REKAPITULASI RENCANA ANGGARAN BIAYA Tahun Anggaran URAIAN JUMLAH (Rp.) ARSITEKTURAL I. PEKERJAAN PERSIAPAN Rp. 5,097,312 II PEK. DINDING BATA Rp. 54,697,323 III. PEKERJAAN LANTAI Rp. 12,669,109 IV. PEKERJAAN PLAFOND Rp. 8,128,665 V PEKERJAAN PINTU DAN JENDELA Rp. 17,891,088 VI PEKERJAAN SANITAIR Rp. 1,948,640 VII. PEKERJAAN ATAP Rp. 16,466,833 VIII PEKERJAAN LAIN LAIN 11,588,256 SUB TOTAL Rp. 128,487,225 STRUKTURAL I. PEKERJAAN GALIAN dan URUGAN Rp. 2,517,919 II. PEK. PONDASI DAN BETON Rp. 32,439,198 SUB TOTAL Rp. 34,957,117 MEKANIKAL ELEKTRIKAL I. PEKERJAAN AIR BERSIH Rp. 7,283,300 II. PEKERJAAN AIR KOTOR Rp. 15,336,757 III. PEKERJAAN ELEKTRIKAL Rp. 11,420,600 SUB TOTAL Rp. 34,040,656 JUMLAH KONSTRUKSI Rp. 197,484,999 PPN 10% Rp. 19,748,500 TOTAL Rp. 217,233,498 DI BULATKAN Rp. 218,741,000 TERBILANG : # DUA RATUS DELAPAN BELAS JUTA TUJUH RATUS EMPAT PULUH SATU RIBU RUPIAH# Cimahi, 21 Mei Mitra Consultant Engineering H.Hari Pradoko,ST. MT. Direktur KOTA CIMAHI
RENCANA ANGGARAN BIAYA Tahun Anggaran NO. KODE DESKRIPSI PEKERJAAN KETERANGAN I. PEKERJAAN PERSIAPAN VOLUME SATUAN JML SAT (Rp.) JUMLAH (Rp.) 1 Listrik kerja dan jaringannya (biaya pemakaian) ******* 1.00 ls 750,000 750,000 2 Air kerja dan jaringannya ******* 1.00 ls 900,000 900,000 3 Pengukuran dan staking out ******* 70.00 m² 15,000 1,050,000 4 Pasang bowplank ******* 34.00 m¹ 70,509 2,397,312 II. PEK. DINDING BATA Subtotal I 5,097,312 1 DINDING BATA a Pas. Bata merah 1:5 BATA MERAH GARUT/PASIR PASANG CIMLAKA 201.70 m² 92,260 18,608,842 b Plesteran + acian 1:4 SEMEN TIGA RODA /PASIR PASANG CIMALAKA 403.40 m² 47,610 19,205,874 c Pengecatan dinding luar /SETARA VINILEX SANLEX 201.70 m² 15,420 3,110,214 d Pengecatan dinding dalam /SETARA VINILEX SANLEX 201.70 m² 15,420 3,110,214 2 KERAMIK DINDING a Toilet KW 01, 20X20 11.55 m² 153,900 1,777,545 b Dapur bersih KW 0, 20X20 CM 2.31 m² 153,900 355,509 c Cor nad SEMEN WARNA 13.86 m² 8,000 110,880 3 MEJA BETON a Meja beton dapur bersih PLAT BETON 0.23 m³ 5,217,380 1,205,215 4 DINDING PAGAR a Pondasi batu kali BATU BELAH /PASIRPASANG CIMALAKA 4.80 m³ 610,850 2,932,080 b Sloof 15/20 BETON BERTULANG /BESI TULANGAN BESI SNI 0.38 m³ 3,594,800 1,348,050 PASIR BETON CIMALAKA/SPLIT/PC TIGA RODA c Kolom 15/15 BETON BERTULANG /BESI TULANGAN BESI SNI 4.00 m' 66,850 267,400 PASIR BETON CIMALAKA/SPLIT/PC TIGA RODA d Ringbalk 15/20 BETON BERTULANG /BESI TULANGAN BESI SNI 10.00 m' 66,850 668,500 PASIR BETON CIMALAKA/SPLIT/PC TIGA RODA e Pas. Dinding conblok CISANGKAN 10.00 m² 199,700 1,997,000 III. PEKERJAAN LANTAI Subtotal II 