ANALISIS PRODUKTIVITAS PEKERJAAN PEMASANGAN RANGKA ATAP BAJA RINGAN

dokumen-dokumen yang mirip
ANALISIS FAKTOR-FAKTOR PENYEBAB KETERLAMBATAN PADA PEKERJAAN TIANG PANCANG

ANALISIS KOMPETENSI DAN GAYA KEPEMIMPINAN PROJECT MANAGER PADA PROYEK KONSTRUKSI BANGUNAN GEDUNG

SIMULASI ARUS KAS PADA PROYEK PEMBANGUNAN GEDUNG SEKOLAH SMP DAN SMA STRADA KRANJI

ANALISIS MATERIAL REQUIREMENT PLANNING (MRP) PROYEK JEMBATAN DI JAYAPURA

ANALISIS BIAYA BANK GARANSI TERHADAP ARUS KAS PROYEK

ANALISIS FAKTOR-FAKTOR DOMINAN PENYEBAB KETERLAMBATAN PROYEK KONSTRUKSI BANGUNAN APARTEMEN X BANDUNG

STUDI PERBANDINGAN PRODUKTIVITAS PEKERJAAN PEMASANGAN PENUTUP LANTAI

ANALISIS MANAJEMEN DAN KINERJA PEKERJAAN PEMBONGKARAN GEDUNG DENGAN METODE EARNED VALUE ANALYSIS PADA GEDUNG BANK PANIN BINTARO

ANALISIS PENGGUNAAN METODE CRITICAL PATH SEGMENT (CPS) PADA PENJADWALAN PEKERJAAN STRUKTUR PROYEK KONSTRUKSI GEDUNG

ANALISIS RISIKO PROSES PABRIKASI DAN PEMANCANGAN TIANG PANCANG BETON DENGAN METODE FAILURE MODE AND EFFECTS ANALYSIS

SEKUENSIAL PENYEBAB SENGKETA KONSTRUKSI DENGAN MENGGUNAKAN METODE PATH ANALYSIS

PENGARUH KUALITAS MANAJEMEN KOMUNIKASI ANTARA KONTRAKTOR DAN KONSULTAN TERHADAP KEBERHASILAN PROYEK JALAN DI LINGKUNGAN KOTA BARU PARAHYANGAN

ANALISIS GREEN CONSTRUCTION PADA PROYEK X DI BANDUNG DENGAN METODE ASSESSMENT GREEN CONSTRUCTION SISTEM WULFRAM

INVESTIGASI PENERAPAN KONSEP BUILDING INFORMATION MODELLING (BIM) PADA PROYEK KONSTRUKSI HIGH RISE BUILDING DI INDONESIA

LAPORAN PELAKSANAAN ROADMAP PENELITIAN KOMUNITAS BIDANG ILMU MANAJEMEN DAN REKAYASA KONSTRUKSI TAHUN

SIMULASI PERENCANAAN PENGGUNAAN ALAT BERAT PADA PEKERJAAN PENGGALIAN TANAH

ANALISIS FAKTOR-FAKTOR YANG MEMPENGARUHI PENERAPAN SISTEM MANAJEMEN K3 PADA KONTRAKTOR BERSERTIFIKASI OHSAS 18001

ANALISIS HUBUNGAN PERILAKU KEPEMIMPINAN MANAJER PROYEK DENGAN KINERJA PROYEK KONSTRUKSI

ROADMAP PENELITIAN KOMUNITAS BIDANG ILMU MANAJEMEN DAN REKAYASA KONSTRUKSI TAHUN

PERINGKAT FAKTOR KETERLAMBATAN BERDASARKAN COMPENSABLE DELAYS, EXCUSABLE DELAYS DAN NON-EXCUSABLE DELAYS PADA PROYEK GEDUNG DI KOTA BANDUNG

INVESTIGASI PENERAPAN KONSEP BUILDING INFORMATION MODELLING (BIM) PADA PROYEK KONSTRUKSI DI BIDANG MINYAK DAN GAS BUMI DI INDONESIA

IDENTIFIKASI FAKTOR-FAKTOR YANG BERPENGARUH TERHADAP PENYIMPANGAN BIAYA MATERIAL RANGKA ATAP BAJA RINGAN PADA PT. X SKRIPSI

SKRIPSI OPTIMASI BIAYA DAN WAKTU PENGGUNAAN ALAT BERAT PADA PEKERJAAN PENGGALIAN TANAH MENGGUNAKAN METODE PROGRAMA LINEAR INTEGER

ROADMAP PENELITIAN KOMUNITAS BIDANG ILMU MANAJEMEN DAN REKAYASA KONSTRUKSI TAHUN

KAJIAN PRODUKTIVITAS PADA PEKERJAAAN PENUTUP ATAP

ANALISIS FAKTOR-FAKTOR PENGHAMBAT YANG BERPENGARUH TERHADAP KINERJA WAKTU PELAKSANAAN PROYEK KONSTRUKSI BANGUNAN GEDUNG APARTEMEN DI KOTA BANDUNG

