FAKTOR-FAKTOR YANG MEMPENGARUHI KINERJA KONTRAKTOR TERHADAP WAKTU PELAKSANAAN PADA PEKERJAAN BIDANG KEAIRAN DI KOTA BUKITTINGGI
|
|
- Yanti Sri Kurnia
- 6 tahun lalu
- Tontonan:
Transkripsi
1 FAKTOR-FAKTOR YANG MEMPENGARUHI KINERJA KONTRAKTOR TERHADAP WAKTU PELAKSANAAN PADA PEKERJAAN BIDANG KEAIRAN DI KOTA BUKITTINGGI Masril, Zaidir, Wardi Program Studi Teknik Sipil, Program Pascasarjana Universitas Bung Hatta masril_st@yahoo.com ABSTRACT Affect the contractor's performance including the implementation of labor time that is less effective in working time will hamper the achievement of timely execution of work according to the schedule that has been made. Based on these problems, the goal of this research is to know with certainty the factors that affect the performance of the contractor on the job execution time in Bukittinggi Inundated field and determine the causes that most affect the performance of the contractor on the job execution time Field Inundated in Bukittinggi. There are four (4) factors that affect the performance of the contractor against the execution time of the methods and technology, Field Management, Work Environment, and Human Factors. There are three dominant factors that affect the performance of the contractor on the job execution time in Bukittinggi inundated areas which showed that one factor is more focused on the human factor and field management, a factor of 2 is more focused on methods and technology factors, factor 3 is more focused on work environment factors. Factor is able to explain 42.72% variation, a factor of 2 is able to explain 8.42% of variation, and 3 factors are able to explain 3.78% variation Keywords: Performance, Execution Time ABSTRAK Kinerja kontraktor mempengaruhi waktu pelaksanaan diantaranya tenaga kerja yang kurang efektif dalam bekerja akan menghambat tercapainya waktu pelaksanaan pekerjaan tepat waktu sesuai dengan jadwal yang sudah dibuat. Berdasarkan permasalahan tersebut, maka tujuan penelitian ini adalah mengenal dengan pasti faktor-faktor yang mempengaruhi kinerja kontraktor terhadap waktu pelaksanaan pada pekerjaan Bidang Keairan di Kota Bukittinggi dan mengetahui faktor penyebab yang paling mempengaruhi kinerja kontraktor terhadap waktu pelaksanaan pada pekerjaan Bidang Keairan di Kota Bukittinggi. Hasil penelitian terdapat 4 (empat) faktor yang mempengaruhi kinerja kontraktor terhadap waktu pelaksanaan yaitu Metode dan Teknologi, Manajemen Lapangan, Lingkungan Kerja, dan Faktor Manusia. Terdapat 3 faktor dominan yang mempengaruhi kinerja kontraktor terhadap waktu pelaksanaan pada pekerjaan bidang keairan di Kota Bukittinggi dimana memperlihatkan bahwa faktor lebih difokuskan pada faktor manusia dan manajemen lapangan, faktor 2 lebih difokuskan pada faktor metode dan teknologi, faktor 3 lebih difokuskan pada faktor lingkungan kerja.
2 Faktor mampu menjelaskan 42,72% variasi, faktor 2 mampu menjelaskan 8,42% variasi, dan faktor 3 mampu menjelaskan 3,78% variasi. Secara keseluruhan, ketiga faktor tersebut mampu menjelaskan 74,92% variasi. Kata kunci: Kinerja, Waktu Pelaksanaan. PENDAHULUAN Proses pekerjaan pembangunan sebuah proyek konstruksi yang baik, diperlukan suatu manajemen proyek yang benar agar proyek tersebut berhasil dengan baik. Sebagai patokan keberhasilan suatu proyek konstruksi ditentukan oleh mutu dari konstruksi, biaya yang dipergunakan, serta penggunaan waktu pelaksanaan yang sesuai dengan rencana yang telah ditentukan. Tidak sesuainya penyelesaian proyek dengan waktu pelaksanaan yang telah dibuat disebabkan oleh berbagai faktor seperti faktor cuaca yang tidak memungkinkan dilakukannya pekerjaan, faktor keterlambatan yang terkait dengan material, peralatan, tenaga kerja, perencanaan yang tidak sesuai, lemahnya kontrol waktu proyek, kurangnya personil secara teknikal, koordinasi dan komunikasi yang lemah, pengawasan yang tidak memadai sehingga metode pelaksanaan tidak sesuai dengan perencanaan, dan lain sebagainya. Pencapaian rata-rata waktu pelaksanaan proyek oleh kontraktor kecil bidang keairan di Kota Bukittinggi yang belum mencapai 00% dirasakan perlunya dianalisis faktor-faktor utama yang membuat keterlambatan penyelesaian proyek keairan di Kota Bukittinggi agar kontraktor tidak mengalami kerugian dan mencapai standar mutu agar mampu bersaing dalam bidang jasa konstruksi. Keterlambatan ini menyebabkan kerugikan bagi pihak-pihak yang terkait seperti pemilik yang mengalami kerugian waktu pengoperasian hasil proyek, bagi kontraktor akan mengalami kerugian waktu dan biaya. Pengamatan yang dilakukan terhadap beberapa proyek keairan yang dilaksanakan tahun 200, 20 dan 202 dan dilanjutkan dengan survei terhadap beberapa kontraktor, Asosiasi Kontraktor, dan Dinas Pekerjaan Umum di Kota Bukittinggi terhadap pelaksanaan Proyek Konstruksi Keairan di Kota Bukittinggi, disimpulkan secara umum bahwa sekitar 20% dari proyek keairan yang waktu pelaksanaan tertunta karena kurangnya kinerja dari tenaga kerja dalam melaksanakan proyek tersebut Ada beberapa penelitian tentang faktor-faktor yang mempengaruhi kinerja kontraktor terhadap waktu pelaksanaan telah dilakukan oleh beberapa peneliti diantaranya Proboyo (2009), Sari (20), Nizamuddin (202), Hazmi (202). 2. TINJAUAN LITERATUR 2.. Kinerja Hasibuan (2007) juga menjelaskan bahwa kinerja merupakan hasil kerja yang dicapai seseorang dalam melaksanakan tugas tugas yang dibebankan kepadanya didasarkan atas kecakapan, pengalaman, kesungguhan dan waktu. Kinerja dalam menjalankan fungsinya tidak berdiri sendiri, tapi berhubungan dengan kepuasan kerja dan tingkat imbalan, dipengaruhi oleh ketrampilan, kemampuan dan sifat-sifat individu, dengan demikian kinerja pada dasarnya ditentukan oleh tiga hal yaitu (). Kemampuan, (2). Keinginan, dan 2
