KAJIAN PRODUKTIVITAS PADA PEKERJAAAN PENUTUP ATAP

Ukuran: px
Mulai penontonan dengan halaman:

Download "KAJIAN PRODUKTIVITAS PADA PEKERJAAAN PENUTUP ATAP"

Transkripsi

1

2 KAJIAN PRODUKTIVITAS PADA PEKERJAAAN PENUTUP ATAP Mubarak 1, Fachrurrazi 2, Nurul Malahayati 3, Muhammad Gazi Ansari 4 1,2,3) Jurusan Teknik Sipil, Fakultas Teknik, Universitas Syiah Kuala Jl. Tgk. Syeh Abdul Rauf No. 7, Darussalam Banda Aceh 23111, mubarak@unsyiah.ac.id, fachrurrazi.unsyiah@gmail.com, malahayatijj@yahoo.com 4) Mahasiswa Jurusan Teknik Sipil, Fakultas Teknik, Universitas Syiah Kuala Jl. Tgk. Syeh Abdul Rauf No. 7, Darussalam Banda Aceh 23111, muhammadgaziansari@gmail.com Abstract: Productivity is one of the important factors in determining the success of a construction work. Increased productivity will reduce working time, and that means it will reduce costs. In general, the value of productivity determined by the amount of volume of work, the carrying time, and the number of labor. So that the work can be completed properly, the necessary planning efforts with regard to these factors. Therefore, this study was conducted to determine the value of productivity of a building roof. The object of study is located on the project of the Education Building and Lecture Hall of the Faculty of Engineering of the University of Siyah Kuala. Roofing material using zincalume. The volume of work planned area of 1,513.5 m 2 roof. The study was conducted through field observation by noting the volume of work, the duration of each phase of the work, and the amount of labour involved. The analysis result that the values obtained for work productivity of installation of roof are m 2 /hr or m 2 /day and installation of roof ridge are m/hr or m/day. Keywords: productivity, work, building, roof covering, zincalume. Abstrak: Produktivitas merupakan salah satu faktor penting dalam menentukan keberhasilan suatu pekerjaan konstruksi. Peningkatan produktivitas akan mengurangi waktu pekerjaan, dan itu berarti akan mereduksi biaya. Secara umum, nilai produktivitas ditentukan oleh faktor besaran volume pekerjaan, waktu pelaksanaan, dan jumlah tenaga kerja. Agar pekerjaan dapat diselesaikan dengan baik, diperlukan upaya perencanaan dengan memperhatikan faktor-faktor tersebut. Untuk itu, penelitian ini dilakukan untuk mengetahui nilai produktivitas pada salah satu komponen pekerjaan bangunan gedung yaitu pekerjaan penutup atap. Objek yang diteliti adalah pekerjaan pemasangan penutup atap pada proyek Gedung Pendidikan dan Ruang Kuliah Fakultas Teknik Universitas Syiah Kuala. Material atap menggunakan bahan zincalume. Volume pekerjaan atap direncanakan seluas 1.513,5 m 2. Penelitian dilakukan melalui observasi lapangan dengan mencatat langsung volume pekerjaan, durasi setiap tahap pekerjaan, dan jumlah tanaga kerja yang terlibat. Hasil analisis menunjukkan bahwa nilai produktivitas untuk pekerjaan pemasangan atap diperoleh sebesar 21,502 m 2 /jam atau 150,51 m 2 /hari dan untuk pekerjaan pemasangan rabung atap diperoleh sebesar 13,339 m/jam atau 93,37 m/hari. Kata kunci : produktivitas, pekerjaan, gedung, penutup atap, zincalume. PENDAHULUAN Penyelesaian sebuah konstruksi bangunan gedung dilakukan dalam tahapan-tahapan menurut komponen pekerjaan. Secara umum, komponen tersebut dapat dikelompokkan menjadi komponen struktural dan komponen non-struktural (Anonim, 2007). Komponen struktural berkaitan dengan bagian dari konstruksi yang berfungsi menahan dan meneruskan beban bangunan, sedang komponen non-struktural berkaitan dengan kompo- 133

3 nen arsitektur dan utilitas bangunan. Pelaksanaan pekerjaan konstruksi yang terencana dengan baik merupakan salah satu upaya mencapai kesuksesan penyelesaian sebuah proyek konstruksi. Perencanaan tersebut umumnya berkaitan dengan penyediaan sumber daya proyek, seperti tenaga kerja, material dan peralatan, dan berbagai sumber daya proyek lainnya. Pada tahap pelaksanaan, sinergi antar sumber daya tersebut akan menghasilkan sebuah produktivitas kerja, yang akan menjadi salah satu tolok ukur dalam bagi kesuksesan penyelesaian sebuah proyek. Peningkatan atau penurunan nilai produktivitas sangat ditentukan oleh kemampuan tenaga kerja yang terlibat dalam menyelesaikan suatu pekerjaan dalam kurun waktu tertentu. Produktivitas akan meningkat jika volume sebuah pekerjaan dapat diselesaikan lebih cepat dari target waktu yang ditentukan dan demikian pula sebaliknya. Secara umum, nilai produktivitas ditentukan oleh faktor besaran volume pekerjaan, waktu pelaksanaan, dan jumlah tenaga kerja. Agar pekerjaan dapat diselesaikan dengan baik, diperlukan upaya perencanaan dengan memperhatikan faktor-faktor tersebut. Kajian mengenai produktivitas sangat diperlukan terutama bila dikaitkan dengan proses standarisasi kebutuhan material, tenaga kerja, dan peralatan untuk sebuah pekerjaan. Standar tersebut akan menjadi pedoman bagi seorang perencana, baik dalam perencanaan anggaran maupun dalam perencanaan waktu penyelesaian sebuah proyek. Berdasarkan latar belakang tersebut, penelitian ini ditujukan untuk menganalisis nilai produktivitas pada salah satu komponen non-struktural bangunan gedung. Secara spesifik, kajian dilakukan pada komponen penutup atap. KAJIAN PUSTAKA Konstruksi Atap Bangunan gedung adalah wujud fisik hasil pekerjaan konstruksi yang menyatu dengan tempat dan kedudukannya, sebagian atau seluruhnya berada di atas dan/atau di dalam tanah dan/atau air, yang berfungsi sebagai tempat manusia melakukan kegiatan, baik untuk hunian atau tempat tinggal, kegiatan keagamaan, kegiatan usaha, kegiatan sosial, budaya, maupun kegiatan khusus (Anonim, 2007). Konstruksi bangunan gedung terdiri dari sejumlah komponen yang secara umum dapat dikelompokkan dalam komponen struktural dan komponen non-struktural. Konstruksi atap merupakan salah satu komponen pembentuk sebuah bangunan gedung. Secara umum atap berfungsi sebagai penutup seluruh ruangan yang ada dibawahnya terhadap pengaruh panas, hujan, debu, kotoran, angin, dan sebagainya. Pemilihan bentuk dan jenis atap harus disesuaikan dengan bentuk bangunan dibawahnya, iklim setempat, biaya, serta bahan bangunan yang tersedia di daerah tersebut (Kusjuliadi, 2007). Pada dasarnya, ada dua komponen utama sebagai penyusun atap, yaitu struktur atap dan penutup atap. Struktur atap merupakan susunan rangka batang yang berfungsi sebagai pendukung atau penahan beban penutup atap. Struktur atap meliputi kuda-kuda atap dan rangka atap. Ada banyak bahan yang dapat digunakan sebagai penutup atap,diantaranya meliputi atap genteng, asbes, sirap, polikarbonat, seng, alumunium dan lainlain (Kusjuliadi, 2007). Dari segi bentuk, atap yang lazim digunakan adalah atap datar, atap sandar, atap pelana, 134

4 atap perisai, atap tenda, atap joglo, atap setengah bola, atap silang, dan atap gabungan (Supribadi, 1993). Produktivitas Produktivitas dapat diartikan sebagai perbandingan antara output (hasil produksi) terhadap input (komponen produksi : tenaga kerja, bahan, peralatan, dan waktu). Jadi dalam analisis produktivitas dapat dinyatakan sebagai rasio antara output terhadap input dan waktu (jam atau hari). Bila input dan waktu kecil maka output semakin besar sehingga produktivitas semakin tinggi (Anonim, 2013). Produktivitas dapat dihitung dengan menggunakan persamaan (Soedrajat, 1984) :...(1) Dimana : P = produktivitas (m 2 /hari); V = volume pekerjaan per satuan waktu (m 2 ); n = jumlah tenaga kerja (orang); dan T = waktu kerja efektif (hari). METODE PENELITIAN Objek Penelitian Penelitian ini dilakukan secara khusus pada komponen peutup atap. Penelitian mengambil lokasi pada proyek Pembangunan Gedung Pendidikan dan Ruang Kuliah Fakultas Teknik Universitas Syiah Kuala, Darussalam - Banda Aceh. Bahan penutup atap yang digunakan adalah jenis atap zincalume dengan total volume yang direncanakan seluas 1.513,5 m 2. Lingkup observasi difokuskan pada lima segmen pekerjaan atap yang terdapat pada bangunan gedung yang ditinjau. Pengumpulan Data Penelitian ini menggunakan dua jenis data yaitu data primer dan data sekunder. Data primer didapatkan melalui hasil observasi langsung di lapangan. Pencatatan dan pengukuran yang dilakukan terdiri dari pengukuran volume pekerjaan, pencatatan jumlah tenaga kerja, dan pengukuran waktu kerja efektif penyelesaian pekerjaan pada setiap segmen pekerjaan pemasangan penutup atap. Data sekunder diperoleh dari dokumentasi proyek,berupa informasi seperti gambar rencana atap, daftar pekerjaan dan volume, dan Rencana Kerja dan Syarat-syarat (RKS). Pengolahan Data dan Analisis Data yang telah terkumpul diolah untuk mendapatkan nilai produktivitas. Pengolahan data diawali dengan membuat pengelompokan data sesuai dengan segmen atap. Data volume, jumlah tenaga kerja, dan waktu efektif menjadi masukan untuk mendapatkan nilai produktivitas. Proses analisis dilakukan dengan menggunakan persamaan 1. Nilai produktivitas secara keseluruhan akan ditentukan berdasarkan nilai rerata yang diperoleh dari 5 segmen tinjauan. HASIL DAN DISKUSI 135

