EVALUASI PELAKSANAAN PROYEK PEMBANGUNAN RUANG KELAS MIN TIRAK DENGAN METODE NILAI HASIL

Ukuran: px
Mulai penontonan dengan halaman:

Download "EVALUASI PELAKSANAAN PROYEK PEMBANGUNAN RUANG KELAS MIN TIRAK DENGAN METODE NILAI HASIL"

Transkripsi

1 EVALUASI PELAKSANAAN PROYEK PEMBANGUNAN RUANG KELAS MIN TIRAK DENGAN METODE NILAI HASIL Lyya Supriono * Staf Pengajar Fakultas Teknik Universitas Merdeka Madiun Abstract There are many constraint in every construction project occur in finishing process, because of that, it needs to held weekly evaluation to see the working process, is it getting delay or fast. By the evaluation we can know the constraint early so it can be done the anticipation in well. The method uses to evaluated construction project the new class room in MIN Tirak is result value method. From the evaluation it can be concludes that the project has benefit by the benefitial Rp ,00. The value of SPI=1 so the project run as the schedule planed or can be said on schedule. Key word:, project evaluation, time, value result method PENDAHULUAN 1. Latar Belakang Pembangunan dibidang kontruksi antara satu proyek dengan proyek yang lain memiliki kendala yang berbeda. Begitu pula dengan proyek pembangunan Ruang kelas MIN tirak tak lepas dari kendala dan resiko yang harus dihadapi. Setiap kendala dan hambatan tentunya akan sangat berpengaruh terhadap kelangsungan pelaksanaan proyek tersebut. Untuk mengatisipasi hal tersebut maka perlu dilakukan evaluasi disetiap minggu atau bulannya agar terpantau apakah suatu pekerjaan mengalami keterlambatan atau percepatan. Waktu pelaksanaan tentu akan mempengaruhi biaya. Semakin lama pelaksanaan tentunya akan semakin banyak dana yang harus dikeluarkan. Untuk mengontrol penggunaan dana maka dengan itu dilakukan evaluasi yang berhubungnan dengan waktu dan biaya dengan metode nilai hasil. Metode nilai hasil adalah memiliki beberapa indicator diantaranya adalah ACWP, BCWP dan BCWS. 2. Rumusan Masalah Yang menjadi rumusan masalah dalam a. Apakah proyek menguntungkan? b. Berapa lama waktu penyelesaian proyek? 3. Tujuan Yang menjadi tujuan masalah dalam a. Untuk mengetahui proyek mengun tungkan atau tidak. b. Untuk mengetahui waktu penyelesaian proyek. PILAR TEKNOLOGI: Jurnal Ilmiah Ilmu-ilmu Teknik Volume 1 Nomor 1 Maret 2016; ISSN :

2 Lyya Supriono 4. Batasan Masalah Yang menjadi batasan masalah dalam a. Obyek yang dijadikan penelitian adalah pembangunan ruang kelas MIN Tirak. b. Melakukan analisis hanya pada waktu dan biaya dengan metode nilai hasil. LANDASAN TEORI 1. Manajemen Proyek Manajemen Proyek adalah kegiatan merencanakan, mengorganisasikan, meng arahkan dan mengendalikan sumberdaya organisasi perusahaan untuk mencapi tujuan tertentu dalam waktu tertentu dengan sumber daya tertentu (Budi Santoso, 1997). 2. Metode Nilai Hasil Metode yang berfungsi untuk mengendalikan waktu dan biaya pelaksanaan kontruksi. Metode ini dapat memberikan gambaran nilai akhir biaya yang harus dikeluarkan dan waktu penyelesaian proyek. a. Biaya Aktual Actual Cost of Work Perform (ACWP) yaitu Variabel yang menyatakan pengeluaran actual dari pekerjaan yang sudah dikerjakan sampai waktu tertentu b. Nilai Hasil Bugdeted Cost of Work Performanced (BCWP) Variabel yang menyatakan jumlah biaya yang dikeluarkan untuk pekerjaan yang sudah dikerjakan. c. Jadwal Anggaran Budgeted Cost of Work Schedule (BCWS) yaitu variable yang menyatakan besarnya biaya yang dianggarkan untuk pekerjaan yang dijadwalkan untuk satu periode tertentu dan ditetapkan dalam anggaran d. Varians Biaya dan Jadwal Terpadu Varians Biaya/Cost Varians (CV) dan Varians Jadwal/Schedule Varians (SV) menurut Iman Suharto, 1997., Dirumuskan sebagai Varians Biaya(CV)=BCWP ACWP(2.1) Varians Jadwal(SV)= CWP BCWS( 2.2) Kriteria untuk kedua indikator tersebut diatas baik itu CV (Cost Varians) maupun SV (Schedule Varians) ditabelkan oleh Iman Soeharto seperti tersebut dibawah ini: Tabel 2.1 Analisa Varians Terpadu CV SV Indikasi On schedule, on On schedule, under On schedule, over Sumber: Iman Suharto, 1997:273 A head schedule, on A head schedule, under A head schedule, over Behind schedule, on Behind schedule, under Behind schedule, over e. Indeks Produktivitas dan Kinerja Indek kinerja biaya dan waktu menggunakan rumus sebagai Indeks Kinerja Biaya (2.3) 18 PILAR TEKNOLOGI, Volume 1 Nomor 1 Maret 2016

3 Evaluasi Pelaksanaan Proyek Pembangunan Ruang Kelas Indeks Kinerja Jadwal (2.4) f. Perkiraan waktu dan biaya penyelesaian proyek Perkiraan waktu dan biaya dicari dengan dengan rumus sebagai (2.5) (2.6) Kurva S Kurva S berisi tentang progres pekerjaan yang telah dicapai selama pekerjaan kontruksi berlangsung. Kurva S merupakan cara termudah untuk melihat kemajuan suatu pekerjaan. METODE PENELITIAN 1. Metode Penelitian Jenis metode yang dipergunakan dalam penelitian ini adalah deskritif kuantitatif yaitu mempergunakan data yang terukur. Sedangkan deskritif yaitu dengan memberikan penjelasan tentang masalah yang terkait dengan hasil pengolahan data. 2. Pengumpulan Data Pengumpulan data dari pihak pengawas berupa rencana anggran biaya, Laporan mingguan, laporan bulanan, schedule dan data akuntansi proyek MIN Tirak. 3 Teknik Pengumpulan Data Memperoleh data laporan mingguan, bulanan dan Schedule dari konsultan pengawas 4. Tahap dan Prosedur Penelitia a. Studi literature b. Mengitung ACWP, BCWP, BCWS c. Menghitung CV,SV, CPI, SPI, ETC d. Menghitung EAC e. Pembahasan f. Kesimpulan g. Saran PEMBAHASAN Waktu pelaksanaan proyek maksimal hingga 12 minggu. Jika melebihi batas waktu yang telah ditentukan maka akan ada sangksi yang diberikan kepada kontraktor. Untuk itu dilakukan evaluasi dengan metode nilai hasil. Dengan indicator yang ada maka diperoleh hasil sebagai 4.1 Tabel perhitungan BCWP MGG BCWP BCWP Kom BCWP diperoleh Rp , Tabel perhitungan BCWS MGG BCWS BCWS Kom Volume 1 Nomor 1 Maret 2016, PILAR TEKNOLOGI 19

4 Lyya Supriono MGG BCWS BCWS Kom BCWP diperoleh Rp , Tabel perhitungan ACWP MGG ACWP ACWP Kom ACWP diperoleh Rp , Tabel Rekapitulasi Nilai SPI, CPI MINGGU KE CPI SPI 1 0,92 1,1 2 1,22 1,8 3 1,16 1,4 MINGGU KE CPI SPI 4 1,15 1,4 5 1,13 1,4 6 1,11 1,1 7 1,16 1,4 8 1,14 1,5 9 1,13 1,4 10 1,11 1,3 11 1,12 1,1 12 1,04 1,0 Idek kinerja Biaya pada minggu pertama pengeluran lebih besar dari rencana, sedangkan pada minggu berikutnya hingga minggu ke dua belas pengeluaran lebih kecil dari anggaran yang telah ditentukan. Sedangkan untuk indek kinerja waktu menunjukan bahwa pengerjaan lebih cepat dari rencana dari minggu pertama hingga minggu ke sebelas. Sedangkan minggu ke dua belas tepat sesuai dengan schedule rencana 4.5. Tabel Rekapitulasi Nilai CV, SV CV SV PILAR TEKNOLOGI, Volume 1 Nomor 1 Maret 2016

