Btg Rp. - 2 Besi Beton Ulir Uk. Ø 13 mm Btg Rp. - 3 Besi Beton Ulir Uk. Ø 16 mm Btg Rp. - 4 Besi Beton Ulir Uk. Ø 19 mm Btg Rp. - 5 Besi Beton Ulir Uk. Ø 22 mm Btg Rp. - 6 Besi Beton Ulir Uk. Ø 25 mm Btg Rp. - C. BESI PLAT Uk. 120 x 120 Cm 1 Tebal 1,2 mm Lbr Rp. 575,000.00 2 Tebal 1,5 mm Lbr Rp. 600,000.00 3 Tebal 2,3 mm Lbr Rp. 650,000.00 4 Tebal 3 mm Lbr Rp. - D. BESI SIKU 1 Ukuran : 30. 30. 3 mm - 6 m' Btg Rp. 75,000.00 2 Ukuran : 40. 40. 3 mm - 6 m' Btg Rp. 90,000.00 3 Ukuran : 40. 40. 4 mm - 6 m' Btg Rp. 190,000.00 4 Ukuran : 50. 50. 4 mm - 6 m' Btg Rp. 275,000.00 5 Ukuran : 50. 50. 5 mm - 6 m' Btg Rp. 350,000.00 6 Ukuran : 60. 60. 6 mm - 6 m' Btg Rp. - 7 Ukuran : 70. 70. 6 mm - 6 m' Btg Rp. - 8 Ukuran : 100. 100. 10 mm - 6 m' Btg Rp. - E. KAWAT 1 Kawat Beton / Bendrat Kg Rp. 20,000.00 2 Kawat Duri ( 50 m ) Roll Rp. 250,000.00 3 Kawat Nyamuk dari Logam m' Rp. - 4 Kawat Jaringan / Ayakan m' Rp. 20,000.00 5 Kawat Harmonika m' Rp. 25,000.00 6 Kawat Bronjong ( 50 Kg ) Roll Rp. - X. PAKU - PAKUAN 1 Paku Beton Uk. 1'' - 2'' Kg Rp. 28,000.00 2 Paku Beton Uk. 2,5'' - 3,5'' Kg Rp. 28,000.00 3 Paku Beton Uk. 4'' - 6'' Kg Rp. 28,000.00 4 Paku Biasa Uk. 2'' - 5'' Kg Rp. 18,000.00 5 Paku Biasa Uk. 2,5'' - 3,5'' Kg Rp. 18,000.00 6 Paku Biasa Uk. 4'' - 6'' Kg Rp. 18,000.00 7 Paku Tripleks Kg Rp. 28,000.00 8 Paku Seng Kg Rp. 26,000.00 9 Paku Gypsum Kg Rp. - 10 Paku Sirap Kg Rp. - 11 Paku Kait Kg Rp. - 12 Paku Tindis Dos Rp. 5,000.00 13 Paku Sekrup 2 Cm Dos Rp. 12,000.00 14 Paku Sekrup 4 Cm Dos Rp. 12,000.00 15 Baut Engsel Besi Dos Rp. 18,000.00 16 Baut & mur Ø12-250 Set Rp. 7,000.00
No JENIS MATERIAL & BAHAN FABRIKASI Satuan HARGA SATUAN KETERANGAN XIX. BAHAN FINISHING A. CAT BESI & CAT JALAN 1 Cat Marka Jalan Kg Rp. - 2 Cat Besi Alteks Kg Rp. 15,000.00 3 Meni Besi Kg Rp. 10,000.00 B. CAT KAYU 1 Cat Glotex Kg Rp. 55,000.00 2 Meni Kayu Kg Rp. 32,000.00 3 Politur Kg Rp. 50,000.00 4 Bintang Kg Rp. - 5 Vernis Kg Rp. 23,000.00 6 Lem Kayu ( Fox ) Kg Rp. 30,000.00 7 Pisau Dempul Bh Rp. 10,000.00 C. CAT TEMBOK 1 Aries Kg Rp. 55,000.00 2 Virgo Kg Rp. 60,000.00 3 Yoko Kg Rp. 58,000.00 4 Plamur Tembok ( Boyo ) Kg Rp. 44,000.00 XX. BAHAN LAIN-LAIN 1 Premium Ltr Rp. 4,500.00 2 Solar Ltr Rp. 4,500.00 3 Minyak Tanah Ltr Rp. 3,500.00 4 Minyak Pelumas / Oli Ltr Rp. 26,000.00 5 Aspal Kg Rp. 11,000.00 6 Afdunner Ltr Rp. 20,000.00 7 Spritus Ltr Rp. 25,000.00 8 Kertas Pasir Lbr Rp. 5,000.00