5 Hasil Observasi Lapangan Pelaksanaan pekerjaan pemasangan penutup atap dilakukan pada 5 segmen atap bangunan. Pekerjaan yang dilakukan pada komponen penutup atap tersebut terdiri dari 2 jenis pekerjaan yaitu pemasangan atap dan pemasangan rabung atap. Material atap yang digunakan adalah zincalume dengan dimensi lebar 0,85 m dengan tiga variasi panjang yaitu 4,4 m, 2,4 m, dan 1,1 m. Untuk rabung, material yang digunakan berjenis sama seperti material atap dengan dimensi lebar 0,4 m dan panjang 2,4 m. Gambar rencana pemasangan dan dimensi material dapat dilihat pada Gambar 1. Proses pelaksanaan pemasangan penutup atap dapat dilihat pada Gambar 2. Gambar 1: Rencana Atap dan Dimensi Material a) Peletakan material pada rangka b) Penyetelan posisi peletakan atap 136

6 c) Pemasangan sekrup d) Pemasangan rabung atap Gambar 2. Proses Pemasangan Atap dan Rabung Produktivitas Pekerjaan Nilai produktivitas ditentukan oleh besaran volume pekerjaan, jumlah tenaga kerja, dan waktu efektif pekerjaan. Dari hasil observasi lapangan, informasi mengenai besaran volume, jumlah tenaga kerja, dan waktu efektif pekerjaan ditunjukkan dalam Tabel 1dan Tabel 2. Analisis produktivitas kerja pemasangan penutup atap diawali dengan menghitung volume pekerjaan yang telah dibahas sebelumnya. Kemudian dibandingkan dengan waktu kerja dan waktu efektif dalam menyelesaikan pekerjaan pada setiap segmen pemasangan penutup atap. Hasil dari produktivitas pada tiap segmen pekerjaan pemasangan penutup atap dapat dilihat pada Tabel 3. Tabel 1 Volume, Jumlah Tenaga Kerja, dan Waktu Efektif Pekerjaan Penutup Atap No Segmen Atap Volume Tenaga Kerja Waktu efektif (m 2 ) (orang) (menit) (jam) 1 Segmen A 258, ,45 3,208 2 Segmen B 227, ,93 3,099 3 Segmen C 329, ,41 4,424 4 Segmen D 244, ,41 3,007 5 Segmen E 187, ,17 1,553 Tabel 2 Volume, Jumlah Tenaga Kerja, dan Waktu Efektif Pekerjaan Rabung Atap No Segmen Atap Volume Tenaga Kerja Waktu efektif (m 2 ) (orang) (menit) (jam) 1 Segmen A 11, ,82 0,230 2 Segmen B 10, ,38 0,190 3 Segmen C 14, ,51 0,275 4 Segmen D 10, ,38 0,190 5 Segmen E 6,80 2 7,83 0,

7 Tabel 3 Nilai Produktivitas Pekerjaan Penutup Atap No Uraian Pekerjaan Penutup Atap (m 2 /jam) Penutup Atap (m 2 /hari) Produktivitas Rabung (m/jam) Rabung (m/hari) 1 Segmen A 20, ,157 12,764 89,349 2 Segmen B 18, ,216 13,603 95,220 3 Segmen C 18, ,205 13,592 95,142 4 Segmen D 20, ,243 13,708 95,958 5 Segmen E 30, ,744 13,027 91,188 Rerata 21,50 150,51 13,339 93,371 Hasil analisis menunjukkan bahwa nilai produktivitas untuk pekerjaan penutup atap diperoleh rata-rata sebesar 21,50 m2/jam atau 150,51 m2/hari. Produktivitas terbesar terlihat pada Segmen E dan yang terkecil pada Segmen B. Nilai produktivitas pekerjaan pemasangan rabung atap diperoleh sebesar 13,339 m/jam atau 93,371 m/hari. Produktivitas terbesar terlihat pada Segmen D dan yang terkecil pada Segmen A. Pada pelaksanaan pekerjaan penutup atap dan rabung, jumlah tenaga kerja yang digunakan sama pada seluruh segmen, sehingga nilai produktivitas cenderung ditentukan oleh besaran rasio antara volume pekerjaan dan waktu efektif pelaksanaan. Dengan demikian, bila jumlah volume pekerjaan dapat diselesaikan dalam waktu yang lebih singkat maka nilai produktivitas akan meningkat. KESIMPULAN Dari hasil analisis yang telah dilakukan, penelitian ini menyimpulkan beberapa hal berikut : 1. Untuk pekerjaan penutup atap, nilai produktivitas rata-rata yang diperoleh sebesar 21,50 m 2 /jam atau 150,51 m 2 /hari. 2. Untuk pekerjaan pemasangan rabung atap, nilai produktivitas rata-rata yang diperoleh sebesar 13,339 m/jam atau 93,371 m/hari. 3. Nilai produktivitas cenderung ditentukan oleh besaran rasio antara volume pekerjaan dan waktu efektif pelaksanaan. Hal ini disebabkan oleh penggunaan jumlah tenaga kerja yang sama pada setiap segmen tinjauan. Dengan demikian, bila jumlah volume pekerjaan dapat diselesaikan dalam waktu yang lebih singkat maka nilai produktivitas akan meningkat. DAFTAR PUSTAKA Anonim, Peraturan Menteri Pekerjaan Umum Nomor : No. 45/PRT/M/2007 Tentang Pedoman Teknis Pembangunan Bangunan Gedung Negara. Anonim, Peraturan Menteri Pekerjaan Umum Nomor : No. 11/PRT/M/2013 Tentang Pedoman Analisis Harga Satuan Pekerjaan Bidang Pekerjaan Umum. Kusjuliadi, D., Ragam Bentuk dan Perawatan Atap. Jakarta: Penebar Swadaya. Soedrajat, S., Analisa Anggaran Pelaksanaan. Bandung: Nova. 138

Jl. Perpustakaan, Kampus USU Medan INDONESIA

Jl. Perpustakaan, Kampus USU Medan INDONESIA Perbandingan Biaya dan Produktivitas Pekerja Antara Shift Pagi dan Shift Malam Pada Proyek Pembangunan Gedung The Manhattan Medan Michael Tanaka 1 dan indra jaya pandia 2 1 Departemen Teknik Sipil, Universitas

Lebih terperinci

TIME-COST TRADE-OFF MODEL FOR TIE BEAM ACTIVITY

TIME-COST TRADE-OFF MODEL FOR TIE BEAM ACTIVITY p-issn 2088-9321 e-issn 2502-5295 Volume 7, Nomor 1, Mei 2018 TIME-COST TRADE-OFF MODEL FOR TIE BEAM ACTIVITY Fachrurrazi 1, Mahmuddin 1, Cut Yuniati Anas 1 1) Jurusan Teknik Sipil, Fakultas Teknik, Jl.

Lebih terperinci

PRODUKTIVITAS TENAGA KERJA DENGAN METODE WORK SAMPLING PROYEK PERUMAHAN DI KOTA PEKANBARU

PRODUKTIVITAS TENAGA KERJA DENGAN METODE WORK SAMPLING PROYEK PERUMAHAN DI KOTA PEKANBARU PRODUKTIVITAS TENAGA KERJA DENGAN METODE WORK SAMPLING PROYEK PERUMAHAN DI KOTA PEKANBARU Gusneli Yanti Program Studi Teknik Sipil Universitas Lancang Kuning Jalan Yos Sudarso Km. 8 Rumbai Pekanbaru E-mail

Lebih terperinci

Diajukan oleh : Rusdiansyah

Diajukan oleh : Rusdiansyah PERHITUNGAN KEBUTUHAN PENAMPANG DRAINASE JALAN SIMPANG TIGA TANJUNG DURUN TEPIAN TEBOR KEC. KOTA BANGUN KABUPATEN KUTAI KARTANEGARA Naskah Publikasi Untuk memenuhi sebagai persyaratan memperoleh gelar

Lebih terperinci

ANALISIS PRODUKTIVITAS PEKERJAAN PEMASANGAN RANGKA ATAP BAJA RINGAN

ANALISIS PRODUKTIVITAS PEKERJAAN PEMASANGAN RANGKA ATAP BAJA RINGAN SKRIPSI ANALISIS PRODUKTIVITAS PEKERJAAN PEMASANGAN RANGKA ATAP BAJA RINGAN ANTONIUS TRIANTO NPM : 2013410077 PEMBIMBING : Yohanes Lim Dwi Adianto, Ir., M.T. KO-PEMBIMBING : Adrian Firdaus, S.T., M.Sc.