5 Evaluasi Pelaksanaan Proyek Pembangunan Ruang Kelas Pada minggu pertama pekerjaan selesai lebih cepat dari pada rencana dengan menelan biaya di atas anggaran., sedangkan pada minggu ke dua hingga minggu ke sebelas pekerjaaan terlaksana lebih cepat dari pada jadwal dengan biaya lebih kecil dari pada anggaran, untuk minggu ke dua belas pekerjaan selesai lebih lambat dan menelan biaya yang lebih kecil Tabel Rekapitulasi Nilai ETC, EAC ETC EAC Nilai Perkiraan biaya hingga akhir sebesar Rp ,00 KESIMPULAN DAN SARAN 1. Kesimpulan Hasil dari analisis data diatas dapat disimpulkan bahwa: a. Biaya yang harus dikeluaarkan hingga akhir pekerjaan adalah Rp , b. SPI sama dengan satu menunjukkan bahwa penyelesaian proyek on schedule 2. Saran Agar pengendalian dapat berjalan secara efektif maka tidak hanya dibutuhkan manajemen yang baik tapi juga membutuhkan tenaga ahli yang harus dipersiapkan DAFTAR PUSTAKA Karnila, Analisis Nilai Hasil Terhadap Biaya pada Proyek Kontruksi (Studi kasus Pada Proyek Pembangunan Gedung Perkuliahan Fispol Universitas Gajah Mada Yogyakarta. M. Fauzan Mawardi. Evaluasi Kemajuan Proyek Dengan Metode Nilai Hasil Proses Pengendalian Kinerja Waktu dan Biaya Santoso Budi, Manajemen Proyek, Guna darma, Surabaya. Suharto, Iman, (1995), Manajemen Proyek : Dari Konseptual sampai Operasional, Erlangga, Jakarta. Simanjuntak P., Gray C.,dkk, Pengantar Evaluasi Proyek. Jilid II, Penerbit Gramedia Pustaka, Jakarta. Soedrajat, Sastramadja Analisa (Cara Modern) Anggaran Biaya Pelaksanaan, Penerbit Nova, Bandung. Tarore H., Analisis Sistem Rekayasa Konstruksi (ASREKO). Sam Ratulangi University Press, Manado. Yohanes L.D. Adianto, Ali Maliki, Wisnu Prasetyo. Analisis Biaya dan Waktu Optimal pada Proyek Ruko Paskal Hypersquare dengan Least Cost Scheduling. Volume 14, No. 1 Edisi XXXIV Pebruari Volume 1 Nomor 1 Maret 2016, PILAR TEKNOLOGI 21

KAJIAN EKONOMI PROYEK PENGADAAN DAN PERBAIKAN TULISAN ALUN-ALUN KABUPATEN NGAWI

KAJIAN EKONOMI PROYEK PENGADAAN DAN PERBAIKAN TULISAN ALUN-ALUN KABUPATEN NGAWI KAJIAN EKONOMI PROYEK PENGADAAN DAN PERBAIKAN TULISAN ALUN-ALUN KABUPATEN NGAWI Laily Fatmawati 1) 1) Staf Pengajar Fakultas Teknik Universitas Merdeka Madiun, email : laily.fatmawati@gmail.com ABSTRACT

Lebih terperinci

DAFTAR ISI HALAMAN JUDUL LEMBAR PENGESAHAN LEMBAR PERSETUJUAN KATA PENGANTAR DAFTAR TABEL DAFTAR GAMBAR DAFTAR NOTASI DAN ISTILAH ABSTRAK

DAFTAR ISI HALAMAN JUDUL LEMBAR PENGESAHAN LEMBAR PERSETUJUAN KATA PENGANTAR DAFTAR TABEL DAFTAR GAMBAR DAFTAR NOTASI DAN ISTILAH ABSTRAK DAFTAR ISI HALAMAN JUDUL i LEMBAR PENGESAHAN ii LEMBAR PERSETUJUAN iii MOTTO iv KATA PENGANTAR v DAFTAR ISI viii DAFTAR TABEL xii DAFTAR GAMBAR xiii DAFTAR NOTASI DAN ISTILAH xiv ABSTRAK xv ABSTRACT xvi

Lebih terperinci

ANALISIS NILAI HASIL TERHADAP BIAYA PADA PROYEK KONSTRUKSI (STUDI KASUS PADA PROYEK PEMBANGUNAN HOTEL EASTPARC YOGYAKARTA)

ANALISIS NILAI HASIL TERHADAP BIAYA PADA PROYEK KONSTRUKSI (STUDI KASUS PADA PROYEK PEMBANGUNAN HOTEL EASTPARC YOGYAKARTA) ANALISIS NILAI HASIL TERHADAP BIAYA PADA PROYEK KONSTRUKSI (STUDI KASUS PADA PROYEK PEMBANGUNAN HOTEL EASTPARC YOGYAKARTA) Agus Marhaendra 1), Siti Qomariyah 2) 1) Fakultas Teknik, Jurusan Teknik Sipil,

Lebih terperinci

BAB III METODOLOGI PENELITIAN

BAB III METODOLOGI PENELITIAN BAB III METODOLOGI PENELITIAN 3.1 TAHAPAN METODOLOGI PENELITIAN 3.1.1 Diagram Alir Tahapan Penulisan Tugas Akhir MULAI Survei Literatur Identifikasi Masalah Studi Pustaka Pengumpulan Data b. Jadwal Pelaksanaan

Lebih terperinci

Pertemuan ke 13 KONSEP NILAI HASIL

Pertemuan ke 13 KONSEP NILAI HASIL Halaman 1 dari Pertemuan ke - 13 Pertemuan ke 13 KONSEP NILAI HASIL 13.1 Pengertian Konsep Nilai Hasil Konsep nilai hasil adalah konsep menghitung besarnya biaya yang sesuai dengan pekerjaan yang telah

Lebih terperinci

PENGENDALIAN PROYEK PEMBANGUNAN LANJUTAN SMA NEGERI INTERNASIONAL SUMATERA SELATAN PALEMBANG DENGAN METODE EARNED VALUE

PENGENDALIAN PROYEK PEMBANGUNAN LANJUTAN SMA NEGERI INTERNASIONAL SUMATERA SELATAN PALEMBANG DENGAN METODE EARNED VALUE PENGENDALIAN PROYEK PEMBANGUNAN LANJUTAN SMA NEGERI INTERNASIONAL SUMATERA SELATAN PALEMBANG DENGAN METODE EARNED VALUE Gusti Rahma Dini 1*, Ika Juliantina 2 1,2 Jurusan Teknik Sipil Fakultas Teknik Universitas

Lebih terperinci

BAB V ANALISIS, HASIL DAN PEMBAHASAN

BAB V ANALISIS, HASIL DAN PEMBAHASAN BAB V ANALISIS, HASIL DAN PEMBAHASAN 5.1 GAMBARAN UMUM PROYEK Dalam rangka meningkatkan efisiensi dan efektifitas kerja diperlukan adanya sarana dan prasarana yang memadai. Untuk ini telah telah diupayakan

Lebih terperinci

ANALISIS PENGENDALIAN BIAYA DAN WAKTU DENGAN METODE KONSEP NILAI HASIL PADA PROYEK PEMBANGUNAN PASAR PRAMBANAN KABUPATEN SLEMAN ABSTRAK

ANALISIS PENGENDALIAN BIAYA DAN WAKTU DENGAN METODE KONSEP NILAI HASIL PADA PROYEK PEMBANGUNAN PASAR PRAMBANAN KABUPATEN SLEMAN ABSTRAK ANALISIS PENGENDALIAN BIAYA DAN WAKTU DENGAN METODE KONSEP NILAI HASIL PADA PROYEK PEMBANGUNAN PASAR PRAMBANAN KABUPATEN SLEMAN Hasta Mufti Satriawan Fakultas Teknik Sipil dan Perencanaan, Jurusan Teknik

Lebih terperinci

Spektrum Sipil, ISSN Vol. 2, No. 2 : , September 2015

Spektrum Sipil, ISSN Vol. 2, No. 2 : , September 2015 Spektrum Sipil, ISSN 1858-4896 125 Vol. 2, No. 2 : 125-136, September 2015 PENGENDALIAN BIAYA DAN WAKTU PADA PROYEK PEMBANGUNAN GEDUNG J (IRMA UTAMA) RSU PROVINSI NTB MENGGUNAKAN METODE EARNED VALUE Cost

Lebih terperinci

BAB II TINJAUAN PUSTAKA

BAB II TINJAUAN PUSTAKA DAFTAR ISI ABSTRAK... UCAPAN TERIMAKASIH... DAFTAR ISI... DAFTAR GAMBAR... DAFTAR TABEL... DAFTAR NOTASI... i ii iii iv v vi BAB I PENDAHULUAN... 1 1.1 Latar Belakang... 1 1.2 Rumusan Masalah... 3 1.3

Lebih terperinci

BAB III METODOLOGI PENELITIAN

BAB III METODOLOGI PENELITIAN BAB III METODOLOGI PENELITIAN 3.1 Definisi Konsep dan Operasional 3.1.1 Definisi Konsep Pengendalian adalah usaha yang sistematis untuk menentukan standar yang sesuai dengan sasaran perencanaan, merancang

Lebih terperinci

EVALUASI PENGENDALIAN WAKTU DAN BIAYA PROYEK PEMBANGUNAN RUMAH KOST DUA LANTAI DI KEPUTIH TEGAL TIMUR SURABAYA. I Komang Kerthajaya

EVALUASI PENGENDALIAN WAKTU DAN BIAYA PROYEK PEMBANGUNAN RUMAH KOST DUA LANTAI DI KEPUTIH TEGAL TIMUR SURABAYA. I Komang Kerthajaya EXTRAPOLASI Jurnal Teknik Sipil Untag Surabaya P-ISSN: 1693-8259 Juli 2014, Vol. 7 No. 1, hal. 53-62 EVALUASI PENGENDALIAN WAKTU DAN BIAYA PROYEK PEMBANGUNAN RUMAH KOST DUA LANTAI DI KEPUTIH TEGAL TIMUR

Lebih terperinci

EVALUASI KINERJA KONTRAKTOR PADA PENGENDALIAN KONSTRUKSI DI LAPANGAN DALAM SUATU PROYEK RENOVASI DI PERUSAHAAN FARMASI DI BANDUNG

EVALUASI KINERJA KONTRAKTOR PADA PENGENDALIAN KONSTRUKSI DI LAPANGAN DALAM SUATU PROYEK RENOVASI DI PERUSAHAAN FARMASI DI BANDUNG EVALUASI KINERJA KONTRAKTOR PADA PENGENDALIAN KONSTRUKSI DI LAPANGAN DALAM SUATU PROYEK RENOVASI DI PERUSAHAAN FARMASI DI BANDUNG Yobeth Patu Sibilang NRP : 9321104 NIRM: 41077011930329 Pembimbing : Ir.