3 (3). Lingkungan (Donelly, Gibson dan Invancevich; 994 ). Penentuan kinerja tenaga kerja merupakan suatu hal yang sangat sulit ditentukan. Banyak faktor yang mempengaruhi kinerja tenaga kerja sebagai kualitatif, berkembang sangat maju dan memang banyak sekali dibutuhkan pengalaman. 2.2 Faktor-faktor yang mempengaruhi kinerja kontraktor Faktor-faktor yang dapat mempengaruhi tingkat kinerja dapat dibagi menjadi dua bagian : a. Faktor dari dalam pekerja, misal moral dan tingkah laku, absensi dan keterlambatan,keahlian, kerja sama team, dan motivasi pekerja. b. Faktor luar, misalnya material, upah kerja, alat, informasi, cuaca, jadwal pelaksanaan kepemimpinan, kontrol dan pengawasan. Untuk dapat mencapai keberhasilan proyek perlu diperhatikan faktor-faktor yang mempengaruhi kinerja tenaga kerja adalah: () faktor Metode dan Teknologi, (2) Fakto r Manajemen Lapangan, (3) Faktor Lingkungan Kerja dan (4) Faktor Manusia (Kaming, 997). 2.3 Waktu dalam Proyek Konstruksi Waktu dan jadwal pelaksanaan merupakan salah satu sasaran utama proyek. Kinerja waktu adalah suatu aktifitas yang harus diselesaikan suatu proyek yang bertujuan agar proyek dapat diselesaikan dengan waktu yang ditentukan sesuai dengan kontrak dan biaya yang telah disepakati Pengelolaan Waktu Pengelolaan waktu bertujuan agar proyek dapat diselesaikan tepat waktu atau dapat dipercepat dari jadwal. Pengelolaan waktu meliputi semua kegiatan yang berkaitan dengan penjadwalan sampai selesainya proyek Pengendalian Waktu Pengendalian waktu di lapangan bertujuan untuk menjaga agar waktu pelaksanaan sesuai dengan rencana waktu yang telah dipersiapkan sebelum proyek dimulai. Hal ini dimaksudkan agar rencana waktu yang telah ada dapat digunakan sebagai tolok ukur terhadap pelaksanaan untuk mengetahui kemajuan pekerjaan. Pengendalian waktu pelaksanaan proyek dapat dilakukan dengan menggunakan alat bantu jadwal pelaksanaan seperti Bar Chat Schedule, kurva S, Vektor Diagram, Metode Network Planning sebagai indikator terlambat tidaknya proyek dan formulir-formulir pengendalian jadwal yang lebih rinci, masing-masing untuk bahan, alat maupun subkontraktor. 3. METODOLOGI PENELITIAN Metodologi penelitian merupakan bagian yang memuat tahap-tahap pelasanakaan penelitian mulai dari studi pendahuluan, literatur yang digunakan, metode pemecahan masalah sampai dengan teknik analisis dan kesimpulan. Metodologi juga menjabarkan instrumen yang digunakan dalam penelitian berikut dengan respondennya. Kerangka metodologi penelitian dapat dilihat pada Gambar. 3
4 Penelitian Pendahuluan Mulai Kerangka Pemikiran Identifikasi Masalah Studi Pendahuluan dan Literatur Metode Penelitian Pengumpulan Data Penelitian Penyebaran Kuesioner Penelitian Rekapitulasi data Pengolahan dan Analisis Valid dan Reliabel? Tidak Ya Distribusi Frekuensi Analisis dan Pembahasan Selesai Gambar. Metodologi Penelitian 4. HASIL DAN PEMBAHASAN Penelitian dilakukan pada perusahaan konstruksi kualifikasi kecil (K-K3) yang ada di Kota Bukittinggi. Kuesioner disebarkan kepada 75 responden dengan tingkat pengembalian kuesioner 00%. Dari 75 kuesioner yang kembali semuanya bisa digunakan untuk data penelitian sehingga response rate dari kuesioner adalah 00%. Hasil uji validitas dan reliabilitas memperlihatkan bahwa dari 35 butir pertanyaan yang diidentifikasi di awal, 22 butir pertanyaan dinyatakan valid dan reliabel, sehingga untuk penelitian ini menggunakan 22 butir pertanyaan. 4.. Faktor-faktor yang mempengaruhi kinerja kontraktor terhadap waktu pelaksanaan Hasil analisis korelasi untuk faktor-faktor yang mempengaruhi kinerja kontraktor terhadap waktu pelaksanaan pada pekerjaan bidang keairan di Kota Bukittinggi dapat dilihat pada Tabel. Dari 22 butir pertanyaan yang valid tentang faktor yang mempengaruhi kinerja waktu pelaksanaan berkorelasi sedang, kuat sampai sangat kuat dengan nilai korelasi berkisar antara 0,308-0,987. Hasil analisis korelasi, ditemukan 4 faktor yang mempengaruhi kinerja waktu pelaksanaan pada pekerjaan bidang keairan di Kota Bukittinggi yaitu, Metode dan Teknologi, Manajemen Lapangan, Lingkungan Kerja, dan Faktor Manusia. 4
5 Tabel Hasil Analisis Korelasi Faktor TQM Indikator/Pertanyaan r Tingkat Metode Teknologi Manajemen Lapangan Lingkungan Kerja dan Faktor Manusia Bagaimana tingkat pengaruh spesifikasi dan kualitas terhadap kinerja? Bagaimana tingkat pengaruh target pekerjaan batu bata terhadap kinerja? Bagaimana tingkat pengaruh Penggunaan Bar Chart terhadap kinerja? Bagaimana tingkat pengaruh Pengaruh sumber daya peralatan terhadap pekerjaan? Bagaimana tingkat pengaruh tidak tepatnya penggunaan teknologi terhadap kinerja? Bagaimana tingkat pengaruh Perencanaan Kebutuhan Peralatan terhadap kinerja? Bagaimana tingkat pengaruh sumber daya tenaga kerja pada perusahaan terhadap kinerja? Bagaimana tingkat pengaruh sumber daya material terhadap kinerja? Bagaimana tingkat pengaruh Kelancaran pengadaan terhadap kinerja? Bagaimana tingkat pengaruh ketersediaan jumlah material terhadap kinerja? Bagaimana tingkat pengaruh Jarak material dengan lapangan terhadap kinerja? Bagaimana tingkat pengaruh spesifikasi material terhadap kinerja? Bagaimana tingkat pengaruh Tingkat Pendidikan terhadap kinerja? Bagaimana tingkat pengaruh Jarak tempat tinggal terhadap kinerja? Bagaimana tingkat pengaruh Hubungan yang baik dan harmonis pekerja terhadap kinerja? Bagaimana tingkat pengaruh Hubungan bawahan dan atasan terhadap kinerja? Bagaimana tingkat pengaruh dari pengarahan atasan terhadap kinerja? Bagaimana tingkat pengaruh Kesehatan terhadap kinerja? Bagaimana tingkat pengaruh Makanan yang sehat dan bergizi terhadap kinerja? Bagaimana tingkat pengaruh Usia pekerja terhadap kinerja? Bagaimana tingkat pengaruh Kebutuhan Sehari-hari terhadap kinerja? Bagaimana tingkat pengaruh Status terhadap kinerja? Korelasi 0,647 Kuat 0,45 Sedang 0,934 Sangat Kuat 0,579 Sedang 0,747 Kuat 0,437 Sedang 0,720 Kuat 0,934 Sangat Kuat 0,322 Sedang 0,384 Sedang 0,542 Sedang 0,626 Kuat 0,308 Sedang 0,7 Kuat 0,695 Kuat 0,548 Sedang 0,706 Kuat 0,930 Sangat Kuat 0,925 Sangat Kuat 0,987 Sangat Kuat 0,836 Sangat Kuat 0,925 Sangat Kuat 5
6 Pada Tabel 4. memperlihatkan bahwa dari 22 butir pertanyaan yang valid tentang faktor yang mempengaruhi kinerja waktu pelaksanaan berkorelasi sedang, kuat sampai sangat kuat dengan nilai korelasi berkisar antara 0,308-0,987. Untuk mendapatkan faktor yang dominan mempengaruhi yang mempengaruhi kinerja waktu pelaksanaan, maka pertanyaan dengan korelasi sedang dikeluarkan dari analisis korelasi. Dari hasil analisis korelasi, ditemukan 4 faktor yang mempengaruhi kinerja waktu pelaksanaan pada pekerjaan bidang Tabel 2 Total Variance Explained keairan di Kota Bukittinggi yaitu, Metode dan Teknologi, Manajemen Lapangan, Lingkungan Kerja, dan Faktor Manusia. 4.2 Faktor-faktor dominan yang mempengaruhi kinerja kontraktor terhadap waktu pelaksanaan Hasil analisis dari 22 butir pertanyaan yang dianalisis dapat dilihat pada Total Variance Explained dan Rotated Component Matrix yang menjadikan 3 faktor seperti disajikan pada Tabel 2 dan Tabel 3 Compo nent Initial Eigenvalues Extraction Sums of Squared Loadings Rotation Sums of Squared Loadings Total % of Variance Cumulati ve % Total % of Variance Cumulati ve % Total % of Variance Cumula tive % 5,980 42,76 42,76 5,980 42,76 42,76 4,38 30,840 30, ,579 8,423 6,39 2,579 8,423 6,39 4,00 28,58 59,42 3,930 3,785 74,925,930 3,785 74,925 2,70 5,503 74,925 Berdasarkan Tabel 3 diketahui bahwa dari 22 butir pertanyaan yang dianalisis ternyata hasil ekstraksi komputer menjadi tiga faktor (nilai eigen value >, menjadi faktor). Faktor mampu menjelaskan 42,72% variasi, faktor 2 mampu menjelaskan 8,42% variasi, dan faktor 3 mampu menjelaskan 3,78% variasi. Secara keseluruhan, ketiga faktor tersebut mampu menjelaskan 74,92% variasi. Tabel 3 Rotated Component Matrix Component 2 3 Metode & Teknologi 0,087 0,77-0,056 Metode & Teknologi 5 0,44 0,89 0,59 Metode & Teknologi 7 0,223 0,85-0,087 Metode & Teknologi 0,268 0,829 0,07 Metode & Teknologi 2 0,44 0,89 0,59 Manajemen Lapangan 4 0,467-0,28 0,02 Lingkungan kerja 2-0,039 0,38 0,900 Lingkungan kerja 5 0,206-0,72 0,729 Lingkungan kerja 7-0,7 0,226 0,85 Faktor Manusia 3 0,939 0,270-0,005 Faktor Manusia 6 0,77 0,74-0,4 Faktor Manusia 7 0,898 0,273 0,032 Faktor Manusia 0,883 0,303 0,068 Faktor Manusia 2 0,89 0,320 0,08 6