Lebih terperinci

OPTIMALISASI BIAYA DAN WAKTU PADA PELAKSANAAN PEKERJAAN PASANGAN DINDING BATA MERAH DENGAN METODE TIME STUDY

OPTIMALISASI BIAYA DAN WAKTU PADA PELAKSANAAN PEKERJAAN PASANGAN DINDING BATA MERAH DENGAN METODE TIME STUDY OPTIMALISASI BIAYA DAN WAKTU PADA PELAKSANAAN PEKERJAAN PASANGAN DINDING BATA MERAH DENGAN METODE TIME STUDY (Cost And Time Optimization In Red Brick Instalation Using Time Study Method) Andi Pramudiyanto

Lebih terperinci

PRIYANTO D

PRIYANTO D EVALUASI BIAYA PEKERJAAN PROYEK PEMBANGUNAN GEDUNG KULIAH 5 LANTAI DENGAN SISTEM DAKTAIL PENUH DI WILAYAH GEMPA 3 Disusun sebagai salah satu syarat menyelesaikan Program Studi Strata I pada Jurusan Teknik

Lebih terperinci

PERBANDINGAN PERHITUNGAN RENCANA ANGGARAN BIAYA LANJUTAN PEMBANGUNAN GEDUNG KULIAH FAKULTAS EKONOMI UNIVERSITAS SUMATERA UTARA

PERBANDINGAN PERHITUNGAN RENCANA ANGGARAN BIAYA LANJUTAN PEMBANGUNAN GEDUNG KULIAH FAKULTAS EKONOMI UNIVERSITAS SUMATERA UTARA PERBANDINGAN PERHITUNGAN RENCANA ANGGARAN BIAYA LANJUTAN PEMBANGUNAN GEDUNG KULIAH FAKULTAS EKONOMI UNIVERSITAS SUMATERA UTARA LAPORAN Ditulis untuk Menyelesaikan Matakuliah Tugas Akhir Semester VI Pendidikan

Lebih terperinci

PERBANDINGAN PRODUKTIVITAS EXCAVATOR PADA PEKERJAAN PASANG/SUSUN BATU GUNUNG UKURAN KG DAN KG

PERBANDINGAN PRODUKTIVITAS EXCAVATOR PADA PEKERJAAN PASANG/SUSUN BATU GUNUNG UKURAN KG DAN KG ISSN 2088-9321 pp. 91-100 PERBANDINGAN PRODUKTIVITAS EXCAVATOR PADA PEKERJAAN PASANG/SUSUN BATU GUNUNG UKURAN 5-250 KG DAN 1000-1500 KG Mahmuddin 1 dan Nurisra 2 1,2) Jurusan Teknik Sipil, Fakultas Teknik

Lebih terperinci

PRODUKTIVITAS PADA PROYEK KONSTRUKSI

PRODUKTIVITAS PADA PROYEK KONSTRUKSI PRODUKTIVITAS PADA PROYEK KONSTRUKSI Oleh Taufik Dwi Laksono Abstract Lact in the Indonesia eployment awareness concerning the importance of productivity, is one of the causal factors of the job lack produced,

Lebih terperinci

SIMULASI ARUS KAS PADA PROYEK PEMBANGUNAN GEDUNG SEKOLAH SMP DAN SMA STRADA KRANJI

SIMULASI ARUS KAS PADA PROYEK PEMBANGUNAN GEDUNG SEKOLAH SMP DAN SMA STRADA KRANJI SKRIPSI SIMULASI ARUS KAS PADA PROYEK PEMBANGUNAN GEDUNG SEKOLAH SMP DAN SMA STRADA KRANJI FRANSISKUS XAVERIUS RONALDO NPM : 2014410083 PEMBIMBING: Ir. Theresita Herni S., M.T. UNIVERSITAS KATOLIK PARAHYANGAN

Lebih terperinci

TKS 4406 Material Technology I

TKS 4406 Material Technology I TKS 4406 Material Technology I Dr.Eng. Achfas Zacoeb, ST., MT. Department of Civil Engineering Faculty of Engineering University of Brawijaya UMUM Atap adalah bagian bangunan yang mempunyai fungsi ganda

Lebih terperinci

DiajukanKepadaUniversitas Islam Indonesia YogyakartaUntukMemenuhi PersyaratanMemperolehDerajatSarjana Strata SatuTeknikSipil

DiajukanKepadaUniversitas Islam Indonesia YogyakartaUntukMemenuhi PersyaratanMemperolehDerajatSarjana Strata SatuTeknikSipil TUGAS AKHIR ANALISIS PRODUKTIVITAS TENAGA KERJA PADA PEKERJAAN PENGECATAN DENGAN METODE MPDM (Studi Kasus: Perumahan Residence Palagan 2 Hyarta, Yogyakarta) DiajukanKepadaUniversitas Islam Indonesia YogyakartaUntukMemenuhi

Lebih terperinci

KONSTRUKSI RANGKA ATAP

KONSTRUKSI RANGKA ATAP KONSTRUKSI RANGKA ATAP 2. URAIAN MATERI ATAP Atap merupakan bagian dari bangunan gedung ( rumah ) yang letaknya berada dibagian paling atas, sehingga untuk perencanaannya atap ini haruslah diperhitungkan

Lebih terperinci

FAKTOR-FAKTOR PERTIMBANGAN PENERAPAN TEKNOLOGI PRECAST TERHADAP KINERJA PELAKSANAAN PROYEK KONSTRUKSI GEDUNG DI KOTA BANDA ACEH

FAKTOR-FAKTOR PERTIMBANGAN PENERAPAN TEKNOLOGI PRECAST TERHADAP KINERJA PELAKSANAAN PROYEK KONSTRUKSI GEDUNG DI KOTA BANDA ACEH ISSN 2088-9321 ISSN e-2502-5295 FAKTOR-FAKTOR PERTIMBANGAN PENERAPAN TEKNOLOGI PRECAST TERHADAP KINERJA PELAKSANAAN PROYEK KONSTRUKSI GEDUNG DI KOTA BANDA ACEH pp. 857-868 Rusli Z 1, Mochammad Afifuddin

Lebih terperinci

JURUSAN SIPIL F AKUL T AS TEKNIK UNIVERSITAS HASANUDDIN 2016

JURUSAN SIPIL F AKUL T AS TEKNIK UNIVERSITAS HASANUDDIN 2016 TUGAS AKHIR ANALISA PERBANDINGAN WAKTU PELAKSANAAN METODE KONSTRUKSI BOTTOM-UP DENGAN TOP DOWN (Study Kasus Proyek Hotel Howard Johnson) : DISUSUN OLEH: MEGATRI SERANG 011110 288 JURUSAN SIPIL F AKUL T

Lebih terperinci

3. Bagian-Bagian Atap Bagian-bagian atap terdiri atas; kuda-kuda, ikatan angin, jurai, gording, sagrod, bubungan, usuk, reng, penutup atap, dan

3. Bagian-Bagian Atap Bagian-bagian atap terdiri atas; kuda-kuda, ikatan angin, jurai, gording, sagrod, bubungan, usuk, reng, penutup atap, dan 3. Bagian-Bagian Atap Bagian-bagian atap terdiri atas; kuda-kuda, ikatan angin, jurai, gording, sagrod, bubungan, usuk, reng, penutup atap, dan talang. a. Gording Gording membagi bentangan atap dalam jarak-jarak

Lebih terperinci

INFO TEKNIK Volume 5 No. 1, Juli 2004 (1-6) Kinerja Tukang dan Laden Pada Proyek Pembangunan Gedung

INFO TEKNIK Volume 5 No. 1, Juli 2004 (1-6) Kinerja Tukang dan Laden Pada Proyek Pembangunan Gedung INFO TEKNIK Volume 5 No. 1, Juli 2004 (1-6) Kinerja Tukang dan Laden Pada Proyek Pembangunan Gedung Dewi Fameilia 1, Rini Ratnayanti 1, Bernardinus Herbudiman 1 Abstrak On the same quality standard, performance

Lebih terperinci

STUDI OPTIMASI WAKTU DAN BIAYA DENGAN METODE TIME COST TRADE OFF PADA PROYEK PEMBANGUNAN GEDUNG TIPE B SMPN BARU SIWALANKERTO

STUDI OPTIMASI WAKTU DAN BIAYA DENGAN METODE TIME COST TRADE OFF PADA PROYEK PEMBANGUNAN GEDUNG TIPE B SMPN BARU SIWALANKERTO STUDI OPTIMASI WAKTU DAN BIAYA DENGAN METODE TIME COST TRADE OFF PADA PROYEK PEMBANGUNAN GEDUNG TIPE B SMPN BARU SIWALANKERTO Moch. Chusairi Program Studi S1 Teknik Sipil, Fakultas Teknik, Universitas

Lebih terperinci

TESIS PENGARUH KARAKTERISTIK TUKANG BATU LOKAL TERHADAP PRODUKTIVITAS

TESIS PENGARUH KARAKTERISTIK TUKANG BATU LOKAL TERHADAP PRODUKTIVITAS TESIS PENGARUH KARAKTERISTIK TUKANG BATU LOKAL TERHADAP PRODUKTIVITAS Oleh : JOAO MIRELES MARIANO NPM. : 14 51 02283/PS/MTS PROGRAM STUDI MAGISTER TEKNIK SIPIL PROGRAM PASCASARJANA UNIVERSITAS ATMA JAYA

Lebih terperinci

PENGARUH QUALITY MANAGEMENT TERHADAP DAYA SAING KONTRAKTOR PADA PROYEK KONSTRUKSI GEDUNG DI KOTA BANDA ACEH

PENGARUH QUALITY MANAGEMENT TERHADAP DAYA SAING KONTRAKTOR PADA PROYEK KONSTRUKSI GEDUNG DI KOTA BANDA ACEH ISSN 2088-9321 ISSN e-2502-5295 pp. 67-76 PENGARUH QUALITY MANAGEMENT TERHADAP DAYA SAING KONTRAKTOR PADA PROYEK KONSTRUKSI GEDUNG DI KOTA BANDA ACEH Nya Munanta 1, Muttaqin Hasan 2, Hafnidar A. Rani 3

Lebih terperinci

Jurnal Teknik Sipil ISSN

Jurnal Teknik Sipil ISSN ISSN 2088-9321 ISSN e-2502-5295 pp. 543-552 TINJAUAN KONDISI PERKERASAN JALAN DENGAN KOMBINASI NILAI INTERNATIONAL ROUGHNESS INDEX (IRI) DAN SURFACE DISTRESS INDEX (SDI) PADA JALAN TAKENGON BLANGKEJEREN