Lebih terperinci

Pandu Sugoro, M. Hamzah Hasyim, dan Saifoe El Unas

Pandu Sugoro, M. Hamzah Hasyim, dan Saifoe El Unas MONITORING PADA PEMBANGUNAN PROYEK TERMINAL PENUMPANG KABUPATEN BARRU SULAWESI SELATAN DENGAN METODE KONSEP NILAI HASIL DIKONVERSIKAN TERHADAP KURVA S. Pandu Sugoro, M. Hamzah Hasyim, dan Saifoe El Unas

Lebih terperinci

EVALUASI PENGENDALIAN BIAYA DAN WAKTU DENGAN MENGGUNAKAN METODE EARNED VALUE PADA PROYEK STUDENT BOARDING HOUSE PRESIDENT UNIVERSITY

EVALUASI PENGENDALIAN BIAYA DAN WAKTU DENGAN MENGGUNAKAN METODE EARNED VALUE PADA PROYEK STUDENT BOARDING HOUSE PRESIDENT UNIVERSITY Prosiding SNaPP2011 Sains, Teknologi, dan Kesehatan ISSN:2089-3582 EVALUASI PENGENDALIAN BIAYA DAN WAKTU DENGAN MENGGUNAKAN METODE EARNED VALUE PADA PROYEK STUDENT BOARDING HOUSE PRESIDENT UNIVERSITY 1

Lebih terperinci

REGITRA DESKA FEBRI NPM

REGITRA DESKA FEBRI NPM Analisis Kinerja Biaya dan Waktu Dengan Metode Nilai Hasil (Earned Value Analysis) Pada Pekerjaan Renovasi Tahap II Asrama Wana Mulia SMK Kehutanan Samarinda NASKAH PUBLIKASI Diajukan Oleh: EKA REGITRA

Lebih terperinci

BAB III METODE PENELITIAN

BAB III METODE PENELITIAN BAB III METODE PENELITIAN 3.1 Bagan Alur (Flowchart) Metode Penelitian Bagan alur (flowchart) metode penelitian proses pembuatan Sistem Informasi Pengendalian Proyek, dengan Menggunakan Analisa Nilai Hasil

Lebih terperinci

EARNED VALUE ANALYSIS TERHADAP BIAYA DAN WAKTU PADA PROYEK KONSTRUKSI (Studi Kasus Proyek Pembangunan Sarana/Prasarana Pengamanan Pantai)

EARNED VALUE ANALYSIS TERHADAP BIAYA DAN WAKTU PADA PROYEK KONSTRUKSI (Studi Kasus Proyek Pembangunan Sarana/Prasarana Pengamanan Pantai) EARNED VALUE ANALYSIS TERHADAP BIAYA DAN WAKTU PADA PROYEK KONSTRUKSI (Studi Kasus Proyek Pembangunan Sarana/Prasarana Pengamanan Pantai) Indri Meliasari 1, M. Indrayadi 2, Lusiana 2 Abstrak Perencanaan

Lebih terperinci

3.2.1 Prosedur Pembuatan Progres Biaya dan Waktu Proyek yang. Adapun prosedur pembuatan progres biaya dan waktu untuk

3.2.1 Prosedur Pembuatan Progres Biaya dan Waktu Proyek yang. Adapun prosedur pembuatan progres biaya dan waktu untuk 30 3.2 Analisis sistem yang Sedang Berjalan 3.2.1 Prosedur Pembuatan Progres Biaya dan Waktu Proyek yang Sedang Berjalan Adapun prosedur pembuatan progres biaya dan waktu untuk mengendalikan sebuah proyek

Lebih terperinci

EVALUASI PELAKSANAAN PROYEK MENGGUNAKAN METODE EARNED VALUE ANALYSIS

EVALUASI PELAKSANAAN PROYEK MENGGUNAKAN METODE EARNED VALUE ANALYSIS EVALUASI PELAKSANAAN PROYEK MENGGUNAKAN METODE EARNED VALUE ANALYSIS Triono Agung Dumadi 1, Sri Sunarjono 2, Muh. Nur Sahid 2 1 Mahasiswa Magister Teknik Sipil, Sekolah Pascasarjana, Universitas Muhammadiyah

Lebih terperinci

EARNED VALUE ANALYSIS TERHADAP BIAYA DAN JADWAL PADA PROYEK GEDUNG WILMAR BUSSINES INSTITUTE MEDAN TUGAS AKHIR

EARNED VALUE ANALYSIS TERHADAP BIAYA DAN JADWAL PADA PROYEK GEDUNG WILMAR BUSSINES INSTITUTE MEDAN TUGAS AKHIR EARNED VALUE ANALYSIS TERHADAP BIAYA DAN JADWAL PADA PROYEK GEDUNG WILMAR BUSSINES INSTITUTE MEDAN TUGAS AKHIR Ditulis sebagai syarat menyelesaikan Mata kuliah Tugas Akhir Semester VIII Pendidikan Program

Lebih terperinci

Kata kunci: Evaluasi Proyek, Konsep Nilai Hasil, ACWP, BCWS, BCWP

Kata kunci: Evaluasi Proyek, Konsep Nilai Hasil, ACWP, BCWS, BCWP ABSTRAK Adanya pembangunan konstruksi yang tidak sesuai dengan rencana, maka pelaksanaan dari proyek konstruksi perlu mendapat perhatian. Untuk mengatasi hal tersebut diperlukan suatu metode yang dapat

Lebih terperinci

Kata kunci: earned value, kinerja, pelaporan, pengendalian

Kata kunci: earned value, kinerja, pelaporan, pengendalian ABSTRAK Wilayah Badung Selatan merupakan pusat pengembangan pariwisata di Kabupaten Badung. Seiring dengan perkembangan pariwisata, maka kebutuhan terhadap air bersih pun akan semakin meningkat. Untuk

Lebih terperinci

Jurnal Sipil Statik Vol.1 No. 1, November 2012 (44-52)

Jurnal Sipil Statik Vol.1 No. 1, November 2012 (44-52) PENGENDALIAN WAKTU DAN BIAYA PADA TAHAP PELAKSANAAN PROYEK DENGAN MENGGUNAKAN METODE NILAI HASIL (Studi Kasus : Proyek Lanjutan Pembangunan Gedung PIP2B Kota Manado) Junaidi H. Tarore, G.Y. Malingkas,

Lebih terperinci

CONTROLLING IDENTIFIKASI VARIANS

CONTROLLING IDENTIFIKASI VARIANS CONTROLLING Ada dua macam teknik dan metode untuk pengendalian biaya dan jadual yaitu : 1. Identifikasi varians 2. Konsep nilai hasil (Earned Value Concept) IDENTIFIKASI VARIANS Identifikasi varians digunakan

Lebih terperinci

PENGENDALIAN PROYEK (Pengendalian Proyek-2 : CPI & SPI)

PENGENDALIAN PROYEK (Pengendalian Proyek-2 : CPI & SPI) PENGENDALIAN PROYEK (Pengendalian Proyek-2 : CPI & SPI) Pertemuan ke-10 Dosen: Ir. Bambang Herumanta, M.T. / Suwardo, S.T., M.T., Ph.D. UNIVERSITAS GADJAH MADA SEKOLAH VOKASI PROGRAM DIPLOMA TEKNIK SIPIL

Lebih terperinci

Jl. Ir. Sutami 36A, Surakarta 57126; Telp

Jl. Ir. Sutami 36A, Surakarta 57126; Telp eissn 2354-8630 ANALISIS TIME COST TRADE OFF DENGAN PENAMBAHAN JAM KERJA PADA PROYEK KONSTRUKSI (STUDI KASUS : PROYEK PEMBANGUNAN JALAN TOL BOGOR RING ROAD SEKSI II A) Okyta Putri Cahya Ardika 1), Sugiyarto

Lebih terperinci

PENGUKURAN KINERJA DAN EVALUASI KEMAJUAN PROYEK

PENGUKURAN KINERJA DAN EVALUASI KEMAJUAN PROYEK PENGUKURAN KINERJA DAN EVALUASI KEMAJUAN PROYEK TUJUAN EVALUASI KINERJA DAN KEMAJUAN PROYEK monitoring tentang apa yang terjadi perkembangan pencapaian jadwal revisi rencana dan jadwal jika dibutuhkan

Lebih terperinci

EVALUASI KEMAJUAN PROYEK DENGAN METODE NILAI HASIL PROSES PENGENDALIAN KINERJA WAKTU DAN BIAYA

EVALUASI KEMAJUAN PROYEK DENGAN METODE NILAI HASIL PROSES PENGENDALIAN KINERJA WAKTU DAN BIAYA TECHSI ~ Jurnal Penelitian Teknik Informatika Universitas Malikussaleh, Lhokseumawe Aceh Perencanaan dan pengendalian biaya dan waktu merupakan bagian dari manajemen proyek konstruksi secara keseluruhan.