7 Berdasarkan Tabel 3 kemudian butirbutir pertanyaan tersebut dikelompokkan menjadi 3 faktor seperti yang disajikan pada Tabel 4. Tabel 4 Pengelompokkan berdasarkan analisis faktor Faktor Faktor X2.4, X4., X4.2 X4.3, X4.6, X4.7 Faktor 2 X., X.5, X.7, X., X.2 Faktor 3 X3.2, X3.5, X3.7 Berdasarkan Tabel 4 maka dapat disimpulkan bahwa terdapat 3 faktor dominan yang mempengaruhi kinerja kontraktor terhadap waktu pelaksanaan pada pekerjaan bidang keairan di Kota Bukittinggi dimana memperlihatkan bahwa faktor lebih difokuskan pada faktor manusia dan manajemen lapangan, faktor 2 lebih difokuskan pada faktor metode dan teknologi, faktor 3 lebih difokuskan pada faktor lingkungan kerja. Pada faktor manusia dan manajemen lapangan, yang harus diperhatikan dalam meningkatkan kinerja kontraktor adalah kesehatan, usia pekerja, pendidikan formal terhadap kinerja, kreatifitas, adaptasi terhadap pekerjaan, dan kemampuan pengambilan keputusan dilapangan. Kondisi kesehatan,. usia pekerja dan pendidikan formal juga meningkatkan produktivitasnya dalam bekerja. Pengaruh ketersediaan jumlah material, jarak material dengan lapangan, pengaruh spesifikasi material yang merupakan sub faktor dari faktor manajemen lapangan ikut mempengaruhi kinerja kontraktor terhadap waktu pelaksanaan pekerjaan keairan di Kota Bukittinggi dimana ketersediaan material dalam jumlah cukup, jarak material yang dekat dengan lokasi pengerjaan, dan spesifikasi material yang sesuai dengan yang direncanakan akan membuat pekerjaan berlangsung dengan efektif dan efisien sehingga waktu Pertanyaan pembentuk pelaksanaan pekerjaan pun dapat dilakukan tepat waktu. Untuk mendukung kinerja yang baik juga diperlukan faktor metode dan teknologi dalam pekerjaan proyek keairan di Kota Bukittinggi diantaranya yang perlu menjadi perhatian adalah pengaruh spesifikasi dan kualitas material yang digunakan, adanya target pekerjaan batu kali, penggunaan bar chart, pengaruh sumber daya peralatan terhadap pekerjaan, pengaruh tidak tepatnya penggunaan teknologi, perencanaan kebutuhan peralatan, pengaruh sumber daya tenaga kerja pada pekerjaan, pengaruh sumber daya material dan pengaruh kelancaran pengadaan dimana semua sub faktor tersebut mempengaruhi kinerja kontraktor terhadap waktu pelaksanaan pekerjaan. Faktor lingkungan kerja seperti tingkat pendidikan, jarak tempat tinggal, hubungan yang baik dan harmonis antar pekerja, hubungan bawahan dan atasan yang terjalin dengan baik, pengaruh dari pengarahan atasan juga perlu mendapat perhatian dimana sub faktor tersebut mempengaruhi pencapaian kinerja yang diharapkan. Tingkat pendidikan sesuai dengan yang dibutuhkan, jarak tempat tinggal yang dekat dengan lokasi proyek, hubungan yang baik dan harmonis antar pekerja, hubungan yang baik antara bawahan dan atasan, arahan dari atasan yang jelas dan mudah diterima oleh bawahan akan membuat pekerja dapat bekerja dengan baik sehingga kinerja yang diharapkan dan 7
8 waktu penyelesaian pekerjaan pun dapat dilakukan tepat waktu. Hasil penelitian ini mendukung penelitian yang dilakukan Hazmi (20) tentang faktor-faktor yang mempengaruhi kinerja pekerja terhadap waktu pelaksanaan konstruksi (studi kasus proyek-proyek di Dinas Pendidikan Kab. Aceh Selatan Propinsi Aceh, menemukan bahwa faktor metode dan teknologi dengan sub faktor pengaruh ketidaktepatan penggunaan teknologi dan pengaruh organisasi proyek/lapangan mempengaruhi kinerja pekerja konstruksi dengan besarnya kekuatan hubungan yang ada yaitu sebesar 68,7%. 5. KESIMPULAN Faktor-faktor yang mempengaruhi kinerja kontraktor terhadap waktu pelaksanaan pada pekerjaan bidang keairan di Kota Bukittinggi dalam pelaksanaan proyek tahun 200 dan 203 yaitu faktor metode dan teknologi, faktor manajemen lapangan, faktor lingkungan kerja dan faktor manusia. Faktor dominan dan signifikan mempengaruhi kinerja kontraktor terhadap waktu pelaksanaan pada pekerjaan bidang keairan di Kota Bukittinggi yaitu faktor manusia dan manajemen lapangan, faktor metode dan teknologi, faktor lingkungan kerja. Faktor manusia dan manajemen lapangan merupakan faktor yang paling besar mempengaruhi kinerja kontraktor terhadap waktu pelaksanaan yaitu mampu menjelaskan 42,72% variasi, kemudian diiringi oleh faktor metode dan teknologi mampu menjelaskan 8,42% variasi, dan faktor lingkungan kerja mampu menjelaskan 3,78% variasi. Secara keseluruhan, ketiga faktor tersebut mampu menjelaskan 74,92% variasi 6. DAFTAR PUSTAKA Arikunto, Suharsimi, 2002, Prosedur Penelitian Suatu Pendekatan Praktek, edisi Revisi. Penerbit PT Rineka Cipta. Azhari, Teuku Budi Aulia, Ibnu Abbas Majid, Faktor Faktor Risiko Yang Mempengaruhi Kinerja Kontraktor Pada Pelaksanaan Proyek Infrastruktur Di Kabupaten Aceh Jaya, Jurnal Teknik Sipil Pascasarjana Universitas Syiah Kuala, Volume 3, No., Februari 204 Gray, Clifford F & Larson, Erik W, 2007, Manajemen Proyek, Proses Manajerial, Yogyakarta : Andi. Hazmi, Syaiful., 20, Faktor- Faktor Yang Mempengaruhi Kinerja Pekerja Terhadap Waktu Pelaksanaan Konstruksi (Studi Kasus Proyek- Proyek Di Dinas Pendidikan Kab. Aceh Selatan Propinsi Aceh), Tesis, Program Pascasarjana Universitas Bung Hatta, Padang Putri, I.A. Praniti Tresna., I.B. Rai Adnyana, A.A. Wiranata, 202, Analisis Faktor-Faktor Yang Menyebabkan Pengajuan Klaim Pelaksanaan Konstruksi Oleh Kontraktor, Jurnal Ilmiah Elektronik Infrastruktur Teknik Sipil, Universitas Udayana, Denpasar Sari, S, P, 20, Faktor-Faktor Risiko Yang Mempengaruhi Kinerja Kontraktor Banda Aceh Dalam Pelaksanaan Proyek Konstruksi, Tugas Akhir Fakultas Teknik Jurusan Sipil, Universitas Syiah Kuala, Banda Aceh. Suharto, Iman., 999, Manajemen Proyek, Dari Konseptual sampai Operasional, Edisi 2, Penerbit Erlangga, Jakarta 8
MODEL MANAJEMEN RISIKO TERHADAP KINERJA BIAYA DAN WAKTU PELAKSANAAN PROYEK KONSTRUKSI