SKRIPSI EVALUASI PENAMPANG WHITMORE PADA SAMBUNGAN BAUT DENGAN ANALISIS KERUNTUHAN MENGGUNAKAN PROGRAM ADINA

ANALISIS SEBAB-DAMPAK DAN FAKTOR RISIKO DARI CHANGE ORDER PADA PROYEK KONSTRUKSI

BAB I PENDAHULUAN. A. Latar Belakang

STUDI EKSPERIMENTAL KUAT TEKAN BETON DENGAN PLASTIK DAUR ULANG OLAHAN JENIS HDPE PENGGANTI SEBAGIAN AGREGAT HALUS

STUDI FAKTOR-FAKTOR PENYEBAB KETERLAMBATAN PADA PROYEK FINE YARN III BUILDING, TANGERANG ABSTRAK

BAB I PENDAHULUAN 1.1 Latar Belakang

STUDI EKSPERIMENTAL KEKUATAN TEKAN SAMBUNGAN MORTISE-AND-TENON BERPENAMPANG LINGKARAN KAYU MERANTI

ESTIMASI BIAYA DAN PENJADWALAN PADA PROYEK JALAN AKSES GEDEBAGE MENGGUNAKAN SIMULASI MONTE CARLO

STUDI MENGENAI FAKTOR PENGHAMBAT PELAKSANAAN PROYEK DI SORONG PAPUA BARAT

SIMULASI PENJADWALAN PROYEK KONSTRUKSI DENGAN PROGRAM KOMPUTER BERBASIS FUZZY LOGIC

STUDI PERBANDINGAN BIAYA PENGGUNAAN BETON RINGAN AERASI DENGAN BATA MERAH BIASA

TESIS STUDI MENGENAI VOLUME LIMBAH DAN MANFAAT MANAJEMEN LIMBAH BERDASARKAN PERSEPSI KONTRAKTOR DI YOGYAKARTA

PERBANDINGAN HARGA DAN KEKUATAN STRUKTUR ANTARA RANGKA ATAP KAYU DENGAN RANGKA ATAP BAJA RINGAN PADA BERBAGAI JENIS PENUTUP ATAP

MANAJEMEN RISIKO PADA PROYEK KONSTRUKSI GEDUNG DI YOGYAKARTA DENGAN MENGGUNAKAN METODE HOUSE OF RISK

STUDI PERBANDINGAN BIAYA KONSTRUKSI METODE PERKERASAN PADA PROYEK X

ANALISIS JALUR PENGENDALIAN AKTIVITAS PROYEK KONSTRUKSI DENGAN LINEAR SCHEDULING METHOD

BAB I PENDAHULUAN 1.1 Latar Belakang

BAB I PENDAHULUAN 1.1 Latar Belakang Masalah

TUGAS AKHIR. Oleh : I Gusti Made Dwi Atmaja

METODE PELAKSANAAN DAN ANALISIS PERBANDINGAN KEBUTUHAN TULANGAN ANTARA GAMBAR KERJA DENGAN SNI 7394:2008 PADA PEMBANGUNAN RUKO R2 NO

EVALUASI ARUS KAS KONTRAKTOR DENGAN SISTEM ANGSURAN PEMBAYARAN BULANAN

STUDI PERBANDINGAN PARAMETER KUAT GESER TANAH KOHESIF MENGGUNAKAN UJI MINI VANE SHEAR, UJI KUAT TEKAN BEBAS, DAN VANE SHEAR LAPANGAN

PERENCANAAN RANGKA ATAP BAJA RINGAN BERDASARKAN SNI 7971 : 2013 IMMANIAR F. SINAGA. Ir. Sanci Barus, M.T.

ANALISIS PERUBAHAN TEGANGAN DI DALAM TANAH AKIBAT TIMBUNAN MENGGUNAKAN METODE ELEMEN HINGGA

TESIS YOGYAKARTA NPM

STUDI KLASIFIKASI DAN PERINGKAT PENYEBAB- PENYEBAB KETERLAMBATAN WAKTU PELAKSANAAN PROYEK

DAFTAR ISI... HALAMAN JUDUL... LEMBAR PENGESAHAN... LEMBAR PERSEMBAHAN... MOTTO... KATA PENGANTAR... INTISARI... LEMBAR KONSULTASI... DAFTAR TABEL...