Lebih terperinci

Aplikasi Metode Nilai Hasil (Earned Value Method) pada Sistem Pengendalian Proyek

Aplikasi Metode Nilai Hasil (Earned Value Method) pada Sistem Pengendalian Proyek JURNAL ILMIAH SEMESTA TEKNIKA Vol. 15, No. 2, 159-166, November 2012 159 Aplikasi Metode Nilai Hasil (Earned Value Method) pada Sistem Pengendalian Proyek (Application of Earned Value Method on Project

Lebih terperinci

ANALISIS PENGENDALIAN BIAYA DAN WAKTU DENGAN METODE KONSEP NILAI HASIL PADA PROYEK PEMBANGUNAN RESERVOIR II ANGGUNGAN DI MENGWI BADUNG

ANALISIS PENGENDALIAN BIAYA DAN WAKTU DENGAN METODE KONSEP NILAI HASIL PADA PROYEK PEMBANGUNAN RESERVOIR II ANGGUNGAN DI MENGWI BADUNG ANALISIS PENGENDALIAN BIAYA DAN WAKTU DENGAN METODE KONSEP NILAI HASIL PADA PROYEK PEMBANGUNAN RESERVOIR II ANGGUNGAN DI MENGWI BADUNG TUGAS AKHIR Oleh : I Gusti Nyoman Suta Gunarta NIM : 1104105098 JURUSAN

Lebih terperinci

BAB 4 ANALISIS DATA DAN PEMBAHASAN

BAB 4 ANALISIS DATA DAN PEMBAHASAN BAB 4 ANALISIS DATA DAN PEMBAHASAN 4.1. Analisis Data Dalam bab pembahasan akan dijelaskan secara rinci mengenai langkah-langkah dalam menyelesaikan tugas akhir ini yang meliputi perhitungan konsep nilai

Lebih terperinci

PENGENDALIAN PROYEK DENGAN METODE EARNED VALUE (STUDI KASUS PROYEK RUSUNAWA UNIVERSITAS DIPONEGORO SEMARANG)

PENGENDALIAN PROYEK DENGAN METODE EARNED VALUE (STUDI KASUS PROYEK RUSUNAWA UNIVERSITAS DIPONEGORO SEMARANG) LAPORAN TUGAS AKHIR PENGENDALIAN PROYEK DENGAN METODE EARNED VALUE (STUDI KASUS PROYEK RUSUNAWA UNIVERSITAS DIPONEGORO SEMARANG) Diajukan Sebagai Syarat Untuk Menyelesaikan Pendidikan Tingkat Strata Satu

Lebih terperinci

Agus Purnomo. Jurusan Teknik Industri Fakultas Teknik Universitas Pasundan

Agus Purnomo. Jurusan Teknik Industri Fakultas Teknik Universitas Pasundan EVALUASI PENGENDALIAN PROYEK DENGAN METODE ANALISIS VARIANS DAN KONSEP NILAI HASIL PADA PEMBANGUNAN TEMPAT PELELANGAN IKAN DI KABUPATEN CIANJUR JAWA BARAT Agus Purnomo Jurusan Teknik Industri Fakultas

Lebih terperinci

ISSN No [ JURNAL TEKNIKA VOL 7 NO 1 MARET 2015]

ISSN No [ JURNAL TEKNIKA VOL 7 NO 1 MARET 2015] ANALISIS PENGENDALIAN BIAYA DAN WAKTU DENGAN KONSEP NILAI HASIL (EARNED VALUE) (Studi Kasus : Fabrikasi Steel Structure Slag Gresik) Dwi Kartikasari*) *) Dosen Prodi Teknik Sipil Fakultas Teknik Universitas

Lebih terperinci

BAB II TINJAUAN PUSTAKA. (resource) yang ada. Yang dimaksud dengan sumber daya (resource) di sini

BAB II TINJAUAN PUSTAKA. (resource) yang ada. Yang dimaksud dengan sumber daya (resource) di sini BAB II TINJAUAN PUSTAKA 2.1 DEFINISI MANAJEMEN PROYEK Pengertian sederhana dari manajemen proyek adalah proses dalam pencapaian suatu tujuan yang telah disepakati dan dibatasi dengan waktu dan sumber daya

Lebih terperinci

ANALISIS METODE MONTECARLO PADA KONSEP NILAI HASIL UNTUK MONITORING PROYEK

ANALISIS METODE MONTECARLO PADA KONSEP NILAI HASIL UNTUK MONITORING PROYEK ANALISIS METODE MONTECARLO PADA KONSEP NILAI HASIL UNTUK MONITORING PROYEK Rizki Gumelar Jurusan Teknik Sipil Fakultas Teknik Universitas Brawijaya Malang Jl. MT. Haryono 167, Malang 65145, Indonesia ABSTRAK

Lebih terperinci

ALEX SATRYA MAULANA ( )

ALEX SATRYA MAULANA ( ) Disusun Oleh : ALEX SATRYA MAULANA (3109.106.046) JURUSAN TEKNIK SIPIL FAKULTAS TEKNIK SIPIL DAN PERENCANAAN INSTITUT SEPULUH NOPEMBER TAHUN 2011 I.1 Latar Belakang 1. Semakin besar dan rumitnya perkembangan

Lebih terperinci

Metode Earned Value untuk Analisa Kinerja Biaya dan Waktu Pelaksanaan pada Proyek Pembangunan Condotel De Vasa Surabaya

Metode Earned Value untuk Analisa Kinerja Biaya dan Waktu Pelaksanaan pada Proyek Pembangunan Condotel De Vasa Surabaya JURNAL TEKNIK ITS Vol. 4, No. 1, (2015) ISSN: 2337-3539 (2301-9271 Print) Metode Earned Value untuk Analisa Kinerja Biaya dan Waktu Pelaksanaan pada Proyek Pembangunan Condotel De Vasa Surabaya Muhammad

Lebih terperinci

PENERAPAN METODE KONSEP NILAI HASIL (EARNED VALUE CONCEPT) DALAM PENGENDALIAN PROYEK. Fauzy Nasution a, Ir. Syahrizal M.T. b

PENERAPAN METODE KONSEP NILAI HASIL (EARNED VALUE CONCEPT) DALAM PENGENDALIAN PROYEK. Fauzy Nasution a, Ir. Syahrizal M.T. b PENERAPAN METODE KONSEP NILAI HASIL (EARNED VALUE CONCEPT) DALAM PENGENDALIAN PROYEK (Studi Kasus : Proyek Pembangunan dan Pengandaan Utilitas Gedung Jasindo) Fauzy Nasution a, Ir. Syahrizal M.T. b Departemen

Lebih terperinci

ANALISA PEMBIAYAAN PROYEK PEMBANGUNAN LANJUTAN GEDUNG LABORATORIUM TERPADU FKIP UNIVERSITAS TANJUNGPURA PONTIANAK

ANALISA PEMBIAYAAN PROYEK PEMBANGUNAN LANJUTAN GEDUNG LABORATORIUM TERPADU FKIP UNIVERSITAS TANJUNGPURA PONTIANAK ANALISA PEMBIAYAAN PROYEK PEMBANGUNAN LANJUTAN GEDUNG LABORATORIUM TERPADU FKIP UNIVERSITAS TANJUNGPURA PONTIANAK Refi Wospoga 1), Rafi e 2), Nurul Wardhani 2) Abstrak Pengendalian biaya dan waktu diperlukan

Lebih terperinci

Perancangan Sistem Informasi Pengendalian Proyek dengan Metode Earned Value Management (EVM)

Perancangan Sistem Informasi Pengendalian Proyek dengan Metode Earned Value Management (EVM) 1 Perancangan Sistem Informasi Pengendalian Proyek dengan Metode Earned Value Management (EVM) Zul Fadli, Yusroniya Eka Putri R.W, ST., MT dan Trijoko Wahyu Adi, ST., MT., PhD Jurusan Teknik Sipil, Fakultas

Lebih terperinci

PENGENDALIAN BIAYA DAN WAKTU PROYEK DENGANN METODE KONSEP NILAI HASIL (Studi Kasus: Proyek Pembangunan The Royal Bukit)