TESIS MODEL MANAJEMEN RISIKO TERHADAP KINERJA BIAYA DAN WAKTU PELAKSANAAN PROYEK KONSTRUKSI JAKA DWI LUCKITO No. Mhs.: 145102201/PS/MTS PROGRAM STUDI MAGISTER TEKNIK SIPIL PROGRAM PASCASARJANA UNIVERSITAS
Lebih terperinciBAB V KESIMPULAN DAN SARAN
BAB V KESIMPULAN DAN SARAN A. Kesimpulan Berdasarkan hasil analisis dan pembahasan tentang pengaruh aspekaspek pelaksanaan konstruksi yang meliputi perizinan proyek, organisasi proyek, peralatan proyek,
Lebih terperinciFAKTOR FAKTOR YANG MEMPENGARUHI WAKTU PELAKSANAAN PROYEK KONSTRUKSI DI DINAS PU. BINA MARGA KABUPATEN SUMENEP
FAKTOR FAKTOR YANG MEMPENGARUHI WAKTU PELAKSANAAN PROYEK KONSTRUKSI DI DINAS PU. BINA MARGA KABUPATEN SUMENEP Dwi Deshariyanto 1, Email : pehati@yahoo.com Subaidillah Fansuri 2 Email : fadil_sf@yahoo.com
Lebih terperinciANALISIS FAKTOR KETERLAMBATAN PEMBANGUNAN GEDUNG DENGAN STRUCTURAL EQUATION MODELING (SEM)
TESIS ANALISIS FAKTOR KETERLAMBATAN PEMBANGUNAN GEDUNG DENGAN STRUCTURAL EQUATION MODELING (SEM) ADRIAN AUSTEN No Mhs : 145102284/MTS PROGRAM STUDI MAGISTER TEKNIK SIPIL PROGRAM PASCASARJANA UNIVERSITAS
Lebih terperinciINDENTIFIKASI FAKTOR FAKTOR RISIKO KONTRAKTOR PADA PELAKSANAAN PROYEK JALAN PERKERASAN LENTUR (FLEXIBEL PAVAMENT) TERHADAP KINERJA MUTU PROYEK JALAN
TESIS INDENTIFIKASI FAKTOR FAKTOR RISIKO KONTRAKTOR PADA PELAKSANAAN PROYEK JALAN PERKERASAN LENTUR (FLEXIBEL PAVAMENT) TERHADAP KINERJA MUTU PROYEK JALAN SRIYONO DWI ZULIYANTO No.Mhs.: 145102228/PS/MTS
Lebih terperinciTESIS ANALISIS HUBUNGAN PERENCANAAN KOMUNIKASI DAN DISTRIBUSI INFORMASI ANTARA KONTRAKTOR DAN SUBKONTRAKTOR DENGAN KINERJA WAKTU
TESIS ANALISIS HUBUNGAN PERENCANAAN KOMUNIKASI DAN DISTRIBUSI INFORMASI ANTARA KONTRAKTOR DAN SUBKONTRAKTOR DENGAN KINERJA WAKTU OLEH : EMA ANGGRAINI WULANDARI NIM. 081237/PS/MTS PROGRAM STUDI MAGISTER
Lebih terperinciANALISA FAKTOR-FAKTOR YANG MEMPENGARUHI PRODUKTIVITAS TENAGA KERJA PROYEK KONSTRUKSI DI SURABAYA
ANALISA FAKTOR-FAKTOR YANG MEMPENGARUHI PRODUKTIVITAS TENAGA KERJA PROYEK KONSTRUKSI DI SURABAYA Neril Harnanik Yuniati, Christiono Utomo Program Studi Magister Manajemen Proyek Institut Teknologi Sepuluh
Lebih terperinciBAB I PENDAHULUAN. 1.1 Latar Belakang
BAB I PENDAHULUAN 1.1 Latar Belakang Pada umumnya setiap proyek konstruksi memiliki perencanaan dan jadwal pelaksanaan yang terstruktur dengan baik, mulai dari awal pengerjaan hingga berakhirnya proyek
Lebih terperinciKUESIONER PENELITIAN
KUESIONER PENELITIAN APLIKASI ANALISIS FAKTOR DENGAN METODE PRINCIPAL COMPONENT ANALYSIS DAN MAXIMUM LIKELIHOOD DALAM FAKTOR-FAKTOR YANG MEMENGARUHI PEMBERIAN MAKANAN TAMBAHAN PADA BAYI USIA 0-6 BULAN
Lebih terperinciPENGARUH QUALITY MANAGEMENT TERHADAP DAYA SAING KONTRAKTOR PADA PROYEK KONSTRUKSI GEDUNG DI KOTA BANDA ACEH
ISSN 2088-9321 ISSN e-2502-5295 pp. 67-76 PENGARUH QUALITY MANAGEMENT TERHADAP DAYA SAING KONTRAKTOR PADA PROYEK KONSTRUKSI GEDUNG DI KOTA BANDA ACEH Nya Munanta 1, Muttaqin Hasan 2, Hafnidar A. Rani 3
Lebih terperinciANALISIS FAKTOR PENYEBAB KETERLAMBATAN PADA PROYEK KONSTRUKSI JALAN DI KOTAMADYA KUPANG
ANALISIS FAKTOR PENYEBAB KETERLAMBATAN PADA PROYEK KONSTRUKSI JALAN DI KOTAMADYA KUPANG Sandro Fanggidae, I Putu Artama Wiguna Program Studi Magister Manajemen Teknologi Bidang Keahlian Manajemen Proyek
Lebih terperinciJurnal Teknik Sipil ITP Vol. 4 No.1 Januari 2017 ISSN:
ANALISIS PERBANDINGAN PRODUKTIVITAS TENAGA KERJA TERHADAP ANALISA HARGA SATUAN PEKERJAAN (AHSP) SNI 2013 DAN ANALISA DI LAPANGAN (STUDI KASUS PROYEK PEMBANGUNAN KANTOR DPPKA KAB. KERINCI PROP. JAMBI) Leli
Lebih terperinciMANAJEMEN RISIKO PADA PROYEK KONSTRUKSI GEDUNG DI YOGYAKARTA DENGAN MENGGUNAKAN METODE HOUSE OF RISK
TESIS MANAJEMEN RISIKO PADA PROYEK KONSTRUKSI GEDUNG DI YOGYAKARTA DENGAN MENGGUNAKAN METODE HOUSE OF RISK PARAMANANDA SOFYAN SOFANDI No. Mhs.: 155102492/PS/MTS PROGRAM STUDI MAGISTER TEKNIK SIPIL PROGRAM
Lebih terperinciSTUDI FAKTOR-FAKTOR PENYEBAB KETERLAMBATAN PADA PROYEK FINE YARN III BUILDING, TANGERANG ABSTRAK
STUDI FAKTOR-FAKTOR PENYEBAB KETERLAMBATAN PADA PROYEK FINE YARN III BUILDING, TANGERANG Aryasta Dariskan NRP : 1021022 Pembimbing : Deni Setiawan, S.T., M.T. ABSTRAK Pelaksanaan proyek konstruksi memiliki
Lebih terperinciANALISIS FAKTOR PENYEBAB KLAIM KONTRAK DAN PENYELESAIANNYA PADA PROYEK KONSTRUKSI
ANALISIS FAKTOR PENYEBAB KLAIM KONTRAK DAN PENYELESAIANNYA PADA PROYEK KONSTRUKSI TUGAS AKHIR Oleh: I Nyoman Gede Mahardika NIM: 1204105121 PROGRAM STUDI TEKNIK SIPIL FAKULTAS TEKNIK UNIVERSITAS UDAYANA
Lebih terperinciANALISIS FAKTOR-FAKTOR RISIKO TERHADAP KETERLAMBATAN PELAKSANAAN PROYEK KONSTRUKSI DI WILAYAH PERKOTAAN SARBAGITA
ANALISIS FAKTOR-FAKTOR RISIKO TERHADAP KETERLAMBATAN PELAKSANAAN PROYEK KONSTRUKSI DI WILAYAH PERKOTAAN SARBAGITA TUGAS AKHIR Oleh : Dewa Ayu Oka Narayanti NIM : 1204105012 JURUSAN TEKNIK SIPIL FAKULTAS
Lebih terperinciFAKTOR-FAKTOR PENYEBAB PENGERJAAN ULANG (REWORK) YANG BERKAITAN DENGAN MANAJERIAL PADA PROYEK KONTRUKSI JALAN DI KABUPATEN ROKAN HULU
FAKTOR-FAKTOR PENYEBAB PENGERJAAN ULANG (REWORK) YANG BERKAITAN DENGAN MANAJERIAL PADA PROYEK KONTRUKSI JALAN DI KABUPATEN ROKAN HULU TABRANI 1 Arifal Hidayat, MT 2 dan Anton Ariyanto, M.Eng 2 Program
Lebih terperinciUNIVERSITAS INDONESIA FAKTOR PENYEBAB TERJADINYA KLAIM YANG MEMPENGARUHI KINERJA WAKTU PROYEK KONSTRUKSI JALAN TOL DI JABODETABEK TESIS
UNIVERSITAS INDONESIA FAKTOR PENYEBAB TERJADINYA KLAIM YANG MEMPENGARUHI KINERJA WAKTU PROYEK KONSTRUKSI JALAN TOL DI JABODETABEK TESIS ANDREAS PARTOGI PASARIBU 0706304965 FAKULTAS TEKNIK PROGRAM PASCASARJANA
Lebih terperinciANALISIS PENGARUH BEBAN KERJA, STRES KERJA DAN MOTIVASI TERHADAP KINERJA KARYAWAN PADA PT. HSP ACADEMY
ANALISIS PENGARUH BEBAN KERJA, STRES KERJA DAN MOTIVASI TERHADAP KINERJA KARYAWAN PADA PT. HSP ACADEMY Dwi Putri Rahmadini, Idi Setyo Utomo Binus University, Jln. Kebon Jeruk Raya No. 21 Kemanggisan /
Lebih terperinciBAB I PENDAHULUAN. 1.1 Latar Belakang
BAB I PENDAHULUAN 1.1 Latar Belakang Proyek adalah aktivitas sementara dari personil, material, serta sarana untuk menjadikan/mewujudkan sasaran-sasaran proyek dalam kurun waktu tertentu yang kemudian
Lebih terperinciANALISIS FAKTOR-FAKTOR DOMINAN PENYEBAB KETERLAMBATAN PROYEK KONSTRUKSI BANGUNAN APARTEMEN X BANDUNG
SKRIPSI ANALISIS FAKTOR-FAKTOR DOMINAN PENYEBAB KETERLAMBATAN PROYEK KONSTRUKSI BANGUNAN APARTEMEN X BANDUNG ARIE RAHAYU P. NPM: 2012410017 PEMBIMBING: Theresita Herni Setiawan, Ir., MT. UNIVERSITAS KATOLIK
Lebih terperinciBAB III METODOLOGI PENELITIAN
BAB III METODOLOGI PENELITIAN 3.1 Pendahuluan Metode penelitian yang digunakan dalam penelitian ini adalah metode analisis deskriptif yaitu penelitian dengan mengumpulkan data primer dan data sekunder.
Lebih terperinciHALAMAN JUDUL HALAMAN PERNYATAAN...