Lebih terperinci

APLIKASI METHOD PRODUCTIVITY DELAY MODELPADA ANALISA PENGARUH WASTEPEKERJA TERHADAP INDEKS KOEFISIEN PRODUKTIVITAS

APLIKASI METHOD PRODUCTIVITY DELAY MODELPADA ANALISA PENGARUH WASTEPEKERJA TERHADAP INDEKS KOEFISIEN PRODUKTIVITAS JURNAL KARYA JURNAL TEKNIK KARYA SIPIL, TEKNIK Volume SIPIL, 6, Nomor Volume 2, Tahun 6, Nomor 2017, 2, Halaman Tahun 2017 31-39 Online di: http://ejournal-s1.undip.ac.id/index.php/jkts APLIKASI METHOD

Lebih terperinci

PRODUKTIVITAS PEKERJAAN PASANGAN BATU BATA PADA DINDING RUMAH TINGGAL. Oleh : Iwan Rustendi

PRODUKTIVITAS PEKERJAAN PASANGAN BATU BATA PADA DINDING RUMAH TINGGAL. Oleh : Iwan Rustendi PRODUKTIVITAS PEKERJAAN PASANGAN BATU BATA PADA DINDING RUMAH TINGGAL Oleh : Iwan Rustendi Abstraksi Penentuan besarnya nilai produktivitas merupakan langkah awal yang harus dilakukan untuk mengetahui

Lebih terperinci

ESTIMASI ANGGARAN BIAYA STRUKTUR PROYEK PEMBANGUNAN HOTEL QUAD MAKASSAR MENGGUNAKAN METODE SNI

ESTIMASI ANGGARAN BIAYA STRUKTUR PROYEK PEMBANGUNAN HOTEL QUAD MAKASSAR MENGGUNAKAN METODE SNI ESTIMASI ANGGARAN BIAYA STRUKTUR PROYEK PEMBANGUNAN HOTEL QUAD MAKASSAR MENGGUNAKAN METODE SNI Kurnia Fatonah 1), Dwi Novi Wulansari 2) 1. Mahasiswa Program Studi Teknik Sipil, Fakultas Teknik Universitas

Lebih terperinci

IDENTIFIKASI INDIKATOR PENERAPAN GREEN CONSTRUCTION PADA PROYEK KONSTRUKSI GEDUNG DI KOTA BANDA ACEH

IDENTIFIKASI INDIKATOR PENERAPAN GREEN CONSTRUCTION PADA PROYEK KONSTRUKSI GEDUNG DI KOTA BANDA ACEH ISSN 2302-0253 7 Pages pp. 101-107 IDENTIFIKASI INDIKATOR PENERAPAN GREEN CONSTRUCTION PADA PROYEK KONSTRUKSI GEDUNG DI KOTA BANDA ACEH Muhammad Furqan 1, T. Budi Aulia 2, Hafnidar A. Rani 3 1) Magister

Lebih terperinci

RASIO KEBUTUHAN TULANGAN PONDASI BETON BERTULANG PADA KONSTRUKSI GEDUNG DI PROVINSI ACEH

RASIO KEBUTUHAN TULANGAN PONDASI BETON BERTULANG PADA KONSTRUKSI GEDUNG DI PROVINSI ACEH Konferensi Nasional Teknik Sipil 11 Universitas Tarumanagara, 26-27 Oktober 2017 RASIO KEBUTUHAN TULANGAN PONDASI BETON BERTULANG PADA KONSTRUKSI GEDUNG DI PROVINSI ACEH Nurul Malahayati 1, Saiful Husin

Lebih terperinci

ANALISIS PRODUKTIVITAS TENAGA KERJA PADA PEMBANGUNAN 1 UNIT RUMAH TYPE 45 (STUDI KASUS : PROYEK PERUMAHAN CEMPAKA MAS DALUNG)

ANALISIS PRODUKTIVITAS TENAGA KERJA PADA PEMBANGUNAN 1 UNIT RUMAH TYPE 45 (STUDI KASUS : PROYEK PERUMAHAN CEMPAKA MAS DALUNG) Jurnal Ilmiah Elektronik Infrastruktur Teknik Sipil ANALISIS PRODUKTIVITAS TENAGA KERJA PADA PEMBANGUNAN 1 UNIT RUMAH TYPE 45 (STUDI KASUS : PROYEK PERUMAHAN CEMPAKA MAS DALUNG) I Gede Putu Aryk Ardianta

Lebih terperinci

PERBANDINGAN HARGA DAN KEKUATAN STRUKTUR ANTARA RANGKA ATAP KAYU DENGAN RANGKA ATAP BAJA RINGAN PADA BERBAGAI JENIS PENUTUP ATAP

PERBANDINGAN HARGA DAN KEKUATAN STRUKTUR ANTARA RANGKA ATAP KAYU DENGAN RANGKA ATAP BAJA RINGAN PADA BERBAGAI JENIS PENUTUP ATAP TUGAS AKHIR PERBANDINGAN HARGA DAN KEKUATAN STRUKTUR ANTARA RANGKA ATAP KAYU DENGAN RANGKA ATAP BAJA RINGAN PADA BERBAGAI JENIS PENUTUP ATAP (Study Kasus Pada Proyek PT. PRIMA ANDALAN GROUP) Diajukan Kepada

Lebih terperinci

Jl. Ir. Sutami 36A, Surakarta 57126; Telp

Jl. Ir. Sutami 36A, Surakarta 57126; Telp OPTIMASI BIAYA DAN WAKTU DENGAN METODE TIME COST TRADE OFF (TCTO) (Studi Kasus Proyek Bangunan Rawat Inap Kelas III dan Parkir RSUD Dr. Moewardi Surakarta) Abstract Ricky Arvianto 1), Fajar Sri Handayani

Lebih terperinci

ANALISIS RISIKO PENAWARAN UNDERESTIMATE COST TERHADAP KUALITAS PROYEK KONSTRUKSI JALAN DI PROVINSI ACEH

ANALISIS RISIKO PENAWARAN UNDERESTIMATE COST TERHADAP KUALITAS PROYEK KONSTRUKSI JALAN DI PROVINSI ACEH ISSN 2088-9321 ISSN e-2502-5295 pp. 511-520 ANALISIS RISIKO PENAWARAN UNDERESTIMATE COST TERHADAP KUALITAS PROYEK KONSTRUKSI JALAN DI PROVINSI ACEH Hamdani 1, M. Isya 2, Hafnidar A. Rani 3 1) Mahasiswa

Lebih terperinci

PENDAHULUAN Latar Belakang

PENDAHULUAN Latar Belakang PENDAHULUAN Latar Belakang Gempa yang melanda daerah Sumatera Barat khususnya Kota Padang pada tanggal 30 September 2009, mengakibatkan banyaknya kantor pemerintahan dan rumah masyarakat (non-engineered

Lebih terperinci

BAB I PENDAHULUAN. Pengujian kualitas genteng pres. (produk kabupaten Kebumen dan produk kabupaten Sukoharjo) UNIVERSITAS SEBELAS MARET.

BAB I PENDAHULUAN. Pengujian kualitas genteng pres. (produk kabupaten Kebumen dan produk kabupaten Sukoharjo) UNIVERSITAS SEBELAS MARET. Pengujian kualitas genteng pres (produk kabupaten Kebumen dan produk kabupaten Sukoharjo) UNIVERSITAS SEBELAS MARET Oleh : Ari Tri Hatmanto NIM : K 1502010 BAB I PENDAHULUAN A. Latar Belakang Masalah Perkembangan

Lebih terperinci

ABSTRACT. Keywords : joint costing, product cost per unit, joint cost allocation method. viii. Universitas Kristen Maranatha

ABSTRACT. Keywords : joint costing, product cost per unit, joint cost allocation method. viii. Universitas Kristen Maranatha ABSTRACT In manufacturing companies, information on production cost and product cost per unit is very important in decision making by management. To be able to produce information about the company's production

Lebih terperinci

BAB I PENDAHULUAN. 1.1 Latar Belakang

BAB I PENDAHULUAN. 1.1 Latar Belakang BAB I PENDAHULUAN 1.1 Latar Belakang Pada pekerjaan konstruksi, atap merupakan salah satu elemen penting pada bangunan gedung dan perumahan. Sebab atap pada bangunan berfungsi sebagi penutup seluruh atau

Lebih terperinci

ANALISIS PRODUKTIVITAS TUKANG KERAMIK

ANALISIS PRODUKTIVITAS TUKANG KERAMIK ANALISIS PRODUKTIVITAS TUKANG KERAMIK Zainuri; Gusneli Yanti; Shanti Wahyuni Megasari Jurusan Teknik Sipil Fakultas Teknik Univeritas Lancang Kuning Jalan Yos Sudarso Km. 8 Rumbai Pekanbaru Email : zainuri20@yahoo.co.id

Lebih terperinci

BAB I PENDAHULUAN. Semakin pesatnya perkembangan bahan material untuk. pembangunan konstruksi banyak melahirkan produk-produk baru.