STUDI KEKUATAN RANGKA ATAP TRUSS MENGGUNAKAN PIPA BAJA DENGAN SAMBUNGAN LAS DENGAN PELAT SAMBUNG

SKRIPSI Disusun sebagai Syarat Memperoleh Gelar Sarjana Teknik Pada Program Studi Teknik Sipil Fakultas Teknik Universitas Sebelas Maret Surakarta

ANALISIS FAKTOR FAKTOR PENYEBAB KETERLAMBATAN PADA PROYEK KONSTRUKSI PELABUHAN DI INDONESIA

BAB I PENDAHULUAN. Seiring dengan perkembangan teknologi dan kebutuhan, struktur sipil. yang mutlak harus dipenuhi seperti aspek ekonomi dan kemudahan

KEBUTUHAN TEKNOLOGI INFORMASI UNTUK MENINGKATKAN KUALITAS LAYANAN TERMINAL LEUWIPANJANG BANDUNG

REDESAIN RANGKA ATAP BAJA KONVENSIONAL GEDUNG FAKULTAS TEKNIK UNIVERSITAS MUHAMMADIYAH PURWOKERTO

ANALISIS PERBANDINGAN BIAYA DAN WAKTU, PEKERJAAN BEKISTING PELAT LANTAI MENGGUNAKAN KAYU (MULTIPLEX) DAN PELAT BONDEK

ANALISIS EFISIENSI BIAYA DAN EFEKTIVITAS WAKTU DENGAN METODE LINE OF BALANCE (Studi Kasus: The Royal Bukit)

PEMASANGAN STRUKTUR RANGKA ATAP YANG EFISIEN

SKRIPSI JURUSAN TEKNIK SIPIL FAKULTAS TEKNIK UNIVERSITAS SEBELAS MARET SURAKARTA commit to user

ANALISIS NILAI HASIL TERHADAP WAKTU PADA PROYEK KONSTRUKSI (Studi Kasus Pada Proyek Pembangunan Hotel Eastparc Yogyakarta) SKRIPSI

BAB I PENDAHULUAN. McGraw-Hill, Journal of Construction Engineering and Management, Vol. 119, No.4, December, 1993, pg ), hal.

PERNY AT AAN KEASLIAN KARYA TULIS TUGASAKHIR. Saya mahasiswa Jurusan Teknik Sipil, Fakultas Desain dan Teknik Perencanaan, Universitas Pelita Harapan,

PENGUKURAN PRODUKTIVITAS TUKANG DAN PEKERJA PADA PEKERJAAN DAK KERATON DENGAN METODE RATED ACTIVITY SAMPLING

LAPORAN. Ditulis untuk Menyelesaikan. Mata Kuliah Tugas Akhir Semester VI. Pendidikan Program Diploma III. oleh: NIM NIM.

STUDI ANALISIS PERUBAHAN PEKERJAAN DALAM PROYEK KONSTRUKSI

PERPINDAHAN PENGGUNA MODA TRANSPORTASI JALAN KE MODA TRANSPORTASI KERETA API RUTE JAKARTA BANDAR UDARA SOEKARNO-HATTA

UNIVERSITAS INDONESIA PENGARUH PENERAPAN GREEN CONSTRUCTION PADA BANGUNAN GEDUNG TERHADAP KINERJA MUTU PROYEK DI LINGKUNGAN PT.

EFEK VARIASI TEGANGAN NORMAL TERHADAP FRIKSI TANAH-BETON DENGAN UJI GESER LANGSUNG

ANALISA RESIKO TERHADAP PRODUKTIVITAS TENAGA KERJA DENGAN METODE FUZZY

TUGAS AKHIR ANALISIS PRODUKTIVITAS PEKERJAAN STRUKTUR LANTAI KONVENSIONAL DAN HOLLOW CORE FLOOR PANEL (HCFP)

KAJIAN TERHADAP PRASARANA DAN SARANA EVAKUASI PADA PROYEK KONSTRUKSI

TINJAUAN KEKUATAN DAN BIAYA STRUKTUR ATAP BAJA RINGAN DAN BAJA KONVENSIONAL GEDUNG DIKLAT RSUP DR. KARIADI SEMARANG

PENELITIAN AWAL PENENTUAN WAKTU PENYELESAIAN PROYEK DENGAN METODE PERT (PROJECT EVALUATION AND REVIEW TECHNIQUE)

ANALISA RISIKO PEKERJAAN TANAH DAN PONDASI PADA PROYEK BANGUNAN GEDUNG DI JABODETABEK SKRIPSI

BAB I PENDAHULUAN. 1.1 Latar Belakang

BAB I PENDAHULUAN. yang ada di bawahnya dari panas,hujan, angin, dan benda-benda lain yang bisa

ANALISIS PERBANDINGAN FAKTOR - FAKTOR PENYEBAB KETERLAMBATAN PENGERJAAN PROYEK KONSTRUKSI DI PROVINSI JATENG DAN DIY

ESTIMASI BIAYA KONSTRUKSI GEDUNG DENGAN METODE COST SIGNIFICANT MODEL (STUDI KASUS PROYEK KONSTRUKSI GEDUNG PEMERINTAH DI KABUPATEN JEMBRANA)

SKRIPSI ANALISIS RISIKO KONSTRUKSI STRUKTUR BORE PILE PADA PROYEK DENGAN METODE ANALYTICAL HIERARCHY PROCESS (AHP)