DAFTAR ISI HALAMAN JUDUL HALAMAN PERNYATAAN... i LEMBAR PENGESAHAN LAPORAN TUGAS AKHIR... ii ABSTRAK... iii UCAPAN TERIMA KASIH... iv DAFTAR ISI... v DAFTAR TABEL... viii DAFTAR GAMBAR... ix BAB I PENDAHULUAN
Lebih terperinciANALISIS KONSEP CADANGAN WAKTU PADA PENJADWALAN PROYEK DENGAN CRITICAL PATH METHOD (CPM) (Studi Kasus : Proyek Pembangunan Rumah Sakit Prima)
ANALISIS KONSEP CADANGAN WAKTU PADA PENJADWALAN PROYEK DENGAN CRITICAL PATH METHOD (CPM) (Studi Kasus : Proyek Pembangunan Rumah Sakit Prima) Gea Geby Aurora Syafridon 1 dan Syahrizal 2 1 Departemen Teknik
Lebih terperinciANALISIS FAKTOR-FAKTOR PENGHAMBAT YANG BERPENGARUH TERHADAP WAKTU PROYEK IRIGASIDI PROVINSI ACEH
ISSN 2088-9321 ISSN e-2502-5295 pp. 259-268 ANALISIS FAKTOR-FAKTOR PENGHAMBAT YANG BERPENGARUH TERHADAP WAKTU PROYEK IRIGASIDI PROVINSI ACEH Anita Rauzana 1, Gunawan 2, Masimin 3 1,3) Jurusan Teknik Sipil,
Lebih terperinciBAB V KESIMPULAN DAN SARAN. Berdasarkan data kuesioner yang diberikan kepada 41 responden,
BAB V KESIMPULAN DAN SARAN 5.1. Kesimpulan Berdasarkan data kuesioner yang diberikan kepada 41 responden, penelitian tentang analisis faktor-faktor penyebab keterlambatan pelaksanaan pekerjaan proyek konstruksi
Lebih terperinciANALISIS PENGARUH FAKTOR-FAKTOR KOMPETENSI PROJECT MANAGER TERHADAP KEBERHASILAN PROYEK KONSTRUKSI SUNGAI PADA DINAS PENGAIRAN ACEH
ISSN 2088-9321 ISSN e-2502-5295 pp. 317-328 ANALISIS PENGARUH FAKTOR-FAKTOR KOMPETENSI PROJECT MANAGER TERHADAP KEBERHASILAN PROYEK KONSTRUKSI SUNGAI PADA DINAS PENGAIRAN ACEH Safrial 1, Masimin 2, Anita
Lebih terperinciBAB I PENDAHULUAN. Dalam pekerjaan proyek konstruksi, waktu (time) adalah salah satu
BAB I PENDAHULUAN 1.1 Latar Belakang Dalam pekerjaan proyek konstruksi, waktu (time) adalah salah satu elemen penting di samping elemen lainnya seperti biaya (cost), dan kualitas (quality). Keterlambatan
Lebih terperinciKata Kunci : Peningkatan Biaya, Analisis Faktor, Faktor Peningkatan Biaya
ABSTRAK Peningkatan biaya merupakan biaya pelaksanaan yang melebihi dari biaya perencanaan proyek. Dimana penyelenggaraan proyek memerlukan pertimbangan yang matang untuk mencapai keberhasilan. Dari kondisi
Lebih terperinciBAB V KESIMPULAN DAN SARAN. Dari hasil penelitian mengenai construction waste yang telah dilakukan melalui
BAB V KESIMPULAN DAN SARAN 5.1. Kesimpulan Dari hasil penelitian mengenai construction waste yang telah dilakukan melalui penyebaran kuesioner dengan responden yang berasal dari kontraktor yang sedang
Lebih terperinciANALISIS FAKTOR-FAKTOR YANG DAPAT MENGUBAH METODE PELAKSANAAN KERJA PADA PROYEK-PROYEK KONSTRUKSI DI KOTA MEDAN LAPORAN
ANALISIS FAKTOR-FAKTOR YANG DAPAT MENGUBAH METODE PELAKSANAAN KERJA PADA PROYEK-PROYEK KONSTRUKSI DI KOTA MEDAN LAPORAN Disusun sebagai Satu Syarat untuk Menyelesaikan Matakuliah Tugas Akhir pada Program
Lebih terperinciANALISIS FAKTOR FAKTOR YANG MEMPENGARUHI COST OVERRUNS PADA PROYEK KONSTRUKSI DI SURABAYA
ANALISIS FAKTOR FAKTOR YANG MEMPENGARUHI COST OVERRUNS PADA PROYEK KONSTRUKSI DI SURABAYA ANALYSIS OF FACTORS - FACTORS AFFECTING THE COST OVERRUNS ON CONSTRUCTION PROJECTS IN SURABAYA Ari Swezni, Retno
Lebih terperinciANALISIS FAKTOR PENYEBAB TERJADINYA TUNTUTAN (CLAIM) PADA PROYEK KONSTRUKSI
ANALISIS FAKTOR PENYEBAB TERJADINYA TUNTUTAN (CLAIM) PADA PROYEK KONSTRUKSI TUGAS AKHIR Oleh : Nia Monita Sari 1104105008 JURUSAN TEKNIK SIPIL FAKULTAS TEKNIK UNIVERSITAS UDAYANA 2015 ABSTRAK Klaim konstruksi
Lebih terperinciBAB II TINJAUAN PUSTAKA Factors Influencing Contractor Performance in Indonesia: A Study of Non Value-Adding Activities
BAB II TINJAUAN PUSTAKA 2.1. Factors Influencing Contractor Performance in Indonesia: A Study of Non Value-Adding Activities Alwi et al. (2002) melakukan studi mengenai non value adding activities pada
Lebih terperinciMANAJEMEN RISIKO DALAM PROSES ESTIMASI BIAYA PADA PROYEK KONSTRUKSI GEDUNG BERTINGKAT DI KOTA DENPASAR
TESIS MANAJEMEN RISIKO DALAM PROSES ESTIMASI BIAYA PADA PROYEK KONSTRUKSI GEDUNG BERTINGKAT DI KOTA DENPASAR IDA AYU PRANITI TRESNA PUTRI PROGRAM PASCASARJANA UNIVERSITAS UDAYANA DENPASAR 2015 TESIS MANAJEMEN
Lebih terperinciIDENTIFIKASI FAKTOR DOMINAN YANG BERPENGARUH PADA KEGAGALAN PEMENANGAN TENDER TUGAS AKHIR
IDENTIFIKASI FAKTOR DOMINAN YANG BERPENGARUH PADA KEGAGALAN PEMENANGAN TENDER TUGAS AKHIR Ditulis sebagai Syarat Menyelesaikan Matakuliah Tugas Akhir Semester VIII Program Sarjana Sains Terapan (Diploma
Lebih terperinciBAB II TINJAUAN PUSTAKA. tersebut dibuat (Arditi and Patel, 1989)
BAB II TINJAUAN PUSTAKA 2.1. Teori Penjadwalan Kunci utama keberhasilan melaksanakan proyek tepat waktu adalah perencanaan dan penjadwalan proyek yang lengkap dan tepat. Keterlambatan dapat dianggap sebagai
Lebih terperinciFAKULTAS TEKNIK UNIVERSITAS WIRARAJA SUMENEP - MADURA
PENYEBAB TERJADINYA KETERLAMBATAN WAKTU PENYELESAIAN PROYEK KONSTRUKSI DI DINAS PU. BINA MARGA KABUPATEN SUMENEP Oleh : Subaidillah Fansuri Dosen Fakultas Teknik Universitas Wiraraja (kacongngaebo@yahoo.co.id)
Lebih terperinciANALlSA FAKTOR PENYEBAB KEGAGALAN PROYEK KONSTRUKSI DI INDONESIA STUDI KASUS PT.WIJAYA KARYA (Persero),Tbk
ANALlSA FAKTOR PENYEBAB KEGAGALAN PROYEK KONSTRUKSI DI INDONESIA STUDI KASUS PT.WIJAYA KARYA (Persero),Tbk Adi Irmawanto dan Christiono Utomo Program Studi Magister Manajemen Teknologi Institut Teknologi
Lebih terperinciANALISIS FAKTOR DOMINAN RESIKO BIAYA PADA PELAKSANAAN PROYEK KONSTRUKSI GEDUNG DI SURAKARTA Herman Susila Suryo Handoyo
AALISIS FAKTOR DOMIA RESIKO BIAYA PADA PELAKSAAA PROYEK KOSTRUKSI GEDUG DI SURAKARTA Herman Susila Suryo Handoyo Abstrak Pekerjaan konstruksi merupakan pekerjaan yang banyak mengandung risiko, salah satunya
Lebih terperinciFielda Roza, Alizar Hasan, M. Nursyaifi Yulius Magister Teknik Sipil Pasca Sarjana Universitas Bunga Hatta.
ANALISIS FAKTOR-FAKTOR PENYEBAB KETIDAKTEPATAN PERHITUNGAN BIAYA PROYEK PADA PROSES PERENCANAAN OLEH KONSULTAN PERENCANA (Studi Kasus Konsultan Perencana di Kota Padang) Fielda Roza, Alizar Hasan, M. Nursyaifi
Lebih terperinciABSTRAK KATA PENGANTAR DAFTAR ISI DAFTAR GAMBAR DAFTAR TABEL DAFTAR LAMPIRAN BAB I PENDAHULUAN
DAFTAR ISI ABSTRAK KATA PENGANTAR... i DAFTAR ISI... iii DAFTAR GAMBAR... vi DAFTAR TABEL... vii DAFTAR LAMPIRAN... viii BAB I PENDAHULUAN 1.1 Latar Belakang... 1 1.2 Permasalahan... 3 1.3 Tujuan Studi...