BAB I PENDAHULUAN. Semakin pesatnya perkembangan bahan material untuk. pembangunan konstruksi banyak melahirkan produk-produk baru. BAB I PENDAHULUAN 1.1 Latar belakang masalah Semakin pesatnya perkembangan bahan material untuk pembangunan konstruksi banyak melahirkan produk-produk baru. Bahanbahan material tersebut dipercaya memiliki

Lebih terperinci

PERBANDINGAN RENCANA ANGGARAN BIAYA KONSTRUKSI BAJA KONVENSIONAL DAN KAYU SEBAGAI KONSTRUKSI RANGKA ATAP BANGUNAN

PERBANDINGAN RENCANA ANGGARAN BIAYA KONSTRUKSI BAJA KONVENSIONAL DAN KAYU SEBAGAI KONSTRUKSI RANGKA ATAP BANGUNAN PERBANDINGAN RENCANA ANGGARAN BIAYA KONSTRUKSI BAJA KONVENSIONAL DAN KAYU SEBAGAI KONSTRUKSI RANGKA ATAP BANGUNAN Rifano Putra, Mafriyal Muluk, Hendra Alexander Jurusan Teknik Sipil Politeknik Negeri Padang

Lebih terperinci

PEMODELAN DESAIN PARAMETER UNTUK ESTIMASI BIAYA PEMBANGUNAN RUMAH

PEMODELAN DESAIN PARAMETER UNTUK ESTIMASI BIAYA PEMBANGUNAN RUMAH TESIS PEMODELAN DESAIN PARAMETER UNTUK ESTIMASI BIAYA PEMBANGUNAN RUMAH NIKOLAUS PANDIN NIM : 145 102 159 PROGRAM STUDI MAGISTER TEKNIK SIPIL PROGRAM PASCASARJANA UNIVERSITAS ATMA JAYA YOGYAKARTA 2015

Lebih terperinci

PENELITIAN AWAL PENENTUAN WAKTU PENYELESAIAN PROYEK DENGAN METODE PERT (PROJECT EVALUATION AND REVIEW TECHNIQUE)

PENELITIAN AWAL PENENTUAN WAKTU PENYELESAIAN PROYEK DENGAN METODE PERT (PROJECT EVALUATION AND REVIEW TECHNIQUE) PENELITIAN AWAL PENENTUAN WAKTU PENYELESAIAN PROYEK DENGAN METODE PERT (Sentosa Limanto, et. al.) PENELITIAN AWAL PENENTUAN WAKTU PENYELESAIAN PROYEK DENGAN METODE PERT (PROJECT EVALUATION AND REVIEW TECHNIQUE)

Lebih terperinci

STUDI FAKTOR-FAKTOR PENYEBAB KETERLAMBATAN PADA PROYEK FINE YARN III BUILDING, TANGERANG ABSTRAK

STUDI FAKTOR-FAKTOR PENYEBAB KETERLAMBATAN PADA PROYEK FINE YARN III BUILDING, TANGERANG ABSTRAK STUDI FAKTOR-FAKTOR PENYEBAB KETERLAMBATAN PADA PROYEK FINE YARN III BUILDING, TANGERANG Aryasta Dariskan NRP : 1021022 Pembimbing : Deni Setiawan, S.T., M.T. ABSTRAK Pelaksanaan proyek konstruksi memiliki

Lebih terperinci

STUDI MENGENAI MODEL ESTIMASI DURASI KONSTRUKSI BANGUNAN GEDUNG

STUDI MENGENAI MODEL ESTIMASI DURASI KONSTRUKSI BANGUNAN GEDUNG Konferensi Nasional Teknik Sipil I (KoNTekS I) Universitas Atma Jaya Yogyakarta Yogyakarta, 11 12 Mei 2007 STUDI MENGENAI MODEL ESTIMASI DURASI KONSTRUKSI BANGUNAN GEDUNG Peter F. Kaming 1, F.. Junaedi

Lebih terperinci

KAJIAN FAKTOR JENIS, PENYEBAB DAN WAKTU TERJADINYA KECELAKAAN KERJA PADA PROYEK KONSTRUKSI DI KOTA BANDA ACEH

KAJIAN FAKTOR JENIS, PENYEBAB DAN WAKTU TERJADINYA KECELAKAAN KERJA PADA PROYEK KONSTRUKSI DI KOTA BANDA ACEH KAJIAN FAKTOR JENIS, PENYEBAB DAN WAKTU TERJADINYA KECELAKAAN KERJA PADA PROYEK KONSTRUKSI DI KOTA BANDA ACEH Buraida Staf Pengajar Jurusan Teknik Sipil Fakultas Teknik Sipil Universitas Syiah Kuala Jln.

Lebih terperinci

ANALISIS PRODUKTIVITAS JUMLAH TENAGA KERJA PADA PEKERJAAN PASANGAN BATA DENGAN METODE WORK STUDY

ANALISIS PRODUKTIVITAS JUMLAH TENAGA KERJA PADA PEKERJAAN PASANGAN BATA DENGAN METODE WORK STUDY ANALISIS PRODUKTIVITAS JUMLAH TENAGA KERJA PADA PEKERJAAN PASANGAN BATA DENGAN METODE WORK STUDY (Studi Kasus Pembangunan Perumahan Grand Mahakam Kota Samarinda) NASKAH PUBLIKASI TEKNIK SIPIL Ditujukan

Lebih terperinci

BAB III METODOLOGI PENELITIAN

BAB III METODOLOGI PENELITIAN BAB III METODOLOGI PENELITIAN 3.1. UMUM Penelitian ini berupa analisa perbandingan pengecoran menggunakan alat berat concrete pump dan concrete bucket untuk pekerjaan konstruksi pada proyek bangunan. Permodelan

Lebih terperinci

ISU LINGKUNGAN DAN KENDALA YANG DIHADAPI PROYEK KONSTRUKSI DI BANDA ACEH

ISU LINGKUNGAN DAN KENDALA YANG DIHADAPI PROYEK KONSTRUKSI DI BANDA ACEH ISU LINGKUNGAN DAN KENDALA YANG DIHADAPI PROYEK KONSTRUKSI DI BANDA ACEH Cut Mutiawati 1, Cut Zukhrina Oktaviani 2, dan Amanda Setiawan 2 1,2,3 Program Studi Teknik Sipil, Universitas Syiah Kuala, Jl.

Lebih terperinci

Jurnal Sipil Statik Vol.4 No.10 Oktober 2016 ( ) ISSN:

Jurnal Sipil Statik Vol.4 No.10 Oktober 2016 ( ) ISSN: PRODUKTIVITAS TENAGA KERJA PADA PEKERJAAN BETON BERTULANG (STUDI KASUS : PEMBANGUNAN GEDUNG RUANG KANTOR DAN RUANG KELAS YAYASAN EBEN HEAZER JALAN 14 FEBRUARI TELING ATAS, MANADO) Indra Prasetyo Talimbo

Lebih terperinci

ANALISIS PERBANDINGAN KOEFISIEN HARGA SATUAN UPAH PEKERJAAN BERDASARKAN HASIL PENGAMATAN DI LAPANGAN DAN STANDAR NASIONAL INDONESIA (SNI)

ANALISIS PERBANDINGAN KOEFISIEN HARGA SATUAN UPAH PEKERJAAN BERDASARKAN HASIL PENGAMATAN DI LAPANGAN DAN STANDAR NASIONAL INDONESIA (SNI) ANALISIS PERBANDINGAN KOEFISIEN HARGA SATUAN UPAH PEKERJAAN BERDASARKAN HASIL PENGAMATAN DI LAPANGAN DAN STANDAR NASIONAL INDONESIA (SNI) Oleh: Alfian Prasetyo Dosen Pembimbing: 1. Dr.Ir. Koespiadi M.T

Lebih terperinci

SKRIPSI JURUSAN TEKNIK SIPIL FAKULTAS TEKNIK UNIVERSITAS SEBELAS MARET SURAKARTA commit to user

SKRIPSI JURUSAN TEKNIK SIPIL FAKULTAS TEKNIK UNIVERSITAS SEBELAS MARET SURAKARTA commit to user OPTIMASI BIAYA DAN WAKTU DENGAN METODE TIME COST TRADE OFF (TCTO) (STUDI KASUS PROYEK BANGUNAN RAWAT INAP KELAS III DAN PARKIR RSUD. Dr. MOEWARDI SURAKARTA) OPTIMIZATION COSTS AND TIME METHOD OF TIME COST

Lebih terperinci

Analisis Pondasi Konvensional dan Pondasi Elevated Tangki Refrigerated LPG PT Pertamina Tanjung Sekong dari Segi Biaya dan Waktu

Analisis Pondasi Konvensional dan Pondasi Elevated Tangki Refrigerated LPG PT Pertamina Tanjung Sekong dari Segi Biaya dan Waktu D165 Analisis Pondasi Konvensional dan Pondasi Elevated Tangki Refrigerated LPG PT Pertamina Tanjung Sekong dari Segi Biaya dan Waktu Sry Rashida Sofyan dan Cahyono Bintang Nurcahyo Departemen Teknik Sipil,

Lebih terperinci

ANALISA PERBEDAAN HARGA RAB DENGAN RAP UNTUK PEKERJAAN BETON BERTULANG PADA PROYEK ITC POLONIA MEDAN

ANALISA PERBEDAAN HARGA RAB DENGAN RAP UNTUK PEKERJAAN BETON BERTULANG PADA PROYEK ITC POLONIA MEDAN ANALISA PERBEDAAN HARGA RAB DENGAN RAP UNTUK PEKERJAAN BETON BERTULANG PADA PROYEK ITC POLONIA MEDAN LAPORAN Ditulis untuk Menyelesaikan Mata Kuliah Tugas Akhir Semester VI Pendidikan Program Diploma III

Lebih terperinci

Disusun sebagai salah satu syarat memperoleh gelar Sarjana. pada Program Studi Teknik Sipil Fakultas Teknik. Universitas Sebelas Maret Surakarta

Disusun sebagai salah satu syarat memperoleh gelar Sarjana. pada Program Studi Teknik Sipil Fakultas Teknik. Universitas Sebelas Maret Surakarta PENGENDALIAN BIAYA BAHAN DENGAN METODE ANALISA VARIAN PADA PELAKSANAAN PROYEK KONSTRUKSI (Studi Kasus Proyek Rumah Dinas PT. Taspen, Jakarta Pusat) Cost Control Material Analysis Method with Variety Of

Lebih terperinci

TINJAUAN KEKUATAN DAN BIAYA STRUKTUR ATAP BAJA RINGAN DAN BAJA KONVENSIONAL GEDUNG DIKLAT RSUP DR. KARIADI SEMARANG

TINJAUAN KEKUATAN DAN BIAYA STRUKTUR ATAP BAJA RINGAN DAN BAJA KONVENSIONAL GEDUNG DIKLAT RSUP DR. KARIADI SEMARANG TINJAUAN KEKUATAN DAN BIAYA STRUKTUR ATAP BAJA RINGAN DAN BAJA KONVENSIONAL GEDUNG DIKLAT RSUP DR. KARIADI SEMARANG Disusun sebagai salah satu syarat menyelesaikan Program Studi Strata I pada Jurusan Teknik