PENGENDALIAN BIAYA DAN WAKTU PROYEK DENGANN METODE KONSEP NILAI HASIL (Studi Kasus: Proyek Pembangunan The Royal Bukit) PENGENDALIAN BIAYA DAN WAKTU PROYEK DENGANN METODE KONSEP NILAI HASIL (Studi Kasus: Proyek Pembangunan The Royal Bukit) TUGAS AKHIR Oleh : A.A.Wira Adi Kusuma NIM: 1104105096 JURUSAN TEKNIK SIPIL FAKULTAS

Lebih terperinci

BAB II TINJAUAN PUSTAKA. titik awal dan titik akhir serta hasil tertentu. Proyek biasanya bersifat lintas fungsi

BAB II TINJAUAN PUSTAKA. titik awal dan titik akhir serta hasil tertentu. Proyek biasanya bersifat lintas fungsi BAB II TINJAUAN PUSTAKA 2.1. Pengertian Proyek Konstruksi Proyek merupakan sekumpulan aktivitas yang saling berhubungan. Ada titik awal dan titik akhir serta hasil tertentu. Proyek biasanya bersifat lintas

Lebih terperinci

PENGENDALIAN BIAYA DAN JADUAL TERPADU PADA PROYEK KONSTRUKSI. Dewa Ketut Sudarsana 1

PENGENDALIAN BIAYA DAN JADUAL TERPADU PADA PROYEK KONSTRUKSI. Dewa Ketut Sudarsana 1 PENGENDALIAN BIAYA DAN JADUAL TERPADU PADA PROYEK KONSTRUKSI. Dewa Ketut Sudarsana 1 Abstrak: Sumberdaya utama terbatas pada tahap pelaksanaan suatu proyek kostruksi adalah biaya, mutu dan waktu. Perencanaan,

Lebih terperinci

ANALISIS NILAI HASIL TERHADAP WAKTU PADA PROYEK KONSTRUKSI (Studi Kasus Pada Proyek Pembangunan Hotel Eastparc Yogyakarta) SKRIPSI

ANALISIS NILAI HASIL TERHADAP WAKTU PADA PROYEK KONSTRUKSI (Studi Kasus Pada Proyek Pembangunan Hotel Eastparc Yogyakarta) SKRIPSI ANALISIS NILAI HASIL TERHADAP WAKTU PADA PROYEK KONSTRUKSI (Studi Kasus Pada Proyek Pembangunan Hotel Eastparc Yogyakarta) Analysis on Earned Value to Time of Construction Project (Case Study at Building-Construction

Lebih terperinci

PELAKSANAAN PROYEK DENGAN METODE GEDUNG PM3 PT. ADIPRIMA SURAPRINTA GRESIK OLEH : ARIFIAN SYAH PUTRA

PELAKSANAAN PROYEK DENGAN METODE GEDUNG PM3 PT. ADIPRIMA SURAPRINTA GRESIK OLEH : ARIFIAN SYAH PUTRA ANALISA KINERJA BIAYA DAN WAKTU PELAKSANAAN PROYEK DENGAN METODE EARNED VALUE PADA GEDUNG PM3 PT. ADIPRIMA SURAPRINTA GRESIK OLEH : ARIFIAN SYAH PUTRA 3109.106.059 BAB 1 PENDAHULUAN Latar Belakang 1. Gedung

Lebih terperinci

Analisa Earned Value pada Proyek Pembangunan Vimala Hills Villa dan Resort Bogor

Analisa Earned Value pada Proyek Pembangunan Vimala Hills Villa dan Resort Bogor D-76 Analisa Earned Value pada Proyek Pembangunan Vimala Hills Villa dan Resort Bogor Yomelda dan Christiono Utomo Jurusan Teknik Sipil, Fakultas Teknik Sipil dan Perencanaan, Institut Teknologi Sepuluh

Lebih terperinci

MONITORING PROYEK REHABILITASI SALURAN IRIGASI NGREJO DENGAN METODE KONSEP NILAI HASIL BERDASARKAN TIME BASED DAN PROGRESS BASED SKRIPSI TEKNIK SIPIL

MONITORING PROYEK REHABILITASI SALURAN IRIGASI NGREJO DENGAN METODE KONSEP NILAI HASIL BERDASARKAN TIME BASED DAN PROGRESS BASED SKRIPSI TEKNIK SIPIL MONITORING PROYEK REHABILITASI SALURAN IRIGASI NGREJO DENGAN METODE KONSEP NILAI HASIL BERDASARKAN TIME BASED DAN PROGRESS BASED SKRIPSI TEKNIK SIPIL Ditujukan untuk memenuhi persyaratan memperoleh gelar

Lebih terperinci

PENGENDALIAN BIAYA DAN WAKTU PADA PROYEK KONSTRUKSI DENGAN KONSEP EARNED VALUE (STUDI KASUS PROYEK PEMBANGUNAN JEMBATAN BERINGIN KOTA PADANG)

PENGENDALIAN BIAYA DAN WAKTU PADA PROYEK KONSTRUKSI DENGAN KONSEP EARNED VALUE (STUDI KASUS PROYEK PEMBANGUNAN JEMBATAN BERINGIN KOTA PADANG) PENGENDALIAN BIAYA DAN WAKTU PADA PROYEK KONSTRUKSI DENGAN KONSEP EARNED VALUE (STUDI KASUS PROYEK PEMBANGUNAN JEMBATAN BERINGIN KOTA PADANG) Jajang Atmaja, Yan Parta Wijaya, Hartati Jurusan Teknik Sipil

Lebih terperinci

RENCANA KERJA ULANG PROYEK PEMBANGUNAN GEDUNG DAN OPTIMALISASI NASKAH PUBLIKASI

RENCANA KERJA ULANG PROYEK PEMBANGUNAN GEDUNG DAN OPTIMALISASI NASKAH PUBLIKASI RENCANA KERJA ULANG PROYEK PEMBANGUNAN GEDUNG DAN OPTIMALISASI (Studi Kasus Pelaksanaan Proyek Pembangunan Asrama Baru Lantai 5 Kantor LPPKS Indonesia) NASKAH PUBLIKASI Diajukan Kepada Program Magister

Lebih terperinci

YOGYAKARTA NPM :10 02

YOGYAKARTA NPM :10 02 ANALISIS TINGKAT EFEKTIFITAS PENGGUNAAN METODE NILAI HASIL PADAA PENGENDALIAN PROYEK KONSTRUKSI DI YOGYAKARTA Tugas Akhir Oleh : PUTRI MONICA SARI NPM :10 02 13506 PROGRAM STUDI TEKNIK SIPIL FAKULTAS TEKNIK

Lebih terperinci

BAB II STUDI PUSTAKA 2.1 Penelitian Wahyudi (2007) 2.2 Penelitan Rizki Gumelar (2012)

BAB II STUDI PUSTAKA 2.1 Penelitian Wahyudi (2007) 2.2 Penelitan Rizki Gumelar (2012) BAB II STUDI PUSTAKA Studi pustaka berisi mengenai penelitian yang telah dilakukan sebelumnya mengenai analilsis konsep nilai hasil. Studi pustaka untuk penelitian ini meliputi : 2.1 Penelitian Wahyudi

Lebih terperinci

EARNED VALUE METHOD UNTUK PENGENDALIAN BIAYA DAN WAKTU DENGAN MENGGUNAKAN MICROSOFT PROJECT DAN EXCEL

EARNED VALUE METHOD UNTUK PENGENDALIAN BIAYA DAN WAKTU DENGAN MENGGUNAKAN MICROSOFT PROJECT DAN EXCEL Konferensi Nasional Teknik Sipil I (KoNTekS I) Universitas Atma Jaya Yogyakarta Yogyakarta, 11 12 Mei 2007 EARNED VALUE METHOD UNTUK PENGENDALIAN BIAYA DAN WAKTU DENGAN MENGGUNAKAN MICROSOFT PROJECT DAN

Lebih terperinci

ANALISIS NILAI HASIL TERHADAP WAKTU PADA PROYEK KONSTRUKSI (STUDI KASUS PADA PROYEK PEMBANGUNAN HOTEL EASTPARC YOGYAKARTA)

ANALISIS NILAI HASIL TERHADAP WAKTU PADA PROYEK KONSTRUKSI (STUDI KASUS PADA PROYEK PEMBANGUNAN HOTEL EASTPARC YOGYAKARTA) ANALISIS NILAI HASIL TERHADAP WAKTU PADA PROYEK KONSTRUKSI (STUDI KASUS PADA PROYEK PEMBANGUNAN HOTEL EASTPARC YOGYAKARTA) Erik Pradana Putra (1), Siti Qomariyah (2), Sugiyarto (3) 1) Mahasiswa Fakultas

Lebih terperinci

BAB III METODOLOGI 3.1 Rancangan Penelitian

BAB III METODOLOGI 3.1 Rancangan Penelitian 25 BAB III METODOLOGI Untuk mencapai hasil yang optimal dari tujuan dan sasaran didalam analisa ini, maka perlu diterapkan suatu pendekatan penanganan yang tepat dan realistis. Dalam hal ini adanya proses