Lebih terperinciANALISIS FAKTOR-FAKTOR PENYEBAB KETERLAMBATAN PELAKSANAAN PROYEK KONSTRUKSI
Konferensi Nasional Teknik Sipil 11 Universitas Tarumanagara, 26-27 Oktober 2017 ANALISIS FAKTOR-FAKTOR PENYEBAB KETERLAMBATAN PELAKSANAAN PROYEK KONSTRUKSI I.A.Rai Widhiawati 1, I G.A.Adnyana Putera 1,
Lebih terperinciANALISA FAKTOR FAKTOR YANG MEMPENGARUHI KONSUMEN DALAM MEMLIH MIE INSTANT
ANALISA FAKTOR FAKTOR YANG MEMPENGARUHI KONSUMEN DALAM MEMLIH MIE INSTANT Heru Saputra 1, Noviyarsi 2, M. Nursyaifi Yulius 3 1,2,3 Jurusan Teknik Industri, Fakultas Teknologi Industri Universitas Bung
Lebih terperinciBAB II TINJAUAN PUSTAKA. kali dilaksanakan dan umumnya berjangka waktu pendek. Dalam rangkaian
BAB II TINJAUAN PUSTAKA 2.1 Proyek Konstruksi Proyek Konstruksi merupakan suatu rangkaian kegiatan yang hanya satu kali dilaksanakan dan umumnya berjangka waktu pendek. Dalam rangkaian kegiatan tersebut,
Lebih terperinciJURNAL ILMIAH TEKNIK INDUSTRI
JURNAL ILMIAH TEKNIK INDUSTRI ANALISIS RISIKO PELAKSANAAN PEKERJAAN MENGGUNAKAN KONTRAK UNIT PRICE (Studi Kasus: Peningkatan dan Pelebaran Aset Infrastruktur Jalan Alai-By Pass Kota Padang Sebagai Jalur
Lebih terperinciANALISIS FAKTOR-FAKTOR PENYEBAB KETERLAMBATAN PELAKSANAAN PROYEK KONSTRUKSI DI KABUPATEN BULELENG
ANALISIS FAKTOR-FAKTOR PENYEBAB KETERLAMBATAN PELAKSANAAN PROYEK KONSTRUKSI DI KABUPATEN BULELENG TUGAS AKHIR Oleh : Ni Kadek Lia Arista 1204105007 JURUSAN TEKNIK SIPIL FAKULTAS TEKNIK UNIVERSITAS UDAYANA
Lebih terperinciANALISIS FAKTOR-FAKTOR YANG MEMPENGARUHI KINERJA MUTU PADA PROYEK KONSTRUKSI GEDUNG DI KOTA PADANG PANJANG
ANALISIS FAKTOR-FAKTOR YANG MEMPENGARUHI KINERJA MUTU PADA PROYEK KONSTRUKSI GEDUNG DI KOTA PADANG PANJANG ARTIKEL SURYA EKA PRIANA NIM. 1210018312024 PROGRAM STUDI TEKNIK SIPIL ANALISIS FAKTOR-FAKTOR
Lebih terperinciABSTRAK ABSTRACT. Fatoni Azis Teknik Industri, Universitas 17 Agustus 1945 Surabaya
PERBANDINGAN PELAKSANAAN PROYEK PEMBANGUNAN LIFT BARANG DUA LANTAI DENGAN METODE CRITICAL PATH METHOD (CPM) (Studi Kasus : CV. Prisma Tehnik Gemilang Gresik) Fatoni Azis Teknik Industri, Universitas 17
Lebih terperinciANALISIS RISIKO PENAWARAN UNDERESTIMATE COST TERHADAP KUALITAS PROYEK KONSTRUKSI JALAN DI PROVINSI ACEH
ISSN 2088-9321 ISSN e-2502-5295 pp. 511-520 ANALISIS RISIKO PENAWARAN UNDERESTIMATE COST TERHADAP KUALITAS PROYEK KONSTRUKSI JALAN DI PROVINSI ACEH Hamdani 1, M. Isya 2, Hafnidar A. Rani 3 1) Mahasiswa
Lebih terperinciANALISA PENGARUH RENDAHNYA KUALITAS SUMBER DAYA MANUSIA TERHADAP KINERJA PROYEK DI SURABAYA
ANALISA PENGARUH RENDAHNYA KUALITAS SUMBER DAYA MANUSIA TERHADAP KINERJA PROYEK DI SURABAYA Soelistyono 1) Program Studi Pascasarjana Teknik Sipil, Institut Teknologi Sepuluh Nopember, Jl. Kampus ITS Sukolilo,
Lebih terperinciDAFTAR PUSTAKA. Hamzah,Muzadir Analisis Faktor Penyebab Keterlambata Penyelesaian Proyek Konstruksi. Jakarta.Uni. Bung Hatta.
DAFTAR PUSTAKA Ariefasa,Ryan. 2011. Faktor Penyebab Keterlambatan Pekerjaan Konstruksi Bangunan Gedung Bertingkat yang Berpengaruh terhadap Perubahan Anggaran Biaya pada Pekerjaan Struktur. Jakarta.UI-press.
Lebih terperinciGARIS BESAR PROGRAM PEMBELAJARAN (GBPP)
GARIS BESAR PROGRAM (GBPP) Mata Kuliah : Manajemen Konstruksi Kode Mata Kuliah : KT 411307 Semester/SKS : V/2 Penanggung Jawab Mata Kuliah : Murdini, Ir, MT Deskripsi Singkat : Mata kuliah ini membahas
Lebih terperinciPenelitian menggunakan alat ukur berupa kuesioner, dengan penilaian 6 tingkat dengan norma sebagai berikut:
Lampiran 1. Pengolahan data statistik Survei dilakukan kepada para karyawan di kantor pos pasar baru, dengan sampel sebanyak 50 karyawan. Kantor ini dipilih karena tidak hanya merupakan kantor cabang saja,
Lebih terperinciKata kunci: Evaluasi Proyek, Konsep Nilai Hasil, ACWP, BCWS, BCWP
ABSTRAK Adanya pembangunan konstruksi yang tidak sesuai dengan rencana, maka pelaksanaan dari proyek konstruksi perlu mendapat perhatian. Untuk mengatasi hal tersebut diperlukan suatu metode yang dapat
Lebih terperinciANALISIS KINERJA PROYEK PEMBANGUNAN RUANG KELAS BARU SMKN 6 BALIKPAPAN
ANALISIS KINERJA PROYEK PEMBANGUNAN RUANG KELAS BARU SMKN 6 BALIKPAPAN Noviar 1, Anang Yahya 2 1 Mahasiswa Prodi Studi Teknik Sipil, Universitas Balikpapan 2 Dosen Prodi Teknik Sipil, Universitas Balikpapan
Lebih terperinciBAB V KESIMPULAN DAN SARAN. rapat internal mingguan proyek konstruksi dan hal yang dibahas dalam rapat
BAB V KESIMPULAN DAN SARAN 5.1 Kesimpulan Penelitian mengenai analisis faktor-faktor yang menyebabkan diadakannya rapat internal mingguan proyek konstruksi dan hal yang dibahas dalam rapat internal proyek
Lebih terperinciBAB I PENDAHULUAN. I.1 Latar Belakang
BAB I PENDAHULUAN I.1 Latar Belakang Industri konstruksi merupakan salah satu komponen penting dalam perekonomian bangsa, dimana konstribusi industri konstruksi akan meningkat sejalan dengan kemajuan perekonomian
Lebih terperinciSTUDI PERSEPSI FAKTOR-FAKTOR PENYEBAB KLAIM PADA PELAKSANAAN PROYEK KONSTRUKSI BANGUNAN GEDUNG
Konferensi Nasional Teknik Sipil 4 (KoNTekS 4) Sanur-Bali, 2-3 Juni 2010 STUDI PERSEPSI FAKTOR-FAKTOR PENYEBAB KLAIM PADA PELAKSANAAN PROYEK KONSTRUKSI BANGUNAN GEDUNG Wahida Handayani 1, Yohanes Lim Dwi
Lebih terperinciSTUDI PERENCANAAN WAKTU DAN BIAYA BLOCK OFFICE PEMERINTAH KOTA BATU MALANG ABSTRAK
STUDI PERENCANAAN WAKTU DAN BIAYA BLOCK OFFICE PEMERINTAH KOTA BATU MALANG ABSTRAK Perusahaan dalam menjalankan proyek seringkali mengalami kesulitan atau kendala-kendala seperti tanah yang tidak labil,
Lebih terperinciPOLITEKNIK NEGERI MEDAN
ANALISIS FAKTOR-FAKTOR YANG MEMPENGARUHI KONTRAKTOR DALAM MENGIKUTI PELELANGAN PEKERJAAN KONSTRUKSI DI KOTA MEDAN Ditulis untuk Menyelesaikan Matakuliah Tugas Akhir Semester VIII Program Studi D-IV MRKG
Lebih terperinciBAB III METODE ANALISIS
BAB III METODE ANALISIS 3.1. Uraian Umum Metode penelitian yang digunakan dalam penelitian ini adalah metode analisis deskriptif yaitu suatu metode yang berfungsi untuk mendeskripsikan atau memberi gambaran
Lebih terperinciSURVEI MENGENAI BIAYA OVERHEAD SERTA FAKTOR-FAKTOR YANG MEMPENGARUHINYA