Lebih terperinci

ANALISIS FAKTOR-FAKTOR YANG DAPAT MENGUBAH METODE PELAKSANAAN KERJA PADA PROYEK-PROYEK KONSTRUKSI DI KOTA MEDAN LAPORAN

ANALISIS FAKTOR-FAKTOR YANG DAPAT MENGUBAH METODE PELAKSANAAN KERJA PADA PROYEK-PROYEK KONSTRUKSI DI KOTA MEDAN LAPORAN ANALISIS FAKTOR-FAKTOR YANG DAPAT MENGUBAH METODE PELAKSANAAN KERJA PADA PROYEK-PROYEK KONSTRUKSI DI KOTA MEDAN LAPORAN Disusun sebagai Satu Syarat untuk Menyelesaikan Matakuliah Tugas Akhir pada Program

Lebih terperinci

ANALISIS FAKTOR-FAKTOR DOMINAN PENYEBAB KETERLAMBATAN PROYEK KONSTRUKSI BANGUNAN APARTEMEN X BANDUNG

ANALISIS FAKTOR-FAKTOR DOMINAN PENYEBAB KETERLAMBATAN PROYEK KONSTRUKSI BANGUNAN APARTEMEN X BANDUNG SKRIPSI ANALISIS FAKTOR-FAKTOR DOMINAN PENYEBAB KETERLAMBATAN PROYEK KONSTRUKSI BANGUNAN APARTEMEN X BANDUNG ARIE RAHAYU P. NPM: 2012410017 PEMBIMBING: Theresita Herni Setiawan, Ir., MT. UNIVERSITAS KATOLIK

Lebih terperinci

ANALISIS PRODUKTIVITAS CONCRETE PUMP PADA PROYEK BANGUNAN TINGGI

ANALISIS PRODUKTIVITAS CONCRETE PUMP PADA PROYEK BANGUNAN TINGGI Konferensi Nasional Teknik Sipil 3 (KoNTekS 3) Jakarta, 6 7 Mei 009 ANALISIS PRODUKTIVITAS CONCRETE PUMP PADA PROYEK BANGUNAN TINGGI Sentosa Limanto Program Studi Teknik Sipil, Universitas Kristen Surabaya,

Lebih terperinci

ANALISIS FAKTOR-FAKTOR PENGHAMBAT YANG BERPENGARUH TERHADAP WAKTU PROYEK IRIGASIDI PROVINSI ACEH

ANALISIS FAKTOR-FAKTOR PENGHAMBAT YANG BERPENGARUH TERHADAP WAKTU PROYEK IRIGASIDI PROVINSI ACEH ISSN 2088-9321 ISSN e-2502-5295 pp. 259-268 ANALISIS FAKTOR-FAKTOR PENGHAMBAT YANG BERPENGARUH TERHADAP WAKTU PROYEK IRIGASIDI PROVINSI ACEH Anita Rauzana 1, Gunawan 2, Masimin 3 1,3) Jurusan Teknik Sipil,

Lebih terperinci

BAB I PENDAHULUAN Latar Belakang

BAB I PENDAHULUAN Latar Belakang BAB I PENDAHULUAN 1.1. Latar Belakang Sejalan dengan pertumbuhan ekonomi,maka tingkat konsumsi masyarakat terhadap sesuatu juga semakin tinggi. Namun permasalahannya adalah masyarakat menginginkan barang

Lebih terperinci

Jurnal Teknik Sipil ISSN Pascasarjana Universitas Syiah Kuala 8 Pages pp

Jurnal Teknik Sipil ISSN Pascasarjana Universitas Syiah Kuala 8 Pages pp ISSN 2302-0253 8 Pages pp. 14-21 PENGARUH KARAKTERISTIK, PERILAKU, MOTIVASI DAN KEPUASAN KERJA TENAGA KERJA KONSTRUKSI TERHADAP PRESTASI KERJA PADA PROYEK KONSTRUKSI GEDUNG DI KOTA BANDA ACEH Buraida 1,

Lebih terperinci

(Studi Kasus Proyek Pembangunan Gedung II Dan Bangunan Penghubung FISIP, Universitas Brawijaya Malang)

(Studi Kasus Proyek Pembangunan Gedung II Dan Bangunan Penghubung FISIP, Universitas Brawijaya Malang) Analisa Perbandingan Metode SNI Dan Software MS. Project Dalam Perhitungan Harga Satuan Pekerjaan Penutup Lantai dan Dinding Serta Pemasangan Paving Block Untuk Konstruksi Bangunan (Studi Kasus Proyek

Lebih terperinci

TUGAS AKHIR. Diajukan guna melengkapi sebagian syarat Dalam mencapai gelar Sarjana Strata Satu (S1)

TUGAS AKHIR. Diajukan guna melengkapi sebagian syarat Dalam mencapai gelar Sarjana Strata Satu (S1) TUGAS AKHIR Analisa Efisiensi Durasi Waktu Proyek Dengan Metode CPM & PERT ( Studi Kasus Proyek Modifikasi Silo Powder Plant di PT.Sayap Mas Utama Jakarta) Diajukan guna melengkapi sebagian syarat Dalam

Lebih terperinci

Dadiyono Amat Pawiro Jurusan Teknik Sipil, Politeknik Negeri Semarang Jl.Prof. Soedarto, SH, Tembalang, Semarang

Dadiyono Amat Pawiro Jurusan Teknik Sipil, Politeknik Negeri Semarang Jl.Prof. Soedarto, SH, Tembalang, Semarang Dadiyono Amat Pawiro, Suharyanto, Pranoto Samto Atmojo Optimasi Biaya dan Waktu dalam Penyusunan Jadwal Pelaksanaan Proyek (Studi Kasus Proyek Pembangunan Gedung Pusat Kegiatan Optimasi Biaya dan Waktu

Lebih terperinci

STUDI PEMELIHARAAN BANGUNAN GEDUNG KAMPUS Studi Kasus: Gedung Graha Widya Maranatha

STUDI PEMELIHARAAN BANGUNAN GEDUNG KAMPUS Studi Kasus: Gedung Graha Widya Maranatha STUDI PEMELIHARAAN BANGUNAN GEDUNG KAMPUS Studi Kasus: Gedung Graha Widya Maranatha Michael Roberto Gunawan NRP: 1221045 Pembimbing: Ir. Maksum Tanubrata, M.T. ABSTRAK Kebutuhan bangunan gedung untuk berbagai

Lebih terperinci

ABSTRAK Universitas Kristen Maranatha

ABSTRAK Universitas Kristen Maranatha ABSTRAK EVALUASI SISTEM KESELAMATAN DAN KESEHATAN KERJA PADA PROYEK RS. LIMIJATI Fadly Utama (0321054), Program Studi Teknik Sipil, Fakultas Teknik Sipil,, 2010. Konstruksi merupakan sektor industri yang

Lebih terperinci

ANALISA SISI POSITIF DAN NEGATIF PEMILIHAN BENTUK ATAP BERPENUTUP GENTENG UNTUK RUMAH TINGGAL. Sudarmadji ABSTRAK

ANALISA SISI POSITIF DAN NEGATIF PEMILIHAN BENTUK ATAP BERPENUTUP GENTENG UNTUK RUMAH TINGGAL. Sudarmadji ABSTRAK ANALISA SISI POSITIF DAN NEGATIF PEMILIHAN BENTUK ATAP BERPENUTUP GENTENG UNTUK RUMAH TINGGAL Sudarmadji Staf Pengajar Jurusan Teknik Sipil Politeknik Negeri Sriwijaya Jln. Srijaya Negara Bukit Besar Palembang,

Lebih terperinci

STUDI PERBANDINGAN PRODUKTIVITAS PEKERJAAN PEMASANGAN PENUTUP LANTAI

STUDI PERBANDINGAN PRODUKTIVITAS PEKERJAAN PEMASANGAN PENUTUP LANTAI SKRIPSI STUDI PERBANDINGAN PRODUKTIVITAS PEKERJAAN PEMASANGAN PENUTUP LANTAI ARNOLDUS JANSSEN NPM : 2013410134 PEMBIMBING: Theresita Herni, Ir., M.T. UNIVERSITAS KATOLIK PARAHYANGAN FAKULTAS TEKNIK PROGRAM

Lebih terperinci

ANALISIS KEBUTUHAN TENAGA KERJA PADA PEMBANGUNAN RUMAH TINGGAL BERDASARKAN KOEFISIEN SNI 2008 DAN HSPK 2012 DENGAN KONDISI REAL DI LAPANGAN

ANALISIS KEBUTUHAN TENAGA KERJA PADA PEMBANGUNAN RUMAH TINGGAL BERDASARKAN KOEFISIEN SNI 2008 DAN HSPK 2012 DENGAN KONDISI REAL DI LAPANGAN ANALISIS KEBUTUHAN TENAGA KERJA PADA PEMBANGUNAN RUMAH TINGGAL BERDASARKAN KOEFISIEN SNI 008 DAN HSPK 0 DENGAN KONDISI REAL DI LAPANGAN ANALYSIS OF LABOR NEEDS IN HOUSE DEVELOPMEN BASED COEFFICIENTS SNI

Lebih terperinci

STUDI KASUS PEKERJAAN PRODUKSI DAN PEMASANGAN DINDING PRECAST PADA PROYEK APARTEMEN

STUDI KASUS PEKERJAAN PRODUKSI DAN PEMASANGAN DINDING PRECAST PADA PROYEK APARTEMEN STUDI KASUS PEKERJAAN PRODUKSI DAN PEMASANGAN DINDING PRECAST PADA PROYEK APARTEMEN Andree Surya Salim 1, Lukito Kaswara 2, Andi 3 ABSTRAK : Kesuksesan suatu proyek konstruksi dipengaruhi oleh beberapa