PERBANDINGAN EFISIENSI KERJA ALAT DIESEL HAMMER

ESTIMASI ANGGARAN BIAYA PEKERJAAN STRUKTUR DAN PENJADWALAN PADA PROYEK PEMBANGUNAN GEDUNG KCU BCA DI JALAN ASIA MEDAN

SKRIPSI UJI EKSPERIMENTAL BETON NORMAL DIBANDINGKAN BETON SELF COMPACTING DENGAN AGREGAT DAUR ULANG DAN LIMBAH GENTENG TANAH LIAT

PEMODELAN PERAMALAN DEBIT SUNGAI JIANGWAN PROVINSI ZHEJIANG RRT DENGAN METODE ESIM

STUDI PERBANDINGAN PERHITUNGAN STABILITAS DINDING PENAHAN TANAH ANTARA METODE KONVENSIONAL DAN METODE ELEMEN HINGGA

ANALISA PERBEDAAN HARGA RAB DENGAN RAP UNTUK PEKERJAAN BETON BERTULANG PADA PROYEK ITC POLONIA MEDAN

ANALISIS DAN DESAIN STRUKTUR BAJA MENGGUNAKAN SISTEM RANGKA TERBREIS KONSENTRIS KHUSUS TIPE CHEVRON

TUGAS AKHIR. Diajukan guna melengkapi sebagian syarat Dalam mencapai gelar Sarjana Strata Satu (S1)

KUALITAS MIKROBIOLOGIS MAKANAN DAN SIKAP PENJAMAH MAKANAN TENTANG HIGIENE SANITASI PENGOLAHAN MAKANAN PADA KANTIN SEKOLAH DASAR DI WILAYAH

TUGAS AKHIR Diajukan sebagai salah satu syarat untuk memperoleh gelar Sarjana Teknik. Ade Kusnady

ANATOMI SENGKETA KONSTRUKSI PADA PROYEK BANGUNAN GEDUNG DI INDONESIA

SKRIPSI KAJIAN PENENTUAN SEGMEN JALAN BERDASARKAN Pd T B, AASHTO (1986), DAN THOMAS (2003)

PENERAPAN OHSAS 18001:2007 SEBAGAI PEMENUHAN STANDAR SISTEM MANAJEMEN KESELAMATAN DAN KESEHATAN KERJA PADA PERUSAHAAN KONTRAKTOR DI KOTA BANDUNG

PENGARUH TINGKAT PEMAHAMAN SEORANG MANAJER PROYEK KONSTRUKSI DARI ASPEK MANAJEMEN KUALITAS TERHADAP KINERJA WAKTU (Studi Kasus: PT.

LEMBAR PENGESAHAN TUGAS AKHIR

ANALISIS FAKTOR-FAKTOR PENYEBAB KONFLIK PADA PROYEK KONSTRUKSI

STUDI LABORATORIUM PENGARUH PENAMBAHAN KAPUR DAN BOTTOM ASH PADA TANAH EKSPANSIF TERHADAP NILAI CBR

Transkripsi:

SKRIPSI ANALISIS PRODUKTIVITAS PEKERJAAN PEMASANGAN RANGKA ATAP BAJA RINGAN ANTONIUS TRIANTO NPM : 2013410077 PEMBIMBING : Yohanes Lim Dwi Adianto, Ir., M.T. KO-PEMBIMBING : Adrian Firdaus, S.T., M.Sc. UNIVERSITAS KATOLIK PARAHYANGAN FAKULTAS TEKNIK PROGRAM STUDI TEKNIK SIPIL (Terakreditasi Berdasarkan SK BAN-PT Nomor: 227/BAN-PT/Ak-XVI/S/XI/2013) BANDUNG JUNI 2017