SURVEI MENGENAI BIAYA OVERHEAD SERTA FAKTOR-FAKTOR YANG MEMPENGARUHINYA Henry Pascal Magaline 1, Alvin Januar Haryono 2, Andi 3 ABSTRAK : Biaya overhead sebuah proyek merupakan salah satu unsur harga pokok
Lebih terperinciKata kunci : Perubahan biaya, Faktor, Regresi, Korelasi
ABSTRAK Pelaksanaan proyek konstruksi tidak luput dari masalah-masalah yang harus dihadapi, salah satunya adalah perubahan biaya. Perubahan biaya pelaksanaan proyek terhadap perubahan rencana anggaran
Lebih terperinciKata kunci: perbandingan biaya, penambahan tenaga kerja, jam kerja (kerja lembur), time cost trade off
ABSTRAK Pelaksanaan proyek konstruksi sering kali ditemukan masalah-masalah seperti penyelesaian proyek yang tidak sesuai dengan kontrak atau terlambat dari yang telah direncanakan di dalam kontrak. Faktor-
Lebih terperinciPERENCANAAN DAN PENGENDALIAN JADWAL DENGAN MENGGUNAKAN PROGRAM MICROSOFT PROJECT 2010 (Studi Kasus: Proyek PT. Trakindo Utama)
PERENCANAAN DAN PENGENDALIAN JADWAL DENGAN MENGGUNAKAN PROGRAM MICROSOFT PROJECT 2010 (Studi Kasus: Proyek PT. Trakindo Utama) David M. Walean R.J.M. Mandagi., J. Tjakra, G.Y. Malingkas Fakultas Teknik,
Lebih terperinciBAB V KESIMPULAN DAN SARAN. Berdasarkan rincian pada bab IV, maka pada bab V ini dapat disimpulkan
46 BAB V KESIMPULAN DAN SARAN 5.1. Kesimpulan Berdasarkan rincian pada bab IV, maka pada bab V ini dapat disimpulkan sebagai berikut: 5.1.1. Faktor-faktor yang mempengaruhi keterlambatan kerja a. Faktor
Lebih terperinciPENGARUH KUALITAS MANAJEMEN KOMUNIKASI ANTARA KONTRAKTOR DAN KONSULTAN TERHADAP KEBERHASILAN PROYEK JALAN DI LINGKUNGAN KOTA BARU PARAHYANGAN
SKRIPSI PENGARUH KUALITAS MANAJEMEN KOMUNIKASI ANTARA KONTRAKTOR DAN KONSULTAN TERHADAP KEBERHASILAN PROYEK JALAN DI LINGKUNGAN KOTA BARU PARAHYANGAN JONATHAN WESLEY NPM : 2013410057 PEMBIMBING: Theresita
Lebih terperinciSTUDI TINGKAT KEMATANGAN MANAJEMEN PROYEK PADA PERUSAHAAN KONTRAKTOR DI PROPINSI MALUKU
STUDI TINGKAT KEMATANGAN MANAJEMEN PROYEK PADA PERUSAHAAN KONTRAKTOR DI PROPINSI MALUKU Dirk Eduard Tomaluweng Yulvi Zaika Indradi Wijatmiko Program Pascasarjana Teknik Sipil (S-2) Universitas Brawijaya
Lebih terperinciBAB V PENUTUP. kontraktor adalah mendekati waktu penyelesaian proyek. lembur menurut tukang adalah Gaji atau upah pekerja.
38 BAB V PENUTUP 5.1 KESIMPULAN Berdasarkan pembahasan yang telah dilakukan, dapat ditarik kesimpulan sebagai berikut : 1. Faktor yang paling dominan mempengaruhi terjadinya kerja lembur menurut pemilik
Lebih terperinciBAB III METODE PENELITIAN
BAB III METODE PENELITIAN 3.1 Metodologi Penelitian Metodologi penelitian merupakan alur pemikiran yang ditempuh dalam menentukan analisis metode dari penelitian ini. Untuk mendapat data di dalam penelitian
Lebih terperinciTESIS STUDI MENGENAI HUBUNGAN KARAKTERISTIK DAN KINERJA PERUSAHAAN KONTRAKTOR KUALIFIKASI KECIL DI DAERAH ISTIMEWA YOGYAKARTA
TESIS STUDI MENGENAI HUBUNGAN KARAKTERISTIK DAN KINERJA PERUSAHAAN KONTRAKTOR KUALIFIKASI KECIL DI DAERAH ISTIMEWA YOGYAKARTA ALBERTUS DWI CHRISTIAWAN No. Mhs : 12 51 01895/PS/MTS PROGRAM STUDI MAGISTER
Lebih terperinciLampiran 1. Kuesioner Achievement Goal Orientation dan Data Penunjang
Lampiran 1. Kuesioner Achievement Goal Orientation dan Data Penunjang KUESIOER ACHIEVEMET GOAL ORIETATIO Pernyataan-pernyataan berikut di bawah ini merupakan gambaran dirimu dalam belajar. Berikan jawabanmu
Lebih terperinciAnalisis Faktor-faktor yang Mempengaruhi Sisa Hasil Usaha Pada Koperasi Pegawai Negeri Niaga Artha Sari Singaraja
Analisis Faktor-faktor yang Mempengaruhi Sisa Hasil Usaha Pada Koperasi Pegawai Negeri Niaga Artha Sari Singaraja Ade Dharma Putra1, Made Artana1, Luh Indrayani2 Jurusan Pendidikan Ekonomi Universitas
Lebih terperinciANALISA FAKTOR FAKTOR YANG MEMPENGARUHI COST OVERRUNS (Pembengkakan Biaya ) PADA PROYEK- PROYEK PT.MECO INOXPRIMA
ANALISA FAKTOR FAKTOR YANG MEMPENGARUHI COST OVERRUNS (Pembengkakan Biaya ) PADA PROYEK- PROYEK PT.MECO INOXPRIMA Imam Kholiq Universitas Wijaya Putra kholiqimam@gmail.com ABSTRAK Proyek pembuatan Plan
Lebih terperinciHalaman KATA PENGANTAR... DAFTAR ISI... DAFTAR TABEL... DAFTAR GAMBAR... DAFTAR LAMPIRAN...
D A F T A R I S I KATA PENGANTAR... DAFTAR ISI... DAFTAR TABEL... DAFTAR GAMBAR...... DAFTAR LAMPIRAN... i iii v vi vii I. PENDAHULUAN... 1 1.1. Latar Belakang..... 1 1.2. Perumusan Masalah..... 5 1.3.
Lebih terperinciAbstract. Keywords: perception, working discipline, productivity. Universitas Kristen Maranatha
Employee s Perception Toward 5 Days Work Time Policy and Its Influence to The Working Discipline and Productivity Study On Non Medical Employees At Cicendo Eye Hospital Bandung Abstract This research try
Lebih terperinciANALISA RISIKO PELAKSANAAN PROYEK APARTEMEN PUNCAK KERTAJAYA SURABAYA
ANALISA RISIKO PELAKSANAAN PROYEK APARTEMEN PUNCAK KERTAJAYA SURABAYA Bagus Prasetyo Budi 3108100042 Dosen Pembimbing Ir. I Putu Artama Wiguna, MT, Ph.D. JURUSAN TEKNIK SIPIL Fakultas Teknik Sipil dan
Lebih terperinciFAKTOR-FAKTOR PRODUKTIVITAS TENAGA KERJA OUTSOURCING/TENAGA KONTRAK YANG MEMPENGARUHI KINERJA WAKTU DALAM PROYEK KONSTRUKSI
Lampiran 1 : Kuesioner Pakar FAKTOR-FAKTOR PRODUKTIVITAS TENAGA KERJA OUTSOURCING/TENAGA KONTRAK YANG MEMPENGARUHI KINERJA WAKTU DALAM PROYEK KONSTRUKSI KUESIONER PENELITIAN TESIS (VALIDASI PAKAR) OLEH
Lebih terperinciBAB I PENDAHULUAN. 1.1 Latar Belakang. Indonesia merupakan negara berkembang yang sedang marak dengan
BAB I PENDAHULUAN 1.1 Latar Belakang Indonesia merupakan negara berkembang yang sedang marak dengan pembangunannya. Hal ini terlihat dari banyaknya proyek-proyek konstruksi di Indonesia yang sedang dikerjakan
Lebih terperinciTESIS PENGARUH KARAKTERISTIK TUKANG BATU LOKAL TERHADAP PRODUKTIVITAS
TESIS PENGARUH KARAKTERISTIK TUKANG BATU LOKAL TERHADAP PRODUKTIVITAS Oleh : JOAO MIRELES MARIANO NPM. : 14 51 02283/PS/MTS PROGRAM STUDI MAGISTER TEKNIK SIPIL PROGRAM PASCASARJANA UNIVERSITAS ATMA JAYA
Lebih terperinciBAB III...19 RENCANA KEGIATAN...19
DAFTAR ISI ABSTRAK... i UCAPAN TERIMA KASIH... ii DAFTAR ISI... iii DAFTAR TABEL... v DAFTAR GAMBAR... vi BAB I...1 PENDAHULUAN...1 1.1 Latar Belakang... 1 1.2 Rumusan Masalah... 2 1.3 Tujuan Penelitian...