Lebih terperinci

ANALISIS KINERJA PROYEK PEMBANGUNAN RUANG KELAS BARU SMKN 6 BALIKPAPAN

ANALISIS KINERJA PROYEK PEMBANGUNAN RUANG KELAS BARU SMKN 6 BALIKPAPAN ANALISIS KINERJA PROYEK PEMBANGUNAN RUANG KELAS BARU SMKN 6 BALIKPAPAN Noviar 1, Anang Yahya 2 1 Mahasiswa Prodi Studi Teknik Sipil, Universitas Balikpapan 2 Dosen Prodi Teknik Sipil, Universitas Balikpapan

Lebih terperinci

ANALISIS PENGENDALIAN WAKTU DENGAN EARNED VALUE PADA PROYEK PEMBANGUNAN HOTEL FAVE KOTABARU YOGYAKARTA

ANALISIS PENGENDALIAN WAKTU DENGAN EARNED VALUE PADA PROYEK PEMBANGUNAN HOTEL FAVE KOTABARU YOGYAKARTA ANALISIS PENGENDALIAN WAKTU DENGAN EARNED VALUE PADA PROYEK PEMBANGUNAN HOTEL FAVE KOTABARU YOGYAKARTA Vendie Abma 1 1 Staf Pengajar Program Studi Teknik Sipil, Fakultas Teknik Sipil dan Perencanaan, Universitas

Lebih terperinci

CONTROLLING IDENTIFIKASI VARIANS

CONTROLLING IDENTIFIKASI VARIANS CONTROLLING Ada dua macam teknik dan metode untuk pengendalian biaya dan jadual yaitu : 1. Identifikasi varians 2. Konsep nilai hasil (Earned Value Concept) IDENTIFIKASI VARIANS Identifikasi varians digunakan

Lebih terperinci

BAB II TINJAUAN PUSTAKA

BAB II TINJAUAN PUSTAKA BAB II TINJAUAN PUSTAKA 2.1 Manajemen Proyek Menurut Ir. Abrar Husen, MT., Manajemen Proyek adalah penerapan ilmu pengetahuan, keahlian dan keterampilan, cara teknis yang terbaik dan dengan sumber daya

Lebih terperinci

Konsep Earned Value dalam Aplikasi Pengelolaan Proyek Konstruksi

Konsep Earned Value dalam Aplikasi Pengelolaan Proyek Konstruksi JURNAL ILMIAH SEMESTA TEKNIKA Vol. 11 No. 2 (November 2008): 153-161 153 Konsep Earned Value dalam Aplikasi Pengelolaan Proyek Konstruksi (Earned Value Concept for Application on Construction Project Management)

Lebih terperinci

PENGENDALIAN WAKTU DAN BIAYA PADA PROYEK DENGAN METODE EARNED VALUE (STUDI KASUS PEMBANGUNAN DERMAGA KASIPUTE KAB.BOMBANA)

PENGENDALIAN WAKTU DAN BIAYA PADA PROYEK DENGAN METODE EARNED VALUE (STUDI KASUS PEMBANGUNAN DERMAGA KASIPUTE KAB.BOMBANA) PENGENDALIAN WAKTU DAN BIAYA PADA PROYEK DENGAN METODE EARNED VALUE (STUDI KASUS PEMBANGUNAN DERMAGA KASIPUTE KAB.BOMBANA) Ahmad Efendi 1, La Ode Sumarsiddin 2 1&2 Staf Dosen Program Studi Teknik Sipil,

Lebih terperinci

KAJIAN PERENCANAAN APLIKASI ANALISIS VARIANS DAN KONSEP NILAI HASIL MENGGUNAKAN MICROSOFT ACCESS DALAM PENGENDALIAN PROYEK KONSTRUKSI

KAJIAN PERENCANAAN APLIKASI ANALISIS VARIANS DAN KONSEP NILAI HASIL MENGGUNAKAN MICROSOFT ACCESS DALAM PENGENDALIAN PROYEK KONSTRUKSI ISSN 2407-733X E-ISSN 2407-9200 pp. 39-53 Jurnal Teknik Sipil Unaya KAJIAN PERENCANAAN APLIKASI ANALISIS VARIANS DAN KONSEP NILAI HASIL MENGGUNAKAN MICROSOFT ACCESS DALAM PENGENDALIAN PROYEK KONSTRUKSI

Lebih terperinci

BAB II TINJAUAN PUSTAKA

BAB II TINJAUAN PUSTAKA BAB II TINJAUAN PUSTAKA 2.1 Pengertian Proyek Dan Manajemen Proyek Proyek adalah rangkaian kegiatan yang dimulai dari perencanaan, dan dilaksanakan sampai benar-benar memberikan hasil atau keluaran-keluaran

Lebih terperinci

PENGGUNAAN METODE EARNED VALUE UNTUK MENGANALISA KINERJA BIAYA DAN WAKTU PADA PROYEK PEMBANGUNAN HOTEL HOLIDAY INN EXPRESS SURABAYA

PENGGUNAAN METODE EARNED VALUE UNTUK MENGANALISA KINERJA BIAYA DAN WAKTU PADA PROYEK PEMBANGUNAN HOTEL HOLIDAY INN EXPRESS SURABAYA 1 PENGGUNAAN METODE EARNED VALUE UNTUK MENGANALISA KINERJA BIAYA DAN WAKTU PADA PROYEK PEMBANGUNAN HOTEL HOLIDAY INN EXPRESS SURABAYA Reza Rifaldi, Farida Rachmawati Jurusan Teknik Sipil, Fakultas Teknik

Lebih terperinci

USULAN RANCANGAN PERENCANAAN DAN PENGENDALIAN PROYEK PEMBUATAN JIG LOCATOR SIDE BODY DI PT. PELITA SEHAT ABADI

USULAN RANCANGAN PERENCANAAN DAN PENGENDALIAN PROYEK PEMBUATAN JIG LOCATOR SIDE BODY DI PT. PELITA SEHAT ABADI Reka Integra ISSN: 2338-5081 Jurusan Teknik Industri Itenas No.04 Vol.02 Jurnal Online Institut Teknologi Nasional Oktober 2014 USULAN RANCANGAN PERENCANAAN DAN PENGENDALIAN PROYEK PEMBUATAN JIG LOCATOR

Lebih terperinci

Analisa Earned Value Concept dan Cost Varians pada Pekerjaan Jalan Wilayah Painan-Kambang Sumatra Barat

Analisa Earned Value Concept dan Cost Varians pada Pekerjaan Jalan Wilayah Painan-Kambang Sumatra Barat Analisa Earned Value Concept dan Cost Varians pada Pekerjaan Jalan Wilayah Painan-Kambang Sumatra Barat Milla Dwi Astari, ST., M.Eng. (mdwiastari@gmail.com) Intisari Proyek konstruksi merupakan suatu rangkaian

Lebih terperinci

ANALISIS MONITORING PELAKSANAAN PEKERJAAN PROYEK PASAR RAKYAT BARENG KOTA MALANG

ANALISIS MONITORING PELAKSANAAN PEKERJAAN PROYEK PASAR RAKYAT BARENG KOTA MALANG ANALISIS MONITORING PELAKSANAAN PEKERJAAN PROYEK PASAR RAKYAT BARENG KOTA MALANG Faris Rizal Andardi *1, Wisnumurti 2, Agus Suharyanto 3 1 Mahasiswa / Magister / Teknik Sipil / Univeritas Brawijaya 2 Dosen

Lebih terperinci

STUDI PENGENDALIAN WAKTU DAN BIAYA PADA PELAKSANAAN PEMELIHARAAN JALAN SIMPANG RAJA BAKONG - TANAH PASIR DENGAN MENGGUNAKAN KONSEP NILAI HASIL

STUDI PENGENDALIAN WAKTU DAN BIAYA PADA PELAKSANAAN PEMELIHARAAN JALAN SIMPANG RAJA BAKONG - TANAH PASIR DENGAN MENGGUNAKAN KONSEP NILAI HASIL STUDI PENGENDALIAN WAKTU DAN BIAYA PADA PELAKSANAAN PEMELIHARAAN JALAN SIMPANG RAJA BAKONG - TANAH PASIR DENGAN MENGGUNAKAN KONSEP NILAI HASIL Adzuha Desmi Jurusan Teknik Sipil Universitas Malikussaleh

Lebih terperinci

Keywords : Earned Value Analysis (EVA), Microsoft Project 2007, Cost Control, Time Control Brothers 2 Hotel Solo Baru.