Lebih terperinci

BAB XIV PEKERJAAN KONSTRUKSI ATAP

BAB XIV PEKERJAAN KONSTRUKSI ATAP BAB XIV PEKERJAAN KONSTRUKSI ATAP Pasal 1 : Kuda-Kuda Rangka Baja Ringan 1. Bentuk kuda-kuda baja ringan baik bentang, tinggi dan kemiringanya sesuai dengan Gambar Bestek. 2. Kuda-kuda dirakit/dipasang

Lebih terperinci

LAMPIRAN 1 PERAN ENERGI DALAM ARSITEKTUR

LAMPIRAN 1 PERAN ENERGI DALAM ARSITEKTUR LAMPIRAN 1 PERAN ENERGI DALAM ARSITEKTUR Prasato Satwiko. Arsitektur Sadar Energi tahun 2005 Dengan memfokuskan permasalahan, strategi penataan energi bangunan dapat dikembangkan dengan lebih terarah.strategi

Lebih terperinci

ANALISIS PRODUKTIVITAS TENAGA KERJA PADA PELAKSANAAN PEKERJAAN KONSTRUKSI RANGKA ATAP BAJA RINGAN PADA PERUMAHAN DI KALIMANTAN SELATAN

ANALISIS PRODUKTIVITAS TENAGA KERJA PADA PELAKSANAAN PEKERJAAN KONSTRUKSI RANGKA ATAP BAJA RINGAN PADA PERUMAHAN DI KALIMANTAN SELATAN ANALISIS PRODUKTIVITAS TENAGA KERJA PADA PELAKSANAAN PEKERJAAN KONSTRUKSI RANGKA ATAP BAJA RINGAN PADA PERUMAHAN DI KALIMANTAN SELATAN Noor Irwansyah dan Yuslan Irianie ANALISIS PRODUKTIVITAS TENAGA KERJA

Lebih terperinci

BAB V KESIMPULAN DAN SARAN

BAB V KESIMPULAN DAN SARAN BAB V KESIMPULAN DAN SARAN 5.1 Kesimpulan Berdasarkan data dan analisis data yang dilakukan maka dapat di tarik kesimpulan: 1) Berdasarkan hasil identifikasi, terdapat 15 (lima belas) faktor penyebab terjadinya

Lebih terperinci

PROFIL PERMUKAAN TANAH KERAS KOTA SURAKARTA SEBAGAI INFORMASI PRADESAIN PONDASI

PROFIL PERMUKAAN TANAH KERAS KOTA SURAKARTA SEBAGAI INFORMASI PRADESAIN PONDASI PROFIL PERMUKAAN TANAH KERAS KOTA SURAKARTA SEBAGAI INFORMASI PRADESAIN PONDASI Reza Satria Warman 1), Yusep Muslih Purwana 2), Noegroho Djarwanti 3) 1) Soil Mechanics Laboratory, Program Studi Teknik

Lebih terperinci

DAMPAK TEKNOLOGI MULSA PLASTIK TERHADAP PRODUKSI DAN PENDAPATAN PETANI TOMAT

DAMPAK TEKNOLOGI MULSA PLASTIK TERHADAP PRODUKSI DAN PENDAPATAN PETANI TOMAT EPP.Vo. 7. No 1. 2010 : 14-19 14 DAMPAK TEKNOLOGI MULSA PLASTIK TERHADAP PRODUKSI DAN PENDAPATAN PETANI TOMAT (Lycopersicum Esculentum L. Mill) DI DESA BANGUNREJO KECAMATAN TENGGARONG SEBERANG KABUPATEN

Lebih terperinci

PERBANDINGAN PRODUKTIVITAS ALAT HYDRAULIC HAMMER DAN JACK IN PILE DI SURABAYA

PERBANDINGAN PRODUKTIVITAS ALAT HYDRAULIC HAMMER DAN JACK IN PILE DI SURABAYA PERBANDINGAN PRODUKTIVITAS ALAT HYDRAULIC HAMMER DAN JACK IN PILE DI SURABAYA Risanto Tedjokusumo 1, Verryanto Goenawan 2, Paravita S. Wulandari 3, dan Jonathan Hendra Kusuma 4 ABSTRAK : Pelaksanaan pemancangan

Lebih terperinci

ANALISA KOEFISIEN PRODUKTIVITAS TENAGA KERJA PADA PEKERJAAN PEMBESIAN. Khubab Basari, Rendra Yoga Pradipta, Jati Utomo Dwi Hatmoko *), Arif Hidayat *)

ANALISA KOEFISIEN PRODUKTIVITAS TENAGA KERJA PADA PEKERJAAN PEMBESIAN. Khubab Basari, Rendra Yoga Pradipta, Jati Utomo Dwi Hatmoko *), Arif Hidayat *) JURNAL KARYA TEKNIK SIPIL, Volume 3, Nomor 4, Tahun 2014, Halaman 830 JURNAL KARYA TEKNIK SIPIL, Volume 3, Nomor 4, Tahun 2014, Halaman 830 839 Online di: http://ejournal-s1.undip.ac.id/index.php/jkts

Lebih terperinci

Perhitungan dan Upaya Peningkatan Output Rate di PT. X

Perhitungan dan Upaya Peningkatan Output Rate di PT. X Perhitungan dan Upaya Peningkatan Output Rate di PT. X Gary Limanto Soegiarto 1, Liem Yenny Bendatu 2 Abstract: PT. X hasn t yet measured output rate in production process, so company would like to measure

Lebih terperinci

Prosiding Matematika ISSN:

Prosiding Matematika ISSN: Prosiding Matematika ISSN: 2460-6464 Analisis Elastisitas Substitusi Tenaga Kerja Dan Modal Suatu Fungsi Produksi Constant Elasticity Of Substitution Analysis Elasticity of Substitution Labor and Capital

Lebih terperinci

Tesis Magister. Oleh : Gama Putranto NIM : Pembimbing : DR. Ir. Krishna S. Pribadi

Tesis Magister. Oleh : Gama Putranto NIM : Pembimbing : DR. Ir. Krishna S. Pribadi IDENTIFIKASI PENGELOLAAN LIMBAH KONSTRUKSI DALAM PROYEK KONSTRUKSI DI INDONESIA SEBAGAI DASAR BAGI PENGEMBANGAN MODEL PROSEDUR PENGELOLAAN LIMBAH KONSTRUKSI Tesis Magister Oleh : Gama Putranto NIM : 25000018

Lebih terperinci

BAB 1 PENDAHULUAN Latar Belakang Isi Laporan

BAB 1 PENDAHULUAN Latar Belakang Isi Laporan BAB 1 PENDAHULUAN 1.1. Latar Belakang Dengan semakin pesatnya perkembangan dunia teknik sipil di Indonesia saat ini menuntut terciptanya sumber daya manusia yang dapat mendukung dalam bidang tersebut.

Lebih terperinci

EVALUASI PRODUKTIVITAS KERJA STRUKTUR KOLOM, BALOK, DAN PLAT DI PROYEK TUNJUNGAN PLAZA 6

EVALUASI PRODUKTIVITAS KERJA STRUKTUR KOLOM, BALOK, DAN PLAT DI PROYEK TUNJUNGAN PLAZA 6 EVALUASI PRODUKTIVITAS KERJA STRUKTUR KOLOM, BALOK, DAN PLAT DI PROYEK TUNJUNGAN PLAZA 6 Benaya A. S. Turangan, Andrew D. Saputra 2, Sentosa Limanto 3, Yusuf D. E. Wicaksono 4 ABSTRAK: Berkembangnya zaman

Lebih terperinci

ABSTRACT. Keywords: Traditional Methods, Cost Centre, Just In Time methods, Inventory. Universitas Kristen Maranatha

ABSTRACT. Keywords: Traditional Methods, Cost Centre, Just In Time methods, Inventory. Universitas Kristen Maranatha ABSTRACT The production process is a very important activity in the manufacturing company. production function is a cost center that will determine the amount or size of production costs and affect the

Lebih terperinci

TUGAS AKHIR ANALISIS PRODUKTIVITAS PEKERJAAN STRUKTUR LANTAI KONVENSIONAL DAN HOLLOW CORE FLOOR PANEL (HCFP)

TUGAS AKHIR ANALISIS PRODUKTIVITAS PEKERJAAN STRUKTUR LANTAI KONVENSIONAL DAN HOLLOW CORE FLOOR PANEL (HCFP) TUGAS AKHIR ANALISIS PRODUKTIVITAS PEKERJAAN STRUKTUR LANTAI KONVENSIONAL DAN HOLLOW CORE FLOOR PANEL (HCFP) PADA PROYEK GEDUNG PAINTING PT ASTRA HONDA MOTOR PLANT KARAWANG Diajukan sebagai syarat untuk

Lebih terperinci

PERBANDINGAN PRODUKTIVITAS PEKERJAAN PASANGAN DINDING BATA RINGAN DAN BATA MERAH PADA PROYEK PERUMAHAN DI SURABAYA

PERBANDINGAN PRODUKTIVITAS PEKERJAAN PASANGAN DINDING BATA RINGAN DAN BATA MERAH PADA PROYEK PERUMAHAN DI SURABAYA PERBANDINGAN PRODUKTIVITAS PEKERJAAN PASANGAN DINDING BATA RINGAN DAN BATA MERAH PADA PROYEK PERUMAHAN DI SURABAYA Evan 1, Henry 2, Sentosa Limanto 3, Jonathan Hendra Kusuma 4 ABSTRAK : Dengan semakin