Lebih terperinciTESIS ANALISIS FAKTOR YANG MEMPENGARUHI KINERJA KARYAWAN PADA PT. JAYA KUSUMA SARANA ANGGA ADITYA ARYA WAHYUDI
TESIS ANALISIS FAKTOR YANG MEMPENGARUHI KINERJA KARYAWAN PADA PT. JAYA KUSUMA SARANA ANGGA ADITYA ARYA WAHYUDI 1391561018 PROGRAM MAGISTER PROGRAM STUDI TEKNIK SIPIL PROGRAM PASCASARJANA UNIVERSITAS UDAYANA
Lebih terperinciBAB I PENDAHULUAN. pembangunan disegala bidang, baik pembangunan dibidang struktur maupun non
BAB I PENDAHULUAN 1.1. Latar Belakang Sebagai negara berkembang, Indonesia saat ini telah menggalakkan pembangunan disegala bidang, baik pembangunan dibidang struktur maupun non struktur. Di Yogyakarta
Lebih terperinciIDENTIFIKASI DAN KAJIAN TERHADAP FAKTOR-FAKTOR PENENTU KEPUASAN KERJA PADA BERBAGAI TINGKATAN PEKERJA PERUSAHAAN KONTRAKTOR TESIS MAGISTER
IDENTIFIKASI DAN KAJIAN TERHADAP FAKTOR-FAKTOR PENENTU KEPUASAN KERJA PADA BERBAGAI TINGKATAN PEKERJA PERUSAHAAN KONTRAKTOR TESIS MAGISTER OLEH : HESTIYANI NIM : 25099048 PROGRAM PASCASARJANA PROGRAM STUDI
Lebih terperinciPENILAIAN KUALIFIKASI PENGETAHUAN DAN KETERAMPILAN MANDOR PADA BANGUNAN GEDUNG DI MEDAN BERDASARKAN SKKNI
PENILAIAN KUALIFIKASI PENGETAHUAN DAN KETERAMPILAN MANDOR PADA BANGUNAN GEDUNG DI MEDAN BERDASARKAN SKKNI Nadya Yessi Utami 1 dan Syahrizal 2 1 Departemen Teknik Sipil, Universitas Sumatera Utara (USU)
Lebih terperinciBAB I PENDAHULUAN. cepat dari waktu yang dijadwalkan, dan dengan tercapainya mutu. Dampak dari
BAB I PENDAHULUAN 1.1 Latar Belakang Keberhasilan proyek merupakan sasaran utama bagi perusahaanperusahaan yang bergerak dibidang jasa konstruksi. Proyek yang dikatakan berhasil merupakan cerminan dari
Lebih terperinciBAB VI KEMAJUAN PEKERJAAN DAN PENGENDALIAN PROYEK
BAB VI KEMAJUAN PEKERJAAN DAN PENGENDALIAN PROYEK 6.1. Pengelolaan Waktu Pelaksanaan Proyek Sebagai Kontraktor Utama pembangunan Proyek One Sentosa Apartement PT. Adhi Persada Gedung harus membuat perencanaan
Lebih terperinciANALISIS FAKTOR-FAKTOR PENYEBAB KETERLAMBATAN PADA PROYEK KONSTRUKSI PEMERINTAH DAN SWASTA DI TIMOR LESTE
THESIS ANALISIS FAKTOR-FAKTOR PENYEBAB KETERLAMBATAN PADA PROYEK KONSTRUKSI PEMERINTAH DAN SWASTA DI TIMOR LESTE SONIA ELISABETH VIEIRA ANICETO. No. Mhs : 135101972/PS/MTS PROGRAM STUDI MAGISTER TEKNIK
Lebih terperinciPOLITEKNIK NEGERI MEDAN
ANALISIS PENYEBAB KETERLAMBATAN PENYELESAIAN PEKERJAAN PROYEK KONSTRUKSI (BANGUNAN GEDUNG) PEMERINTAH DI KABUPATEN NIAS TUGAS AKHIR Ditulis sebagai salah satu syarat untuk memperoleh gelar SARJANA SAINS
Lebih terperinciANALISIS FAKTOR-FAKTOR YANG MEMPENGARUHI KETERLAMBATAN PADA PROYEK PEMERINTAHAN DI KOTA KUPANG
ANALISIS FAKTOR-FAKTOR YANG MEMPENGARUHI KETERLAMBATAN PADA PROYEK PEMERINTAHAN DI KOTA KUPANG Sebastinus Baki Henong Universitas Katolik Widya Mandira Kupang Email :henongsipilunwira15@gmail.com ABSTRAK
Lebih terperinciBAB II TINJAUAN PUSTAKA. Usaha Jasa Pelaksana Konstruksi adalah jenis usaha jasa konstruksi
BAB II TINJAUAN PUSTAKA 2.1 Jasa Konstruksi Usaha Jasa Pelaksana Konstruksi adalah jenis usaha jasa konstruksi yang menyediakan layanan jasa pelaksanaan pekerjaan konstruksi, yang dibedakan menurut bentuk
Lebih terperinciBAB III METODOLOGI PENELITIAN
BAB III METODOLOGI PENELITIAN Metodologi penelitian merupakan landasan berpijak agar proses penelitian berjalan secara sistematis, teratur dan terarah. Metodologi penelitian ini terdiri dari tahapan-tahapan
Lebih terperinciKuesioner Penelitian Skripsi Analisis Proses Keputusan Pembelian Produk Perawatan Tubuh Kendedes Princess Ritual
LAMPIRAN Kuesioner Penelitian Skripsi Analisis Proses Keputusan Pembelian Produk Perawatan Tubuh Kendedes Princess Ritual dan Faktor-faktor yang Mempengaruhi Pembelian di Martha Tilaar Salon Day Spa Bogor
Lebih terperinciFaktor-Faktor Penentu Dalam Berbelanja Secara Online
Wijaya / Faktor-Faktor Penentu Dalam Berbelanja Secara Online/ Jurnal Titra, Vol., No., Januari, pp. - Faktor-Faktor Penentu Dalam Berbelanja Secara Online Ronald Alexander Wijaya, Nyoman Sutapa Abstract:
Lebih terperinciSTUDI MENGENAI MODEL ESTIMASI DURASI KONSTRUKSI BANGUNAN GEDUNG
Konferensi Nasional Teknik Sipil I (KoNTekS I) Universitas Atma Jaya Yogyakarta Yogyakarta, 11 12 Mei 2007 STUDI MENGENAI MODEL ESTIMASI DURASI KONSTRUKSI BANGUNAN GEDUNG Peter F. Kaming 1, F.. Junaedi
Lebih terperinciPERCEPATAN WAKTU PELAKSANAAN PROYEK GEDUNG PERPUSTAKAAN POLITEKNIK NEGERI BANYUWANGI DENGAN METODE LEAST COST ANALYSIS
Jurnal Info Manpro PERCEPATAN WAKTU PELAKSANAAN PROYEK GEDUNG PERPUSTAKAAN POLITEKNIK NEGERI BANYUWANGI DENGAN METODE LEAST COST ANALYSIS Dimas Aji Purnomo (1) Lalu Mulyadi (2) Edi Hargono (3) (1)(2)(3)
Lebih terperinciANALISIS FAKTOR YANG MEMPENGARUHI TENAGA KERJA KONSTRUKSI UNTUK MEMILIKI SKA/SKTK PADA KONTRAKTOR DI KABUPATEN BADUNG
ANALISIS FAKTOR YANG MEMPENGARUHI TENAGA KERJA KONSTRUKSI UNTUK MEMILIKI SKA/SKTK PADA KONTRAKTOR DI KABUPATEN BADUNG I M. Jelantik 1, I M. Alit K. Salain 2, Mayun Nadiasa 3 Abstrak : Undang-undang Jasa
Lebih terperinciIDENTIFIKASI INDIKATOR PENERAPAN GREEN CONSTRUCTION PADA PROYEK KONSTRUKSI GEDUNG DI KOTA BANDA ACEH
ISSN 2302-0253 7 Pages pp. 101-107 IDENTIFIKASI INDIKATOR PENERAPAN GREEN CONSTRUCTION PADA PROYEK KONSTRUKSI GEDUNG DI KOTA BANDA ACEH Muhammad Furqan 1, T. Budi Aulia 2, Hafnidar A. Rani 3 1) Magister
Lebih terperinciISSN No [ JURNAL TEKNIKA VOL 7 NO 1 MARET 2015]
ANALISIS PENGENDALIAN BIAYA DAN WAKTU DENGAN KONSEP NILAI HASIL (EARNED VALUE) (Studi Kasus : Fabrikasi Steel Structure Slag Gresik) Dwi Kartikasari*) *) Dosen Prodi Teknik Sipil Fakultas Teknik Universitas
Lebih terperinci