Keywords : Earned Value Analysis (EVA), Microsoft Project 2007, Cost Control, Time Control Brothers 2 Hotel Solo Baru. PENGENDALIAN BIAYA DAN WAKTU DENGAN MENERAPKAN METODE EARNED VALUE ANALYSIS (EVA) MENGGUNAKAN SOFTWARE MICROSOFT PROJECT 2007 (STUDI KASUS DI PROYEK PEMBANGUNAN HOTEL BROTHERS 2 SOLO BARU, SUKOHARJO) Endar

Lebih terperinci

EVALUASI ARUS KAS KONTRAKTOR DENGAN SISTEM ANGSURAN PEMBAYARAN BERDASARKAN PRESTASI KERJA

EVALUASI ARUS KAS KONTRAKTOR DENGAN SISTEM ANGSURAN PEMBAYARAN BERDASARKAN PRESTASI KERJA EVALUASI ARUS KAS KONTRAKTOR DENGAN SISTEM ANGSURAN PEMBAYARAN BERDASARKAN PRESTASI KERJA Yohanes Poerwadi NRP : 0021030 Pembimbing : Yohanes Lim Dwi Adianto, Ir., MT. FAKULTAS TEKNIK JURUSAN TEKNIK SIPIL

Lebih terperinci

BAB III LANDASAN TEORI

BAB III LANDASAN TEORI BAB III LANDASAN TEORI 3.1. Kinerja Proyek Menurut Cleland (1995), standar kinerja diperlukan untuk melakukan tindakan pengendalian terhadap penggunaan sumber daya yang ada dalam suatu proyek. Hal ini

Lebih terperinci

PENGENDALIAN BIAYA DAN WAKTU PROYEK DENGAN METODE KONSEP NILAI HASIL (EARNED VALUE)

PENGENDALIAN BIAYA DAN WAKTU PROYEK DENGAN METODE KONSEP NILAI HASIL (EARNED VALUE) JURNAL KARYA TEKNIK SIPIL, Volume 6, Nomor 4, Tahun 2017, 460-470 Online di : http://ejournal-s1.undip.ac.id/index.php/jkts PENGENDALIAN BIAYA DAN WAKTU PROYEK DENGAN METODE KONSEP NILAI HASIL (EARNED

Lebih terperinci

TUGAS AKHIR. Diajukan sebagai syarat untuk meraih gelar Sarjana Teknik Strata 1 (S-1) Disusun Oleh: : DWI ANDAYANI NIM :

TUGAS AKHIR. Diajukan sebagai syarat untuk meraih gelar Sarjana Teknik Strata 1 (S-1) Disusun Oleh: : DWI ANDAYANI NIM : TUGAS AKHIR ANALISIS SISTEM PENGENDALIAN PROYEK DENGAN MENGGUNAKAN METODE EARNED VALUE PADA PROYEK PEMBANGUNAN APARTEMEN M-TOWN SIGNATURE SUMMARECON SERPONG Diajukan sebagai syarat untuk meraih gelar Sarjana

Lebih terperinci

EVALUASI BIAYA DAN KINERJA WAKTU PELAKSANAAN KONSTRUKSI BAWAH JEMBATAN AFIAT DESA KANIGORO KECAMATAN PAGELARANKABUPATEN MALANG

EVALUASI BIAYA DAN KINERJA WAKTU PELAKSANAAN KONSTRUKSI BAWAH JEMBATAN AFIAT DESA KANIGORO KECAMATAN PAGELARANKABUPATEN MALANG EVALUASI BIAYA DAN KINERJA WAKTU PELAKSANAAN KONSTRUKSI BAWAH JEMBATAN AFIAT DESA KANIGORO KECAMATAN PAGELARANKABUPATEN MALANG Sabarudin Budiharto, Lalu Mulyadi, Edi Hargono Teknik Sipil Konsentrasi Manajemen

Lebih terperinci

METODE ANALISA VARIANS PEMBUATAN BANGUNAN PENGAMAN PANTAI PADA PROYEK X DI KABUPATEN BOLMONG

METODE ANALISA VARIANS PEMBUATAN BANGUNAN PENGAMAN PANTAI PADA PROYEK X DI KABUPATEN BOLMONG METODE ANALISA VARIANS PEMBUATAN BANGUNAN PENGAMAN PANTAI PADA PROYEK X DI KABUPATEN BOLMONG Pingkan A.K. Pratasis ABSTRAK Pengendalian biaya perlu diadakan didalam pelaksanaan suatu pekerjaan agar pekerjaan

Lebih terperinci

PENGENDALIAN PROYEK (Pengendalian Proyek-1)

PENGENDALIAN PROYEK (Pengendalian Proyek-1) PENGENDALIAN PROYEK (Pengendalian Proyek-1) Pertemuan ke-9 Dosen: Ir. Bambang Herumanta, M.T. / Suwardo, S.T., M.T., Ph.D. UNIVERSITAS GADJAH MADA SEKOLAH VOKASI PROGRAM DIPLOMA TEKNIK SIPIL Alamat : Jl.

Lebih terperinci

MONITORING PELAKSANAAN PEKERJAAN PADA PROYEK BANGUNAN PERGUDANGAN DOUBLE DENGAN METODE KONSEP NILAI HASIL

MONITORING PELAKSANAAN PEKERJAAN PADA PROYEK BANGUNAN PERGUDANGAN DOUBLE DENGAN METODE KONSEP NILAI HASIL MONITORING PELAKSANAAN PEKERJAAN PADA PROYEK BANGUNAN PERGUDANGAN DOUBLE DENGAN METODE KONSEP NILAI HASIL NASKAH PUBLIKASI TEKNIK SIPIL Diajukan untuk memenuhi persyaratan memperoleh gelar Sarjana Teknik

Lebih terperinci

PEMBUATAN PROGRAM UNTUK PENGENDALIAN PELAKSANAAN PROYEK MENGGUNAKAN MICROSOFT ACCESS DENGAN PENDEKATAN ANALISIS VARIANS

PEMBUATAN PROGRAM UNTUK PENGENDALIAN PELAKSANAAN PROYEK MENGGUNAKAN MICROSOFT ACCESS DENGAN PENDEKATAN ANALISIS VARIANS PEMBUATAN PROGRAM UNTUK PENGENDALIAN PELAKSANAAN PROYEK MENGGUNAKAN MICROSOFT ACCESS DENGAN PENDEKATAN ANALISIS VARIANS RULLY KURNIAWAN Jurusan Teknik Sipil, FTSP, Universitas Gunadarma ABSTRAKSI Pengendalian

Lebih terperinci

BAB II TINJAUAN PUSTAKA

BAB II TINJAUAN PUSTAKA 7 BAB II TINJAUAN PUSTAKA 2.1 Kinerja Proyek Kinerja Proyek merupakan bagaimana cara kerja proyek tersebut dengan membandingkan hasil kerja nyata dengan perkiraan cara kerja pada kontrak kerja yang disepakati

Lebih terperinci

Rini Sriyani Staf Pengajar Jurusan Teknik Sipil Fakultas Teknik Universitas Haluoleo Kampus Hijau Bumi Tridharma Anduonohu Kendari

Rini Sriyani Staf Pengajar Jurusan Teknik Sipil Fakultas Teknik Universitas Haluoleo Kampus Hijau Bumi Tridharma Anduonohu Kendari PENGAPLIKASIAN METODE EARNED VALUE PADA PENGENDALIAN WAKTU TERHADAP BIAYA (Study Kasus: Proyek Penggantian Jembatan Sungai Langkolome Cs Kabupaten Muna) Meitri Wulan Laura Bulo Alumni Jurusan Teknik Sipil

Lebih terperinci

PERBANDINGAN BIAYA PROYEK GEDUNG EMPAT LANTAI STKIP KIE RAHA TERNATE DENGAN METODE EARNED VALUE

PERBANDINGAN BIAYA PROYEK GEDUNG EMPAT LANTAI STKIP KIE RAHA TERNATE DENGAN METODE EARNED VALUE PERBANDINGAN BIAYA PROYEK GEDUNG EMPAT LANTAI STKIP KIE RAHA TERNATE DENGAN METODE EARNED VALUE Adria Daulasi Jantje B. Mangare, D.R.O. Walangitan Fakultas Teknik Jurusan Sipil Universitas Sam Ratulangi

Lebih terperinci

BAB II TINJAUAN PUSTAKA. dalam periode tertentu ( Maharesi Dannyanti,2010 ). kurun waktu tertentu ( Tampubolon dalam Dannyanti,2010 )

BAB II TINJAUAN PUSTAKA. dalam periode tertentu ( Maharesi Dannyanti,2010 ). kurun waktu tertentu ( Tampubolon dalam Dannyanti,2010 ) BAB II TINJAUAN PUSTAKA II.1 Pengertian Proyek Proyek dalam analisis jaringan kerja adalah serangkaian kegiatan kegiatan yang bertujuan untuk menghasilkan produk dan hanya dilakukan dalam periode tertentu

Lebih terperinci

ZHAFIRA HADYAN

ZHAFIRA HADYAN ZHAFIRA HADYAN 3108 100 017 Proyek Pembangunan Tempat pengolahan Besi PT. Master Steel Manufactory dilaksanakan pada tanggal 1 Oktober 2011 sampai dengan 31 Juli 2012. Setiap proyek perlu dilakukan tindakan

Lebih terperinci

ANALISIS NILAI HASIL TERHADAP BIAYA PADA PROYEK

ANALISIS NILAI HASIL TERHADAP BIAYA PADA PROYEK ANALISIS NILAI HASIL TERHADAP BIAYA PADA PROYEK KONSTRUKSI (Studi Kasus Pada Proyek Pembangunan Gedung Perkuliahan Fisipol Universitas Gadjah Mada Yogyakarta) Analysis On Earned Value to Cost of Construction