54,697,323 1 KERAMIK LANTAI : a R.dalam KW 1, 40X40 CM POLIS 54.00 m² 144,110 7,781,940 b teras KW 1, 40X40 CM UNPOLISH 4.80 m² 145,840 700,032 c km/wc ROMAN 25X25 CM UN POLIS 3.00 m² 142,900 428,700 d Cor nad SEMEN WARNA 61.80 m² 8,000 494,400 e Plint lantai keramik KRAMIK 10X40 CM UN POLIS 77.50 m¹ 30,670 2,376,925 2 RABAT BETON : a Cor beton 1:2:3 t=10cm PASIR BETON 1 CIMALAKA / SPLIT 0.22 m³ 3,594,800 798,046 SETARA SEMEN TIGA RODA b Kamprot halus 2.22 m² 40,120 89,066 IV. PEKERJAAN PLAFOND Subtotal III 12,669,109 1 Plafond Gypsum Datar RANGKA HOLOW 20X40 & 40X40 MM GALVANIS 54.50 m² 96,270 5,246,715 GYPSUM EX.KNAUF 2 Plafond GRC RANGKA HOLOW 20X40 & 40X40 MM GALVANIS 6.00 m² 96,270 577,620 GRC /GERSIK PRTLAND CEMENT 3 List Plafond LIST GYPSUM 85.50 m² 16,040 1,371,420 4 Pengecatan Plafond SETARA VINILEX/SANLEX 60.50 m² 15,420 932,910 V. PEKERJAAN PINTU DAN JENDELA Subtotal IV 8,128,665 1 P1&P2 Kusen Pintu 5 UNIT RANGKA KUSEN : ALUMUNIUM EX. ALEXINDO 36.00 m' 93,230 3,356,280 (uk. 85cmx275 cm) Daun pintu Fin Vernis RANGKA KAYU BORNEO, DOBEL TRIPLEX 11.69 m² 403,840 4,719,880 Pas kaca boven KACA CLER 5mm 0.34 m² 119,850 40,449 Pas engsel ENGSEL 2 BUAH 5.00 bh 54,950 274,750 Pas kunci SETARA ROYAL 5.00 bh 207,960 1,039,800 Pas pegangan pintu 5.00 bh 124,530 622,650 KOTA CIMAH
2 P3 Kusen Pintu KM WC 1 UNIT RANGKA KUSEN : ALUMUNIUM EX. ALEXINDO 7.00 m' 93,230 652,610 (uk. 75cmx275 cm) Daun pintu RANGKA ALUMUNIUM 3.60 m² 147,510 531,036 Pas kaca boven KACA ES 5mm 0.29 m² 119,850 35,056 Pas engsel ENGSEL 2 BUAH 1.00 bh 54,950 54,950 Pas kunci SETARA ROYAL 1.00 bh 207,960 207,960 Pas pegangan pintu 1.00 bh 124,530 124,530 3 P4 Kusen Pintu Keluarga RANGKA KUSEN : ALUMUNIUM EX. ALEXINDO 14.70 m' - Daun pintu Fin Vernis RANGKA KAYU BORNEO, DOBEL TRIPLEX 1.68 m² 403,840 678,451 Pas kaca boven& jendela KACA CLER 5mm 1.71 m² 119,850 204,944 Pas engsel ENGSEL 2 BUAH 3.00 bh 54,950 164,850 Pas kunci SETARA ROYAL 1.00 bh 207,960 207,960 Daun Jendela SETARA ALEXINDO 3.5 CM 1.64 m² 69,690 114,292 Pas Slot 2.00 bh 31,110 62,220 hak angin 4.00 bh 38,450 153,800 Pas pegangan pintu 1.00 bh 124,530 124,530 4 J1 Kusen jendela RANGKA KUSEN : ALUMUNIUM EX. ALEXINDO 30.50 m' 93,230 2,843,515 Daun jendela SETARA ALEXINDO 3.5 CM 4.03 m² 69,690 280,502 Pas kaca KACA CLER 5mm 4.85 m² 119,850 581,273 Pas engsel ENGSEL 2 BUAH 5.00 bh 54,950 274,750 Pas slot 5.00 bh 31,110 155,550 Pas hak angin 10.00 bh 38,450 384,500 5 BV1 Kusen jendela bouven lich RANGKA KUSEN : ALUMUNIUM EX. ALEXINDO 2.70 m' 93,230 251,721 Pas kaca KACA CLER 5mm 0.46 m² 119,850 