ANALISIS PRODUKTIVITAS PEKERJAAN PEMASANGAN RANGKA ATAP BAJA RINGAN Antonius Trianto NPM: 2013410077 Pembimbing : Yohanes Lim Dwi Adianto, Ir., M.T. Ko-Pembimbing : Adrian Firdaus, S.T., M.Sc. UNIVERSITAS KATOLIK PARAHYANGAN FAKULTAS TEKNIK PROGRAM STUDI TEKNIK SIPIL (Terakreditasi Berdasarkan SK BAN-PT Nomor: 227/SK/BAN-PT/Ak-XVI/S/XI/2013) BANDUNG JUNI 2017 ABSTRAK Baja ringan merupakan merupakan bahan yang semakin umum dan banyak digunakan dalam dunia konstruksi. Salah satu penggunaan baja ringan yang paling populer adalah sebagai material rangka atap. Untuk memastikan pekerjaan dapat terlaksana dengan efisien perlu diketahui nilai produktivitas supaya bisa dilakukan evaluasi mengenai pekerjaan tersebut dan juga penyusunan jadwal yang baik. Tetapi penelitian produktivitas rangka atap baja ringan belum dilakukan secara mendetail. Tujuan dilakukannya penelitian ini adalah untuk mencari nilai produktivitas dari pekerjaan pemasangan rangka atap baja ringan. Penelitian dilakukan dengan mencari nilai produktivitas dari data historis proyek-proyek yang telah selesai dari subkontraktor baja ringan. Selain itu dilakukan juga pengamatan langsung di lapangan pada proyek yang sedang berjalan. Berdasarkan hasil penelitian dari data historis didapatkan nilai produktivitas sebesar 7,355 m 2 /orang hari. Sedangkan dari pengamatan langsung didapatkan nilai produktivitas sebesar 9,821 m 2 / orang hari. Penurunan sebesar 25,11% ini disebabkan oleh tidak diperhitungkannnya jam kerja tidak efektif pada perhitungan nilai produktivitas dari data historis. Pada pengamatan langsung terdapat jam kerja tidak efektif yang cukup signifikan, antara lain saat menunggu datangnya baja ringan dan terhentinya pekerjaan akibat cuaca. Pada umumnya jam kerja efektif dalam 1 hari kerja pemasangan rangka atap baja ringan adalah sebanyak 5,24 jam / hari. Kata Kunci: Produktivitas, Baja Ringan, Rangka Atap i

PRODUCTIVITY ANALYSIS OF LIGHTWEIGHT STEEL ROOF TRUSS INSTALLATION Advisor Co-Advisor Antonius Trianto NPM: 2013410077 : Yohanes Lim Dwi Adianto, Ir., M.T. : Adrian Firdaus, S.T., M.Sc. PARAHYANGAN CATHOLIC UNIVERSITY FACULTY OF ENGINEERING DEPARTEMENT OF CIVIL ENGINEERING (Accreditated by SK BAN-PT Number: 227/SK/BAN-PT/Ak-XVI/S/XI/2013) BANDUNG JUNE 2017 ABSTRACT Lightweight steel is an increasingly common and widely used material in the construction world. One of the most popular uses of lightweight steel is as a roof truss material. To ensure the work can be done efficiently, the productivity value is needed to be known in order to evaluate the work and prepare an efficient schedule. However, studies of productivity analysis of lightweight steel roof truss have not been done in detail. The purpose of this research is to find the productivity value of lightweight steel roof truss. The study was conducted by researching the productivity value of completed projects from lightweight steel roof truss subcontractors. Furthermore, direct observation of ongoing project were also made. From the research of completed projects, the result of lightweight steel roof truss productivity value is 7.355 m 2 / manday. Whereas from direct observation, the productivity value is 9,821 m 2 / manday. This decrease of 25.11% is due to the ineffective working hours not taken into account in the research of historical data.. In direct observation there are some significant ineffective working hours, such as waiting for lightweight steel from factory and postponement of work due to weather. Generally, the effective working hours within 1 working day of installation of lightweight steel roof truss is 5,24 hours / day.. Keywords: Productivity, Lightweight Steel, Roof Truss iii

PRAKATA Puji syukur penulis panjatkan kepada Tuhan Yang Maha Esa atas berkat dan rahmat-nya sehingga penulis memperoleh kesempatan untuk menyusun dan menyelesaikan skripsi yang berjudul berjudul ANALISIS PRODUKTIVITAS PEKERJAAN PEMASANGAN RANGKA ATAP BAJA RINGAN tepat pada waktunya. Skripsi ini ditujukan untuk memenuhi penyelesaian studi program tingkat S-1 di Fakultas Teknik Program Studi Teknik Sipil, Universitas Katolik Parahyangan.. Selama penyusunan skrispi, banyak hambatan dan kendala yang penulis hadapi, tetapi berkat bimbingan, dorongan, dan bantuan dari berbagai pihak, maka hambatan-hambatan dapat diatasi. Oleh karena itu, penulis ingin mengucapkan terima kasih sebesar-besarnya kepada: 1. Bapak Yohanes Lim Dwi Adianto, Ir., M.T. selaku dosen pembimbing yang telah meluangkan waktu dan memberi banyak arahan, dukungan, dan ilmu pengetahuan pada penulis selama penyusunan skripsi, 2. Bapak Adrian Firdaus, S.T., M.Sc. selaku dosen ko-pembimbing yang telah memberikan waktu, tenaga, dan membagikan ilmu pengetahuan yang berguna bagi penulis dalam menyelesaikan skripsi ini dan dalam membimbing penulis, 3. Bapak Andreas Franskie Van Roy, S.T., M.T., Ph.D, Ibu Theresita Herni Setiawan, Ir., MT., Bapak Dr. Anton Soekiman, Ir., M.T., Bapak Dr. Felix Hidayat, S.T., MT., Bapak Zulkifli B. Sitompul, Ir., MT., Bapak Tjia A. Iwan Irawan, Ir., M.T., dan Ibu Dr. Eng. Mia Wimala Soejoso, ST., MT. selaku dosen pengajar Kelompok Bidang Ilmu Manajemen dan Rekayasa Konstruksi yang telah memberikan saran dan kritik kepada penulis sehingga skripsi ini dapat diselesaikan dengan lebih baik, 4. Seluruh Dosen dan Staf Program Studi Teknik Sipil Fakultas Teknik Universitas Katolik Parahyangan yang telah membantu penulis selama proses perkuliahan, v