Lebih terperinci

ANALISIS KEMAJUAN PROYEK DENGAN EARNED VALUE METHOD DALAM PROSES PENGENDALIAN KINERJA PROYEK BANGUNAN TINGGI DI JAKARTA SELATAN

ANALISIS KEMAJUAN PROYEK DENGAN EARNED VALUE METHOD DALAM PROSES PENGENDALIAN KINERJA PROYEK BANGUNAN TINGGI DI JAKARTA SELATAN Konferensi Nasional Teknik Sipil 3 (KoNTekS 3) Jakarta, 6 7 Mei 2009 ANALISIS KEMAJUAN PROYEK DENGAN EARNED VALUE METHOD DALAM PROSES PENGENDALIAN KINERJA PROYEK BANGUNAN TINGGI DI JAKARTA SELATAN Andrew

Lebih terperinci

CONTROL PERFORMEN AND PRODUCTIVITY OF STOREY BUILDING 4 FLOORS

CONTROL PERFORMEN AND PRODUCTIVITY OF STOREY BUILDING 4 FLOORS CONTROL PERFORMEN AND PRODUCTIVITY OF STOREY BUILDING 4 FLOORS FOR PARKING TWO WHEELS IN MUHAMMADIYAH UNIVERSITY OF SURAKARTA PENGENDALIAN KINERJA DAN PRODUKTIVITAS PEMBANGUNAN GEDUNG BERTINGKAT 4 LANTAI

Lebih terperinci

A PROJECT EVALUATION IN SURAKARTA (A Case Project of Order and Built in Taman SumberAsri Housing) Dian Arumningsih Diah Purnamawanti.

A PROJECT EVALUATION IN SURAKARTA (A Case Project of Order and Built in Taman SumberAsri Housing) Dian Arumningsih Diah Purnamawanti. A PROJECT EVALUATION IN SURAKARTA (A Case Project of Order and Built in Taman SumberAsri Housing) Dian Arumningsih Diah Purnamawanti Abstract The Housing business is an effort done by developers to gain

Lebih terperinci

ABSTRAK PANJANG PENERAPAN METODE EARNED VALUE

ABSTRAK PANJANG PENERAPAN METODE EARNED VALUE ABSTRAK PANJANG PENERAPAN METODE EARNED VALUE PADA PELAKSANAAN PROYEK KONSTRUKSI (STUDI KASUS PT SARANAKARYA BANGUN PERSADA DALAM PROYEK PEMBANGUNAN GEDUNG PENUNJANG I, PT SEMEN INDONESIA (PERSERO)) Oleh:

Lebih terperinci

ANALISA PENGENDALIAN BIAYA DENGAN MENGGUNAKAN EARNED VALUE CONCEPT

ANALISA PENGENDALIAN BIAYA DENGAN MENGGUNAKAN EARNED VALUE CONCEPT AALISA PEGEDALIA BIAYA DEGA MEGGUAKA EARED VALUE COCEPT (Studi Kasus : Proyek Pembangunan Gedung Rumah Sakit Pendidikan Universitas Andalas Padang) PEDAHULUA 1.1 Latar Belakang Proses pengendalian waktu

Lebih terperinci

ANALISIS KEBUTUHAN MODAL KERJA DAN PENGENDALIAN BIAYA BERDASARKAN VARIAN BIAYA DALAM PROYEK KONSTRUKSI (STUDI KASUS: LEGIAN VILLAGE, KUTA)

ANALISIS KEBUTUHAN MODAL KERJA DAN PENGENDALIAN BIAYA BERDASARKAN VARIAN BIAYA DALAM PROYEK KONSTRUKSI (STUDI KASUS: LEGIAN VILLAGE, KUTA) Jurnal Ilmiah Teknik Sipil Vol. 17, No. 1, Januari 2013 ANALISIS KEBUTUHAN MODAL KERJA DAN PENGENDALIAN BIAYA BERDASARKAN VARIAN BIAYA DALAM PROYEK KONSTRUKSI (STUDI KASUS: LEGIAN VILLAGE, KUTA) I Gede

Lebih terperinci

Prosiding Seminar Nasional Teknik Sipil 2016 ISSN: Fakultas Teknik Universitas Muhammadiyah Surakarta

Prosiding Seminar Nasional Teknik Sipil 2016 ISSN: Fakultas Teknik Universitas Muhammadiyah Surakarta PENERAPAN EARNED VALUE METHOD DAN PROJECT CRASHING PADA PROYEK KONSTRUKSI (Studi Kasus :Proyek Pembangunan Gedung PONEK RSUD Sunan Kalijaga Kecamatan Demak, Kabupaten Demak) Aditya Pawitra Sari 1 1*, Mandiyo

Lebih terperinci

BAB III METODE PENELITIAN Jenis Penelitian Objek Penelitian Jenis Data Metode Pengumpulan Data Primer dan

BAB III METODE PENELITIAN Jenis Penelitian Objek Penelitian Jenis Data Metode Pengumpulan Data Primer dan DAFTAR ISI KATA PENGANTAR... i HALAMAN PERSEMBAHAN... iii DAFTAR ISI... v DAFTAR GAMBAR... vii DAFTAR TABEL... viii DAFTAR RUMUS... ix DAFTAR LAMPIRAN... x ABSTRACT... xi INTISARI...xxi BAB I PENDAHULUAN...1

Lebih terperinci

ANALISIS KINERJA WAKTU PROYEK SEKOLAH X DENGAN METODE PERFORMANCE INTENSITY

ANALISIS KINERJA WAKTU PROYEK SEKOLAH X DENGAN METODE PERFORMANCE INTENSITY ANALISIS KINERJA WAKTU PROYEK SEKOLAH X DENGAN METODE PERFORMANCE INTENSITY Andrew Santoso 1, Andi Prasetyo 2, Andi 3 ABSTRAK : Kendala waktu sering menjadi masalah dalam proyek konstruksi. Penjadwalan

Lebih terperinci

DAFTAR ISI. BAB 2 TINJAUAN PUSTAKA Penerapan Earned Value Management Stabilitas CPI Sifat Proyek...

DAFTAR ISI. BAB 2 TINJAUAN PUSTAKA Penerapan Earned Value Management Stabilitas CPI Sifat Proyek... DAFTAR ISI HALAMAN JUDUL... HALAMAN PENGESAHAN... HALAMAN PERNYATAAN... KATA PENGANTAR... DAFTAR ISI... DAFTAR SINGKATAN... DAFTAR TABEL... DAFTAR GAMBAR... DAFTAR LAMPIRAN... INTISARI... ABSTRACT... i

Lebih terperinci

Jl. Ir. Sutami 36A, Surakarta 57126; Telp

Jl. Ir. Sutami 36A, Surakarta 57126; Telp PENGENDALIAN BIAYA DAN WAKTU DENGAN MENERAPKAN METODE EARNED VALUE ANALYSIS (EVA) MENGGUNAKAN SOFTWARE PRIMAVERA PROJECT PLANNER P6 (Studi Kasus Proyek Pembangunan Hotel Brothers 2 Solo Baru, Sukoharjo)

Lebih terperinci

BAB III METODOLOGI PENELITIAN

BAB III METODOLOGI PENELITIAN BAB III METODOLOGI PENELITIAN Penelitian adalah terjemahan dari kata Inggris research. Dari itu juga ahli yang menerjemahkan research sebagai riset. Research itu sendiri berasal dari kata re, yang bearti

Lebih terperinci

BAB II TINJAUAN PUSTAKA

BAB II TINJAUAN PUSTAKA BAB II Bab II Tinjauan Pustaka TINJAUAN PUSTAKA 2.1 Manajemen Proyek Manajemen proyek adalah salah satu cara yang ditawarkan untuk maksud pengelolaan suatu proyek, yaitu suatu metode pengelolaan yang dikembangkan

Lebih terperinci

STUDI PENJADUALAN, PERENCANAAN BIAYA DAN PENGENDALIAN JADUAL PADA PROYEK PEMBANGUNAN RUKO DENGAN MENGGUNAKAN PROGRAM MICROSOFT PROJECT 2003

STUDI PENJADUALAN, PERENCANAAN BIAYA DAN PENGENDALIAN JADUAL PADA PROYEK PEMBANGUNAN RUKO DENGAN MENGGUNAKAN PROGRAM MICROSOFT PROJECT 2003 STUDI PENJADUALAN, PERENCANAAN BIAYA DAN PENGENDALIAN JADUAL PADA PROYEK PEMBANGUNAN RUKO DENGAN MENGGUNAKAN PROGRAM MICROSOFT PROJECT 2003 Domy Christoferson NRP : 9921022 Pembimbing : Ir. V. Hartanto,

Lebih terperinci

Penentuan Efektivitas Manfaat melalui Analisa Gap

Penentuan Efektivitas Manfaat melalui Analisa Gap EKOJI999 Nomor 251, 17 Mei 2013 Penentuan Efektivitas Manfaat melalui Analisa Gap oleh Prof. Richardus Eko Indrajit - indrajit@post.harvard.edu Artikel ini merupakan satu dari 999 bunga rampai pemikiran

Lebih terperinci