Subtotal V 17,891,088 VI. PEKERJAAN SANITAIR 1 Zink 1.00 bh 272,160 272,160 2 Kran zink STAILESS STEEL 1.00 bh 37,030 37,030 3 Kran KM + T. Cuci KRAN STENLES STEEL 2.00 bh 37,030 74,060 4 Closet jongkok EX.INA 1.00 set 401,830 401,830 5 T. sabun BAHAN KRAMIK 1 SNI 1.00 bh 118,750 118,750 6 Bak mandi atu bata FINISING KRAMIK 1.00 Set 1,004,180 1,004,180 7 Floor Drain STENLES STEEL 1.00 bh 40,630 40,630 VII. PEKERJAAN ATAP Subtotal VI 1,948,640 1 ATAP GENTENG a Rangka baja ringan EX.SMARTTRUSS ROOF APLIKATOR 70.00 m² 135,000 9,450,000 b Penutup atap genteng palentong EX. JATIWANGI 111.00 m² 20,180 2,239,980 c Pek. Nok palentong EX. SEGITIGA JATI WANGI 11.65 m¹ 73,850 860,353 d Listplank WOOD PLANK/GRC 30.00 m¹ 42,050 1,261,500 e Talang depan dan belakang plat Besi tekuk 17.00 m¹ 125,000 2,125,000 f Talang Vertikal 3" PVC 8.00 m¹ 66,250 530,000 Subtotal VII 16,466,833 VIII PEKERJAAN LAIN LAIN 1 TOWER BESI TOREN KETINGGIAN 6M KAPASITAS KEKUATAN 1000 LITER BESI 60.60.6 87.61 kg 21,450 3,132,017 BESI 50.50.5 141.75 kg 21,450 5,067,563 BESI 40.40.3 20.86 kg 21,450 745,817 PLAT 3MM 9.60 kg 21,450 205,920 PONDASI BETON 0.20 m3 5,049,020 1,009,804 TORN KAPASITAS 1000 L 1.00 bh 1,080,000 1,080,000 PAPAN DUDUKAN 3CM 0.08 m3 4,520,000 347,136 Subtotal XI 11,588,256 KOTA CIMAH
RENCANA ANGGARAN BIAYA Tahun Anggaran NO. KODE DESKRIPSI PEKERJAAN VOLUME SATUAN JML SAT (Rp.) JUMLAH (Rp.) I. PEKERJAAN GALIAN dan URUGAN 1 Galian pondasi batu kali 48.38 m³ 40,680 1,967,895 2 Urugan pasir bawah pondasi batu kali 4.84 m³ 88,870 429,909 3 Lantai kerja bawah pondasi telapak 2.42 m³ 49,660 120,115 II. PEK. PONDASI DAN BETON Subtotal I 2,517,919 1 Sloof 15/20 2.42 m³ 3,594,800 8,694,923 2 Pondasi batu kali 23.22 m³ 588,050 13,654,521 3 Kolom KP 15/15 0.99 m³ 5,067,970 5,035,535 4 RB 1 15/20 64.50 m' 78,360 5,054,220 Subtotal II 32,439,198 KOTA CIMAHI
RENCANA ANGGARAN BIAYA Tahun Anggaran NO. URAIAN PEKERJAAN SAT VOL LINGKUP PEKERJAAN : PLUMBING SAT. TOTAL A PEKERJAAN AIR BERSIH INSTALASI PEMIPAAN AIR BERSIH a PEKERJAAN PLUMBING AIR BERSIH AS 3-6 KOLOM I-J Pipa PVC, Class AW Standard JIS K 6741/2, 10 Kg/cm2, etc. ~ PVC AW dia 20mm m 15.00 22,500.00 337,500.00 ~ PVC AW dia 15mm m 20.00 16,000.00 320,000.00 ~ Aplikasi air bersih bertekanan & alat bantu ls 1.00 250,000.00 250,000.00 b PEKERJAAN PLUMBING AIR BERSIH DARI TOREN Pipa PVC, Class AW Standard JIS K 6741/2, 10 Kg/cm2, etc. Peralatan utama BOOSTER PUMP (Jet Pump) Pengadaan, Pemasangan & pondasi pompa unit 1.00 750,000.00 750,000.00 Lokasi : Toren T y p e : Jet Pump Kelengkapan : dudukan