Lebih terperinci

TUGAS SARJANA. Disusun oleh : HASAN L2E

TUGAS SARJANA. Disusun oleh : HASAN L2E TUGAS SARJANA PENGARUH PENAMBAHAN LIMBAH ABU BATUBARA TERHADAP KONDUKTIVITAS THERMAL, KUAT LENTUR, MASSA JENIS DAN BIAYA PEMBUATAN GENTENG DI INDUSTRI GENTENG KARANGASEM WIROSARI KABUPATEN GROBOGAN Diajukan

Lebih terperinci

ERYANA PURNAWAN Program Studi Akuntansi Fakultas Ekonomi Universitas Siliwangi

ERYANA PURNAWAN Program Studi Akuntansi Fakultas Ekonomi Universitas Siliwangi ANALISIS BIAYA TENAGA KERJA LANGSUNG DAN PRODUKTIVITAS TENAGA KERJA BAGIAN PRODUKSI TERHADAP PROFITABILITAS PERUSAHAAN (Studi Kasus Pada CV. Deden Batik Tasikmalaya) ERYANA PURNAWAN Program Studi Akuntansi

Lebih terperinci

Jalan Perpustakaan Kampus USU, Medan ABSTRAK

Jalan Perpustakaan Kampus USU, Medan ABSTRAK ANALISIS PERBANDINGAN KOEFISIEN HARGA SATUAN PEKERJAAN BERDASARKAN KONDISI AKTUAL, SNI, AHSP, DAN ANALISA K (STUDI KASUS: PROYEK PEMBANGUNAN DRAINASE SALURAN LIMBAH TPA TERJUN MARELAN MEDAN) ANALYSIS OF

Lebih terperinci

BAB I PENDAHULUAN BAB I-1

BAB I PENDAHULUAN BAB I-1 BAB I PENDAHULUAN 1.1 Latar Belakang Proyek adalah suatu rangkaian kegiatan yang dikerjakan dalam waktu terbatas menggunakan sumber daya tertentu dengan harapan untuk memperoleh hasil yang terbaik pada

Lebih terperinci

SISTEM INFORMASI MANAJEMEN BAHAN PADA PROYEK KONSTRUKSI PERUMAHAN SETRADUTA ABSTRAK

SISTEM INFORMASI MANAJEMEN BAHAN PADA PROYEK KONSTRUKSI PERUMAHAN SETRADUTA ABSTRAK SISTEM INFORMASI MANAJEMEN BAHAN PADA PROYEK KONSTRUKSI PERUMAHAN SETRADUTA Disusun oleh : Aureline Dibimbing oleh : Ir. Maksum Tanubrata, M.T. Radiant Victor Imbar, S.Kom., M.T. ABSTRAK Manajemen bahan

Lebih terperinci

PEMILIHAN MODA TRANSPORTASI MAHASISWA FAKULTAS TEKNIK UNS UNTUK MENDUKUNG PROGRAM GREEN CAMPUS

PEMILIHAN MODA TRANSPORTASI MAHASISWA FAKULTAS TEKNIK UNS UNTUK MENDUKUNG PROGRAM GREEN CAMPUS PEMILIHAN MODA TRANSPORTASI MAHASISWA FAKULTAS TEKNIK UNS UNTUK MENDUKUNG PROGRAM GREEN CAMPUS MODA TRANSPORTATION CHOICE OF ENGINEERING FACULTY UNS STUDENT TO SUPPORT GREEN CAMPUS PROGRAM Diajukan Sebagai

Lebih terperinci

KONSTRUKSI ATAP 12.1 Menggambar Denah dan Rencana Rangka atap

KONSTRUKSI ATAP 12.1 Menggambar Denah dan Rencana Rangka atap KONSTRUKSI ATAP 12.1 Menggambar Denah dan Rencana Rangka atap Gambar 12.1 Rencana Atap Rumah Tinggal 12.2 Menggambar Ditail Potongan Kuda-kuda dan Setengah Kuda- Kuda Gambar 12.2 Potongan Kuda-kuda dan

Lebih terperinci

PERENCANAAN METODE PELAKSANAAN STRUKTUR BASEMENT PADA PEMBANGUNAN SEMINYAK HOTEL DEVELOPMENT

PERENCANAAN METODE PELAKSANAAN STRUKTUR BASEMENT PADA PEMBANGUNAN SEMINYAK HOTEL DEVELOPMENT PERENCANAAN METODE PELAKSANAAN STRUKTUR BASEMENT PADA PEMBANGUNAN SEMINYAK HOTEL DEVELOPMENT I Gede Arya Kusmawan 1), I Ketut Nuja S. 2), I Wayan Jawat 2) 1) Mahasiswa Program S1 Teknik Sipil Universitas

Lebih terperinci

PENGARUH ASPEK PELAKSANAAN KONSTRUKSI TERHADAP KINERJA BIAYA DAN WAKTU PROYEK (STUDI KASUS DI DINAS CIPTA KARYA DAN TATA RUANG PROVINSI JAWA-TENGAH)

PENGARUH ASPEK PELAKSANAAN KONSTRUKSI TERHADAP KINERJA BIAYA DAN WAKTU PROYEK (STUDI KASUS DI DINAS CIPTA KARYA DAN TATA RUANG PROVINSI JAWA-TENGAH) PENGARUH ASPEK PELAKSANAAN KONSTRUKSI TERHADAP KINERJA BIAYA DAN WAKTU PROYEK (STUDI KASUS DI DINAS CIPTA KARYA DAN TATA RUANG PROVINSI JAWA-TENGAH) TESIS Disusun Dalam Rangka Memenuhi Salah Satu Persyaratan

Lebih terperinci

STUDI AWAL KEBUTUHAN MATERIAL BATA PADA PROYEK PERUMAHAN YANG BERWAWASAN LINGKUNGAN

STUDI AWAL KEBUTUHAN MATERIAL BATA PADA PROYEK PERUMAHAN YANG BERWAWASAN LINGKUNGAN STUDI AWAL KEBUTUHAN MATERIAL BATA PADA PROYEK PERUMAHAN YANG BERWAWASAN LINGKUNGAN Sentosa Limanto Jurusan Teknik Sipil, Fakultas Teknik, Universitas Kristen Petra Surabaya Jl. Siwalankerto I/121-131

Lebih terperinci

BAB I PENDAHULUAN. Ada beberapa hal yang menyebabkan banyaknya bangunan tinggi diberbagai

BAB I PENDAHULUAN. Ada beberapa hal yang menyebabkan banyaknya bangunan tinggi diberbagai BAB I PENDAHULUAN 1.1. Latar Belakang Ada beberapa hal yang menyebabkan banyaknya bangunan tinggi diberbagai kota besar di dunia, diantaranya adalah akibat bertambahnya permintaan dan meningkatnya kebutuhan

Lebih terperinci

IDENTIFIKASI DAN KAJIAN TERHADAP FAKTOR-FAKTOR PENENTU KEPUASAN KERJA PADA BERBAGAI TINGKATAN PEKERJA PERUSAHAAN KONTRAKTOR TESIS MAGISTER

IDENTIFIKASI DAN KAJIAN TERHADAP FAKTOR-FAKTOR PENENTU KEPUASAN KERJA PADA BERBAGAI TINGKATAN PEKERJA PERUSAHAAN KONTRAKTOR TESIS MAGISTER IDENTIFIKASI DAN KAJIAN TERHADAP FAKTOR-FAKTOR PENENTU KEPUASAN KERJA PADA BERBAGAI TINGKATAN PEKERJA PERUSAHAAN KONTRAKTOR TESIS MAGISTER OLEH : HESTIYANI NIM : 25099048 PROGRAM PASCASARJANA PROGRAM STUDI

Lebih terperinci

1- PENDAHULUAN. Baja Sebagai Bahan Bangunan

1- PENDAHULUAN. Baja Sebagai Bahan Bangunan 1- PENDAHULUAN Baja Sebagai Bahan Bangunan Sejak permulaan sejarah, manusia telah berusaha mencari bahan yang tepat untuk membangun tempat tinggalnya, jembatan untuk menyeberangi sungai dan membuat peralatan-peralatan

Lebih terperinci

struktur. Pertimbangan utama adalah fungsi dari struktur itu nantinya.

struktur. Pertimbangan utama adalah fungsi dari struktur itu nantinya. BAB II TINJAUAN PUSTAKA 2.1 Pendahuluan Pekerjaan struktur secara umum dilaksanakan melalui 3 (tiga) tahap {senol utku, Charles, John Benson, 1977). yaitu : 1. Tahap Perencanaan (Planning phase) Meliputi

Lebih terperinci

PERCEPATAN TIME SCHEDULE PROYEK PEMBANGUNAN GEDUNG DEKANAT FAKULTAS TEKNIK UNIVERSITAS JEMBER DENGAN METODE CUT AND CRASHING

PERCEPATAN TIME SCHEDULE PROYEK PEMBANGUNAN GEDUNG DEKANAT FAKULTAS TEKNIK UNIVERSITAS JEMBER DENGAN METODE CUT AND CRASHING PERCEPATAN TIME SCHEDULE PROYEK PEMBANGUNAN GEDUNG DEKANAT FAKULTAS TEKNIK UNIVERSITAS JEMBER DENGAN METODE CUT AND CRASHING SKRIPSI Oleh Novine Maharstuti NIM 091910301089 JURUSAN TEKNIK SIPIL FAKULTAS

Lebih terperinci

TUGAS AKHIR ANALISIS PERCEPATAN PELAKSANAAN PADA PROYEK KONSTRUKSI BANGUNAN GEDUNG

TUGAS AKHIR ANALISIS PERCEPATAN PELAKSANAAN PADA PROYEK KONSTRUKSI BANGUNAN GEDUNG ii TUGAS AKHIR ANALISIS PERCEPATAN PELAKSANAAN PADA PROYEK KONSTRUKSI BANGUNAN GEDUNG ANALYSIS OF ACCELERATION CONSTRUCTION ON THE BUILDING CONSTRUCTION PROJECT Disusun oleh RIVA I FIBRIYANTO 11511183

Lebih terperinci