DAFTAR ISI ABSTRAK... i ABSTRACT... iii PRAKATA... v DAFTAR ISI... vii DAFTAR NOTASI DAN SINGKATAN... xi DAFTAR GAMBAR... xiii DAFTAR TABEL... xv DAFTAR LAMPIRAN... xvii BAB 1 PENDAHULUAN... 1-1 1.1 Latar Belakang... 1-1 1.2 Inti Permasalahan... 1-2 1.3 Tujuan Penelitian... 1-2 1.4 Pembatasan Masalah... 1-2 1.5 Manfaat Penelitian... 1-2 1.6 Sistematika Penulisan... 1-3 BAB 2 TINJAUAN PUSTAKA... 2-1 2.1 Produktivitas... 2-1 2.1.1 Definisi Produktivitas... 2-1 2.1.2 Faktor-Faktor yang Mempengaruhi Produktivitas... 2-2 2.2 Atap... 2-6 2.2.1 Atap Pelana... 2-6 2.2.2 Atap Perisai... 2-7 2.2.3 Atap Sandar... 2-8 2.2.4 Atap Tenda... 2-8 2.2.5 Atap Joglo... 2-9 2.3 Baja... 2-9 2.3.1 Jenis-jenis Baja... 2-9 2.3.2 Keuntungan dan Kerugian Rangka Atap Baja Ringan... 2-11 2.3.3 Tipe-tipe batang struktur baja dan penyambungnya... 2-12 2.3.4 Tahapan Pekerjaan... 2-13 2.4 Metode Pengumpulan Data... 2-14 vii

2.5 Analisis Data... 2-14 2.5.1 Penentuan Tingkat Ketelitian dan Tingkat Keyakinan... 2-15 2.5.2 Uji Keseragaman Data... 2-15 2.5.3 Uji Kecukupan Data... 2-17 2.5.4 Perhitungan Produktivitas... 2-17 BAB 3 METODOLOGI PENELITIAN... 3-1 3.1 Kerangka Penelitian... 3-1 3.2 Pengumpulan Data... 3-3 3.2.1 Data Proyek... 3-3 3.2.2 Pekerjaan Pemasangan Rangka Atap Baja Ringan... 3-5 3.3 Pemilahan Data... 3-9 3.4 Perhitungan Nilai Produktivitas... 3-11 BAB 4 ANALISIS DAN PEMBAHASAN... 4-1 4.1 Analisis Produktivitas Pemasangan Rangka Atap Baja Ringan... PT. Cahaya Benteng Mas... 4-1 4.1.1 Uji Keseragaman Data... 4-2 4.1.2 Uji Kecukupan Data... 4-5 4.1.3 Perhitungan Produktivitas Pemasangan Rangka Atap... Baja Ringan... 4-6 4.2 Analisis Produktivitas Pemasangan Rangka Atap Baja Ringan... PT. Setra Adhi Surya... 4-7 4.2.1 Uji Keseragaman Data... 4-8 4.2.2 Uji Kecukupan Data... 4-11 4.2.3 Perhitungan Produktivitas Pemasangan Rangka Atap... Baja Ringan... 4-13 4.3 Analisis Produktivitas Pemasangan Rangka Atap Baja Ringan... PT. Eka Karya Graha... 4-13 4.3.1 Uji Keseragaman Data... 4-15 4.3.2 Uji Kecukupan Data... 4-17 4.3.3 Perhitungan Produktivitas Pemasangan Rangka Atap... Baja Ringan... 4-19 4.4 Analisis Produktivitas Pemasangan Rangka Atap Baja Ringan Keseluruhan... 4-19 4.4.1 Uji Keseragaman Data... 4-22 4.4.2 Uji Kecukupan Data... 4-27 viii

4.4.3 Perhitungan Produktivitas Pemasangan Rangka Atap... Baja Ringan... 4-29 4.5 Analisis Produktivitas Data Primer... 4-29 4.5.1 Pengamatan Rangka Atap Baja Ringan Dengan Bentang 8m... 4-30 4.5.2 Pengamatan Rangka Atap Baja Ringan Dengan Bentang 10m... 4-30 4.5.3 Pengamatan Rangka Atap Baja Ringan Keseluruhan... 4-31 4.6 Pembahasan Hasil Produktivitas Pemasangan Rangka Atap... Baja Ringan... 4-32 BAB 5 SIMPULAN DAN SARAN... 5-1 5.1 Simpulan... 5-1 5.2 Saran... 5-1 DAFTAR PUSTAKA... xvii ix