diatas pondasi batu kali seukuran mesin Total head : D a y a : 100 w Valve - Valve : - Gate Valve Dia. 50 mm 2.00 500,000.00 1,000,000.00 - Gate Valve Dia. 40 mm 2.00 450,000.00 900,000.00 - Flexible Joint Dia. 50 mm 2.00 350,000.00 700,000.00 - Check Valve Dia. 50 mm 2.00 450,000.00 900,000.00 Pemipaan Air Bersih dengan pipa PVC AW" Wavin Standard - PVC AW dia 20mm m' 60.00 22,828.58 1,369,714.50 - PVC AW dia 15mm m' 40.00 18,902.13 756,085.00 c Testing Commssioning ls 1.00 1,500,000.00 1,500,000.00 TOTAL PEKERJAAN AIR BERSIH 7,283,299.50 B PEKERJAAN AIR KOTOR INSTALASI PEMIPAAN AIR KOTOR a PEKERJAAN PLUMBING AIR KOTOR AS 3-6 KOLOM I-J Pemipaan Air Kotor, Air bekas & Vent dengan pipa PVC AW" Standard, 5kg/cm2 ~ PVC dia 50mm m 15.00 110,000.00 1,650,000.00 ~ PVC dia 65mm m 15.00 180,000.00 2,700,000.00 ~ Aplikasi air bersih bertekanan & alat bantu ls 1.00 600.00 600.00 PEKERJAAN SEPTICTANK ~ Septictank kap 20m3 uk 40X20X25 Pekerjaan galian m³ 20.69 40,680.00 841,669.20 Pasangan Bata m² 36.26 92,260.00 3,345,347.60 Pekerjaan Plesteran m² 36.26 49,660.00 1,800,671.60 Pekerjaan Beton m³ 0.89 5,217,380.00 4,643,468.20 Plat besi m² 1.28 250,000.00 320,000.00 b Testing Commssioning ls 1.00 35,000.00 35,000.00 TOTAL PEKERJAAN AIR KOTOR 15,336,756.60 TOTAL PEKERJAAN PLUMBING 22,620,056.10
LINGKUP PEKERJAAN : ELECTRIKAL NO. URAIAN PEKERJAAN VOL SAT C PEKERJAAN ELEKTRIKAL I INSTALASI PENERANGAN & STOP KONTAK SAT. TOTAL ~ MCB 1.00 bh 160,000.00 160,000.00 ~ Lampu Downlight Essential 25W 10.00 bh 67,000.00 670,000.00 ~ Stop Kontak 1P,10A 6.00 bh 21,250.00 127,500.00 ~ Saklar ganda 2.00 bh 17,000.00 34,000.00 ~ Saklar tunggal 4.00 bh 11,000.00 44,000.00 ~ Instalasi Penerangan dgn kabel NYA 3X(1X2.5 mm2) dlm PVC conduit 20 mm 6.00 ttk 75,000.00 450,000.00 ~ Instalasi Stop kontak dgn kabel NYA 3X(1X2.5 mm2) dlm PVC conduit 20 mm 6.00 ttk 75,000.00 450,000.00 II PEKERJAAN KABEL FEEDER ~ Dari Panel Utama ke Panel lighting LP-A NYY3X2.5mm2 15.00 m' 21,000.00 315,000.00 ~ Dari Panel Utama ke Panel lighting PP-A NYY3X2.5mm2 15.00 m' 21,000.00 315,000.00 ~ Dari Panel Utama ke Panel lighting PP-POMPA NYY3X2.5mm2 15.00 m' 21,000.00 315,000.00 III PEKERJAAN PANEL LISTRIK ~ Panel Utama Dari PLN 1.00 unit 1,750,000.00 1,750,000.00 Grounding Panel lengkap Bak kontrol 50x50x50 1.00 unit 250,000.00 250,000.00 V BIAYA PERIZINAN Penyambungan daya 75kVA terdiri dari: Biaya penyambungan 220 VA 1,400.00 308,000.00 Uang jaminan langganan 220 VA 450.00 99,000.00 VI TEST COMMISSIONING 220.00 VA 605.00 133,100.00 TOTAL PEKERJAAN ELEKTRIKAL 11,420,600.00