DAFTAR NOTASI DAN SINGKATAN x = Nilai rata rata x = Data pengamatan σ = Standar deviasi BKA = Batas kendali atas BKB = Batas kendali bawah k = Tingkat keyakinan N = Jumlah data aktual N = Jumlah data yang dibutuhkan k = Tingkat keyakinan s = Derajat ketelitian xi

DAFTAR GAMBAR Gambar 2.1 Atap Pelana... 2-6 Gambar 2.2 Atap Perisai... 2-7 Gambar 2.3 Atap Sandar... 2-8 Gambar 2.4 Atap Tenda... 2-8 Gambar 2.5 Atap Joglo... 2-9 Gambar 2.6 Jenis-Jenis Baja Proses Canai Panas... 2-10 Gambar 2.7 Jenis-Jenis Baja Proses Bentukan Dingin... 2-11 Gambar 2.8 Profil C Baja Ringan... 2-12 Gambar 2.9 Profil Reng Baja Ringan... 2-12 Gambar 2.10 Self Drilling Screw... 2-13 Gambar 3.1 Diagram Alir Kerangka Penelitian... 3-1 Gambar 3 2 Mobilisasi Baja Ringan... 3-6 Gambar 3.3 Perakitan Struktur Kuda-Kuda... 3-6 Gambar 3.4 Pemasangan Struktur Kuda-Kuda... 3-7 Gambar 3.5 Pemasangan Bracing... 3-7 Gambar 3.6 Pemasangan Reng... 3-8 Gambar 3.7 Diagram Alir Pemilahan Data... 3-10 xiii

DAFTAR TABEL Tabel 3.1 Data Proyek... 3-4 Tabel 3.2 Data Pengamatan Langsung... 3-8 Tabel 4.1 Perhitungan Berat Rangka Atap dan Produktivitas PT. Cahaya Benteng Mas... 4-2 Tabel 4.2 Uji Keseragaman Berat Rangka Atap Pertama... 4-3 Tabel 4.3 Tahapan Uji Keseragaman Berat Rangka Atap... 4-4 Tabel 4.4 Uji Keseragaman Produktivitas Pertama... 4-4 Tabel 4.5 Tahapan Uji Keseragaman Produktivitas... 4-5 Tabel 4.6 Uji Kecukupan Data... 4-5 Tabel 4.7 Perhitungan Berat Rangka Atap dan Produktivitas... PT. Setra Adhi Surya... 4-8 Tabel 4.8 Uji Keseragaman Berat Rangka Atap Pertama... 4-9 Tabel 4.9 Tahapan Uji Keseragaman Berat Rangka Atap... 4-10 Tabel 4.10 Uji Keseragaman Produktivitas Pertama... 4-10 Tabel 4.11 Tahapan Uji Keseragaman Produktivitas... 4-11 Tabel 4.12 Uji Kecukupan Data... 4-12 Tabel 4.13 Perhitungan Berat Rangka Atap dan Produktivitas PT. Eka Karya Graha... 4-14 Tabel 4.14 Uji Keseragaman Berat Rangka Atap Pertama... 4-15 Tabel 4.15 Tahapan Uji Keseragaman Berat Rangka Atap... 4-16 Tabel 4.16 Uji Keseragaman Produktivitas Pertama... 4-16 Tabel 4.17 Tahapan Uji Keseragaman Produktivitas... 4-17 Tabel 4.18 Uji Kecukupan Data... 4-18 Tabel 4.19 Perhitungan Berat Rangka Atap dan Produktivitas Keseluruhan... 4-20 Tabel 4.20 Uji Keseragaman Berat Rangka Atap Pertama... 4-22 Tabel 4.21 Tahapan Uji Keseragaman Berat Rangka Atap... 4-24 Tabel 4.22 Uji Keseragaman Produktivitas Pertama... 4-25 Tabel 4.23 Tahapan Uji Keseragaman Produktivitas... 4-27 Tabel 4.24 Uji Kecukupan Data... 4-27 xv

DAFTAR LAMPIRAN Lampiran 1 Lampiran 2 Lampiran 3 Data Pengamatan Detail Rangka Atap Perhitungan Uji Keseragaman xvii

BAB 1 PENDAHULUAN 1.1 Latar Belakang Perkembangan teknologi yang terus-menerus terjadi akan mempengaruhi berbagai bidang pekerjaan, termasuk juga di dalam bidang konstruksi. Dalam proyek konstruksi penemuan-penemuan baru dapat membuat proses pembangunan menjadi lebih efisien dan menguntungkan. Material baja ringan adalah salah satu contoh inovasi dalam bidang pembangunan. Penggunaan material baja ringan pada pembangunan di Indonesia pun terus bertumbuh dari tahun ke tahun. Baja ringan menjadi bahan yang umum dan populer dalam proyek konstruksi, salah satunya sebagai bahan rangka atap pengganti kayu atau baja konvensional. Menurut Presiden Direktur PT. NS BlueScope Indonesia Simon Linge, permintaan nasional baja ringan diestimasi 1,3 juta ton per tahun. Selain itu angka pertumbuhan pasar baja ringan berada pada kisaran 5 persen. Hal ini menyebabkan semakin banyaknya produsen dan sub kontraktor baja ringan di Indonesia. Dengan semakin banyaknya penggunaan material baja ringan, dibutuhkan manajemen yang baik untuk memastikan pekerjaan tetap efisien dan efektif. Mengetahui nilai produktivitas merupakan salah satu kunci dari manajemen pekerjaan yang efektif. Dalam menentukan produktivitas suatu pekerjaan, salah satu acuan yang biasa digunakan di Indonesia adalah Standar Nasional Indonesia (SNI). Akan tetapi, belum semua jenis pekerjaan telah diteliti dan tercantum pada Standar Nasional Indonesia (SNI), termasuk salah satunya adalah pekerjaan pemasangan rangka atap baja ringan. Tanpa diketahuinya nilai produktivitas, pemasangan rangka atap baja ringan dapat menyulitkan pihak pemilik dan kontraktor dalam penyusunan jadwal serta dalam memastikan efisiensi pekerjaan tersebut. Dalam skripsi ini akan dilakukan penelitian mengenai produktivitas pekerjaan pemasangan rangka atap baja ringan. Nilai produktivitas ini akan menjadi masukan bagi para pelaku pekerjaan konstruksi atap baja ringan dalam persiapan dan pelaksanaan pekerjaan yang terkait. 1-1

1-2 1.2 Inti Permasalahan Untuk menentukan durasi dan manajemen pekerjaan yang efektif dibutuhkan nilai produktivitas pekerjaan tersebut. Standar Nasional Indonesia (SNI) sebagai acuan yang biasa digunakan belum mencakup secara detil pekerjaan pemasangan rangka atap baja ringan. Diperlukan pencarian nilai produktivitas pemasangan rangka atap baja ringan untuk menjadi alat kontrol dan evaluasi pekerjaan tersebut. 1.3 Tujuan Penelitian Tujuan penelitian dari skripsi ini adalah : 1. Mencari nilai produktivitas pekerjaan pemasangan rangka atap baja ringan 2. Membandingkan antara nilai produktivitas pekerjaan pemasangan rangka atap baja ringan dari data historis dengan pengamatan langsung. 1.4 Pembatasan Masalah Pembatasan masalah dari penulisan ini adalah : 1. Data yang digunakan adalah data primer dari pengamatan langsung di lapangan dan data sekunder yang didapat dari sub kontraktor baja ringan PT. Cahaya Benteng Mas, PT. Setra Adhi Surya, PT. Eka Karya Graha. 2. Pengamatan hanya pada pekerjaaan pemasangan saja, proses pabrikasi dan mobilisasi material tidak diperhitungkan. 3. Pekerjaan yang ditinjau adalah pekerjaan pemasangan rangka atap baja ringan dengan jenis pelana. 1.5 Manfaat Penelitian Dari penelitian ini manfaat yang bisa didapat antara lain : 1. Bagi subkontraktor baja ringan, sebagai bahan masukan dalam upaya meningkatkan produktivitas pekerjaan pemasangan rangka atap baja ringan dan juga sebagai evaluasi atas pekerjaan yang telah berjalan. 2. Bagi penulis, sebagai sarana untuk menambah ilmu dalam bidang manajemen dan rekayasa konstruksi, khususnya mengenai produktivitas dan pekerjaan pemasangan rangka atap baja ringan.

1-3 3. Bagi peneliti selanjutnya, sebagai referensi dan bahan perbandingan apabila ingin melakukan penelitian sejenis mengenai produktvitas pekerjaan pemasangan rangka atap baja ringan di masa depan. 1.6 Sistematika Penulisan Sistematika penulisan skripsi ini terdiri dari 5 tahapan yaitu : BAB 1 PENDAHULUAN Bab ini berisi mengenai latar belakang penelitian, inti permasalahan, tujuan penelitian, pembatasan masalah, manfaat penelitian, dan sistematika penulisan BAB 2 TINJAUAN PUSTAKA Bab ini menjelaskan teori mengenai produktivitas, baja ringan, rangka atap baja ringan, dan metode pengolahan data BAB 3 METODOLOGI PENELITIAN Bab ini berisi tentang metodologi penelitian, cara pengumpulan data, langkahlangkah analisis data, dan penguraian data BAB 4 ANALISIS DAN PEMBAHASAN Bab ini membahas tentang analisis perhitungan produktivitas pemasangan rangka atap baja ringan BAB 5 SIMPULAN DAN SARAN Bab ini menjelaskan tentang simpulan dan saran dari penulis berdasarkan penelitian yang telah dilakukan